View IFT /PQ / REOI / RFP / PPS Notice Details
Ministry : Ministry of Local Government, Rural Development and Co-operatives Division : Local Government Division
Organization : Sylhet City Corporation Procuring Entity Name : Office of the Executive Engineer (Civil), Sylhet City Corporation.
Procuring Entity Code : Procuring Entity District : Sylhet
Procurement Nature : Works Procurement Type : NCT
Event Type : Invitation for : Tender - Single Lot
Invitation Reference No. : 46.07.0000.018.14.093.21.352 Tender/Proposal Status :
App ID : 176841 Tender/Proposal ID : 607491
Key Information and Funding Information :
Procurement Method : Open Tendering Method (OTM) Budget Type : Development
Source of Funds : Government
Particular Information :
Project Code : Infrastructure on SCC Project Name : Construction of Infrastructure in Sylhet City Corporation.
Tender/Proposal Package No. and Description : 46.07.0000.018.14.093.21
Construction of Road by Asphalt at Naiorpool point to Tilagor Kani Chara.
Category : Construction work;Site preparation work;Building demolition and wrecking work and earthmoving work;Test drilling and boring work;Works for complete or part construction and civil engineering work;Building construction work;Engineering works and construction works;Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork;Construction work for water projects;Construction works for plants, mining and manufacturing and for buildings relating to the oil and gas industry;Roof works and other special trade construction works;Building installation work;Electrical installation work;Insulation work;Plumbing and sanitary works;Fencing, railing and safety equipment installation work;Mechanical installations;Building completion work;Plastering work;Joinery and carpentry installation work;Floor and wall covering work;Painting and glazing work;Other building completion work;Hire of construction and civil engineering machinery and equipment with operator;Hire of cranes with operator;Hire of earthmoving equipment with operator
Scheduled Tender/Proposal Publication
Date and Time :
09-Sep-2021 10:00 Tender/Proposal Document last selling /
downloading Date and Time :
03-Oct-2021 17:00
Pre - Tender/Proposal meeting Start
Date and Time :
09-Sep-2021 20:00 Pre - Tender/Proposal meeting End
Date and Time :
27-Sep-2021 17:00
Tender/Proposal Closing
Date and Time :
04-Oct-2021 15:00 Tender/Proposal Opening
Date and Time :
04-Oct-2021 15:00
Last Date and Time for Tender/Proposal Security
Submission :
04-Oct-2021 12:00    
Information for Tenderer/Consultant :
Eligibility of Tenderer :

As per Tender Data Sheet (TDS)
N:B: The tenderer must follow the following instruction before submitting the tender.
1. The certificates submitted by the tenderer in proof of Specific Experience / AACT must be as per the standard format attached/uploaded in Particular Specification Section. Certificate other than the specified format must contain the information like (particulars of PE in/c e-mail & contact no, business shares in case of JV, time extension, liquidity damage, contract & final bill amount etc.). A tenderer failing to submit that will be considered as “Non-responsive” during evaluation.
2. Tenderer must be Upload Tender Capacity paper (for proof of Tender Capacity as per the standard format attached/uploaded in Particular Specification Section). A tenderer failing to submit that will be considered as “Non-responsive” during evaluation.
3. In the case of liquid asset, certificate and statement from bank should be submitted, issued not earlier than the date of publication of IFT Notice in the e-GP Website.
4. In the case of credit facilities, it should be sanctioned and must be submitted as per the format for the Credit Line (Form PW3-7) issued by any scheduled Bank of Bangladesh in accordance with ITT Clause without alteration, issued not earlier than the date of publication of IFT Notice in the e-GP Website.
5. If a tenderer wants to qualify more than one package, each package shall be qualified separately for Liquid asset & Tender Capacity

6. If tenderer submits any fake certificate, action will be taken to debarment of the organization.

Brief Description of Works :

Construction of Road by Asphalt at Naiorpool point to Tilagor Kani Chara.

