View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Corrigendum for tender document. |
| Field Name | Old Value | New Value |
|---|---|---|
| PCC--A. General-- |
The Procuring Entity is |
The Procuring Entity is Chief Engineer (East), Bangladesh Railway, CRB, Chattogram. |
| PCC--A. General-- |
The Project Manager is |
The Project Manager is: Divisional Engineer-1, Bangladesh Railway, Pahartoli, Chattogram. |
| PCC--A. General-- |
The Site is located at [location] and is defined in drawings No: |
The Site is located at holasahar (SLHR) and is defined in drawings No: As per approved drawing. |
| PCC--A. General-- |
The Works consist of |
The Works consist of At Sholasahar (SLHR): Raising of Sholasahar Station Approach road & parking area including construction drain with slab and other allied works. |
| PCC--A. General-- | Other documents forming part of the Contract are;
[list other documents viz. Site Investigation Reports, relevant correspondences prior to signing of the Contract agreement etc.] |
Other documents forming part of the Contract are; N/A |
| PCC--A. General-- | Possession of the Site to the Contractor shall be given on the following date;
[state date of possession of site] |
Possession of the Site to the Contractor shall be given on the following date; within 07 (Seven) days after signing of the contract or the actual date when the site is handed over to contractor by DEN which happened later on. |
| PCC--B. Time Control-- |
The Start Date shall be [insert date ] |
The Start Date shall be within 7 (Seven) days after signing of Contract Agreement or the commencement date of works declared by DEN which happened later on. |
| PCC--B. Time Control-- |
The Intended Completion Date for the whole of the Works shall be [insert date] |
The Intended Completion Date for the whole of the Works shall be 04 (Four) Months after signing of Contract Agreement or the commencement date of works declared by Project Manager. |
| PCC--B. Time Control-- |
The Contractor shall submit a Programme for the Works within [insert days] days of signing the Contract. |
The Contractor shall submit a Programme for the Works within 15(Fifteen) days of signing of the Contract agreement and the interval of submitting updated programme of works shall be 01 (One) months. If the contractor failed to submit programme of works then TK. 25 (Twenty Five) Thousand may be withheld in each progressive payment. |
| PCC--C. Quality Control-- |
The Defects Liability Period is [state months] |
The Defects Liability Period is twelve (12) months. |
| PCC--D. Cost Control-- |
The following additional events shall also be the Compensation Events: |
The following additional events shall also be the Compensation Events: None |
| PCC--D. Cost Control-- | The proportion of payments to be retained is [insert percent] percent. |
The proportion of payments to be retained is: 10 (Ten) percent of the contract price of which,
a) 5% of the total contract price Pay order/Bank gurantee will be submitted by the successfull bidder as performance security.
b) 5% will be retained as retention money from each progressive payment.
(After successfull completion of the whole works 5% performance security will be refunded to the contractor) |
| PCC--D. Cost Control-- |
The amount of Liquidated Damages or in other words Delay Damages is [insert percentage] percent of final Contract price of the uncompleted Works or any part there of it’s per day of delay. |
The amount of Liquidated Damages or in other words Delay Damages is 0.10 of ONE (1) percent of final Contract price of the uncompleted Works or any part there of it’s per day of delay. |
| PCC--D. Cost Control-- |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works. |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is ten (10) percent of the final Contract price of the whole of the Works. |
| PCC--F. Termination-- | The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted Works, is [state percentage] percent.
[ usually between ten (10) to twenty (20) percent depending on the nature of the Works] |
The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted Works, is ten (10) percent.
