As per TDS
** It is to be noted that quoted boring rate should be increased proportionately according to the depth of the well otherwise tender would be consider non-responsive without acceptable clarification.
** No payment (running / final bill) can be paid against a water point which is installed in a depth, 10% lower than the average depth mentioned in the approved official estimate or BOQ of contract document.
** If the tubewell is installed at greater depth than the average depth of the well, extra depth bills will be paid for additional portion work done according to quoted rate by the contractor or approved estimate. In this case, lower unit rate will be followed between them.
Construction of Community Based Water Supply scheme by installing 100mm x 50mm dia tubewell with 1.5 hp Submersible Pump in Patuakhali District under Project for Safe Water Supply Throughout the Country of DPHE during the FY 2021-2022