Evaluation Type : Lot wise
Document Available : Package wise
Document Fees : Package wise
Tender/Proposal Document Price (In BDT) : 4000
Mode of Payment :
Tender/Proposal Security Valid Up to : 01-Mar-2022
Tender/Proposal Valid Up to : 01-Feb-2022
Lot No. Identification of Lot Location Tender/Proposal security
(Amount in BDT)
Tentative Start Date Tentative Completion Date
01 Construction of Road by Asphalt at Naiorpool point to Tilagor Kani Chara. Sylhet City Corporation Area 1100000 01-Nov-2021 01-Mar-2022
Procuring Entity Details:
Name of Official Inviting Tender/Proposal : Engr. Md. Ali Akbar Designation of Official Inviting Tender/Proposal : Executive Engineer
Address of Official Inviting Tender/Proposal :
Address: Sylhet City Corporation, Sylhet.
City: Sylhet
Thana: Sadar, Sylhet.
District: Sylhet - 3100
Country: Bangladesh
Contact details of Official Inviting Tender/Proposal :
Phone No: 0821-714036
Fax No:
The procuring entity reserves the right to accept or reject all Tenders/Proposals / Pre-Qualifications / EOIs
Note: Bank will update the payment transactions only at the end of the day, so the tenderers should make sure the securities and other payments are made at least one day before the submission date.
Documents
Amendment / Corrigendum Detail
 Amendment / Corrigendum No. :  1 
Amendment / Corrigendum Text :

Correction.

Field Name Old Value New Value
PCC--A. General--

The Site is located at [location] and is defined in drawings No: 
[insert numbers]
 

The Site is located at Sylhet City Corporation area and is defined in the site plan/master plan.

PCC--A. General--

The Start Date shall be  [insert date ]

[it is the last date when the Contractor shall commence execution of  the Works under the Contract reasonably immediately after the Commencement Date; refer to GCC  Clause 40]
 

The Start Date shall be within 7 (seven) days of Signing of Contract Agreement.

PCC--A. General--

The PE is
[Name, address, and name of authorized representative]
 

The Intended Completion Date for the whole of the Works shall be “Commencement Date + 120 Days”

PCC--A. General--

The original Contract price is [insert the amount in the NOA]

The original Contract price is...................

PCC--A. General--

The Contractor is
[Name, address, and name of authorized representative]
 

The Contractor is :........................................................

PCC--A. General--

The Works consist of

[state brief summary, including relationship to other Contracts under the Project]

The Works consist of Asphalt work.

PCC--A. General--

The Project Manager is
[Name, address, and name of authorized representative]
 

The Project Manager is related Assistant Engineer, Sylhet City Corporation.

PCC--A. General--

The PE is
[Name, address, and name of authorized representative]

 

The Development Partner is [Name of the DP]

The PE is
Engr. Md. Ali Akbar

Executive Engineer

Sylhet City Corporation.

The Development Partner is N/A

PCC--A. General--

Possession of the Site or part(s) of the Site, to the Contractor shall be given on the following date(s);

[state date or dates  of possession of site] 
 

Possession of the Site or part(s) of the Site, to the Contractor shall be given on the following date(s): Within 7 days of contract signing

PCC--A. General--

Following Key Personnel to carry out the functions stated in the Schedule shall be employed by the Contractor;

[insert name(s)]
 

Following Key Personnel to carry out the functions stated in the Schedule shall be employed by the Contractor; as per TDS Clause 17.1

PCC--A. General--

The Sectional Completion Dates are:

[state part of the works and the corresponding dates, if applicable]
 

The Sectional Completion Dates are: Not Applicable.

PCC--A. General--

Nominated Subcontractor(s)  named below;

____[insert name(s)]___________________________________________
shall be entitled to execute the following specific components of the Works

[state none ,if not applicable]
 

Nominated Subcontractor(s) named below; N/A.

PCC--A. General--

The  Contractual matters between the PE and the Contractor shall be decided by

[state only  if other than the Project Manager]
 

The Contractual matters between the PE and the Contractor shall be decided by: Project Manager and other persons directed by PE

PCC--A. General--

The PE’s address for the purpose of communications under this contract is :
Contact person:
Address:
Tel:
Fax:
e-mail address:


The Contractor’s address for the purpose of communications under this contract is :
Contact person:
Address:
Tel:
Fax:
e-mail address:

The PE’s address for the purpose of communications under this contract is :
Contact person: Executive Engineer
Address: Nagar Bhaban, Sylhet City Corporation.
Tel: 0821-719534
Fax:0821-719336
e-mail address: cescc09@gmail.com


The Contractor’s address for the purpose of communications under this contract is :


Contact person:............................................
Address:......................................................
Tel:...........................................................
Fax:..........................................................
e-mail address:...................................................................

PCC--A. General--

The minimum insurance cover shall be:

(a)

The maximum deductible for insurance of the Works and of Plant and Materials is Tk [state amount]


[the Contractor shall provide this amount at the time of Contract signing].
 