(Noted that cost of incompleted works will be official estimated cost + % of quoted rate ( above of Estimated Cost only, if applicable). |
| PCC--H. Disputes and Settlement-- |
The arbitration shall be conducted in the place mentioned below; |
The arbitration shall be conducted in the place mentioned below; [Railbhaban,16,Abdul Gani Road, Dhaka, Bangladesh ] |
| TDS/PDS--B. Tender Document-- | Allowed to post clarification till 28-July-2021 12:00 PM |
Allowed to post clarification till 28-July-2021 12:30 PM |
| TDS/PDS--C. Qualification Criteria-- | The required average annual construction turnover shall be greater than Tk. 33.00 (Thirty Three ) lakh over the best 03 (Three) years of the last 05(Five) years. |
The required average annual construction turnover shall be greater than Tk. 33.00 (Thirty Three ) lakh over the best 03 (Three) years of the last 05(Five) years. |
| TDS/PDS--C. Qualification Criteria-- | The minimum amount of credit facilities of the Tenderer shall be Tk. 18.00 (Eighteen) lakh shall be submitted as per standard document prescribe form Letter of Commitment for Bank’s Undertaking for Line of Credit (Form PW2a-3). |
The minimum amount of credit facilities of the Tenderer shall be Tk. 18.00 (Eighteen) lakh shall be submitted as per standard document prescribe form Letter of Commitment for Bank’s Undertaking for Line of Credit (Form PW2a-3). |
| TDS/PDS--C. Qualification Criteria-- | The minimum tender capacity shall be: TK. 26.00 (Twenty Six) Lakh. [Attach the minimum tender capacity calculation sheet and year wise turnover]
Where
For Tenders where the package contains more than one (1) Lot, this qualification requirement shall be mentioned separately for each lot in the package |
The minimum tender capacity shall be: TK. 26.00 (Twenty Six) Lakh. [Attach the minimum tender capacity calculation sheet and year wise turnover]
Where
For Tenders where the package contains more than one (1) Lot, this qualification requirement shall be mentioned separately for each lot in the package |
| TDS/PDS--C. Qualification Criteria-- | A satisfactory completed or substantialy completed whose billed amount or executed quantity of similar works of at least Tk. 18.00 (Eighteen) lakh under 01 (one) number of contract or part of contract over the last 05 (Five) years shall be required. [Years counting backward from the date of publication of IFT in the newspaper.]
[ Here Similar works means construction/re - construction/ repair of any civil works successfully completed in a single contract or part of contract under Govt./Semi Govt./Autonomous Authority in a single contract or part of contract] |
A satisfactory completed / substantialy completed whose billed amount or executed quantity of similar works of at least Tk. 18.00 (Eighteen) lakh under 01 (one) number of contract or part of contract over the last 05 (Five) years shall be required. [Years counting backward from the date of publication of IFT in the newspaper.]
[ Here Similar works means construction/re - construction/ repair of any civil works successfully completed /Substantially completed in a single contract or part of contract under Govt./Semi Govt./Autonomous Authority in a single contract or part of contract] |
| TDS/PDS--D. Tender Preparation-- | Tenderer shall submit with its Tender, the following additional documents:
1. Updated copy of latest Income Tax clearance certificate.
3. Updated copy of Trade Licence.
5. Declaration of ownership of necessary construction Equipment.
6. Declaration of necessary Manpower for implementation of works. |
Tenderer shall submit with its Tender, the following additional documents:
1. Updated copy of latest Income Tax clearance certificate.
3. Updated copy of Trade Licence.
5. Declaration of ownership of necessary construction Equipment.
6. Declaration of necessary Manpower for implementation of works. |
| TDS/PDS--D. Tender Preparation-- | The Tender Validity period shall be 120 (One hundred twenty) days. |
The Tender Validity period shall be 120 (One hundred twenty) days. |
| TDS/PDS--D. Tender Preparation-- | The amount of the Tender Security shall be Tk. 84,000.00 (Eighty Four Thousand) Shall be submitted to FA& CAO(East), Bangladesh Railway, CRB, Chittagong. |
The amount of the Tender Security shall be Tk. 84,000.00 (Eighty Four Thousand) Shall be submitted to FA& CAO(East), Bangladesh Railway, CRB, Chittagong. |
| TDS/PDS--E. e-Tender Submission-- | The deadline for lodgment of e-Tenders is 28-July-2021 12:00 PM |
The deadline for lodgment of e-Tenders is 28-July-2021 12:30 PM |
| Amendment / Corrigendum/ Addendum No. : | 1 | ||||
| S. No. | File Name | File Description | File Size (in KB) |
||
|---|---|---|---|---|---|
| 1 | Section-9.doc | Drawing | 127536 | ||
| 2 | Section-7.doc | General Specification | 136646 | ||
| 3 | Section-8.doc | Particular Specifications | 188492 | ||
| 4 | Bituminous Materials.pdf | bituminus | 35744 | ||