(b)

The minimum cover for insurance of the Works and of Plant and Materials in respect of the Contractor’s faulty design is Tk [state amount].


[the amount could be 110% of the value of the works, plant and materials that may be lost in a worst case scenario].
 

(c)

The maximum deductible for insurance of Equipment is Tk [state amount].


[the Contractor shall provide this amount at the time of Contract signing].
 

(d)

The minimum cover for loss or damage to Equipment is Tk [state amount].


[the amount could be 110% of the replacement value of the equipment]
 

(e)

The maximum deductible for insurance of other property is Tk [state amount].


[the Contractor shall state this amount at the time of Contract signing].
 

(f)

The minimum cover for insurance of other property is Tk [state amount].


[it is the responsibility of the Contractor to obtain adequate insurance cover for such risks – recommended value 10% of contract price].
 

(g)

The minimum cover for personal injury or death insurance:


(i) for the Contractor’s employees is as per the law and common practice in Bangladesh.


(ii) and for third parties is as per the law and common practice in Bangladesh.
 

The minimum insurance cover shall be:

(a) The maximum deductible for insurance of the Works and of Plant and Materials is 5% to 10% of the sum insured


(b) The minimum cover for insurance of the Works and of Plant and Materials in respect of the Contractor’s faulty design is 110% of the value of the works, plant and materials


(c) The maximum deductible for insurance of Equipment is 5% to 10% of the sum insured


(d) The minimum cover for loss or damage to Equipment is 110% of the replacement value of the equipment


(e) The maximum deductible for insurance of other property is 5% to 10% of sum insured


(f) The minimum cover for insurance of other property is 10% of the Contract Price


(g) The minimum cover for personal injury or death insurance:

(i) for the Contractor’s employees is as per the law and common practice in Bangladesh.

(ii) and for third parties is as per the law and common practice in Bangladesh.

PCC--A. General--

Other documents forming part of the Contract are; 

 

[list other documents viz. Schedule of other contractors, Schedule of Key Personnel, Site Investigation Reports, relevant correspondences prior to signing of the Contract agreement etc.]

Other documents forming part of the Contract are;

i. Agreed Technical Proposal;

ii. The Schedule of Key Personnel;

iii. Work program;

iv. Joint Venture Agreement (if applicable);

v. Joint Venture Information Sheet (if applicable);

vi. Insurance;

PCC--A. General--

Materials, Equipments Plants and supplies shall not have their origin in  the following countries:

[state countries, if applicable]
 

Materials, Equipment Plants and supplies shall not have their origin in the following countries: Israel

PCC--A. General--

A Contractor or a Subcontractor  that is a national of, or registered in, the following countries are not eligible:

[state countries, if applicable]
 

A Contractor or a Subcontractor that is a national of, or registered in, the following countries are not eligible: Israel

PCC--B. Time Control--

Commencement Date of Works shall be as follows;

[insert different commencement dates for different parts of the Works, if deemed appropriate]
 

Commencement Date of Works shall be: Contract Signing Date + 7 days

PCC--B. Time Control--

The amount to be withheld for late submission of an updated Programme is [state amount].

The amount to be withheld for late submission of an updated Programme is: N/A.

PCC--B. Time Control--

The period between Programme updates is [state interval]

[usually bi-monthly or quarterly depending on the nature of the Works]
 

The period between Programme updates is one quarter.

PCC--B. Time Control--

The Contractor shall submit a Programme for the Works within [insert days] days of signing the Contract.

[usually fifteen (15) days]
 

The Contractor shall submit a Programme for the Works within 7 (Seven) days of signing the Contract.

The Contractor also shall submit the videos and color photos from various angles to the PE during submission of interim and final bills.

PCC--C. Quality Control--

The Defects Liability Period is [state months]

[usually Defect Liability Period is twelve (12) months to cover at least one complete monsoon season].
 

The Defects Liability Period is: 12 (Twelve) months

PCC--D. Cost Control--

The particulars of the Bank Account nominated are as follows :

Title of the Account : [insert title to whom the Contract awarded]
Name of the Bank : [insert name with code, if any]
Name of the Branch : [insert branch name with code ,if any]
Account Number : [insert number]
Address : [insert location with district]
Tel :
Fax :
e-mail address :

[information furnished by the Contractor shall be substantiated by the concerned Bank and authenticated by the PE]
 

The particulars of the Bank Account nominated are as follows : N/A.

PCC--D. Cost Control--

The following additional events shall also be the Compensation Events:


[list events or state none ]
 

The following additional events shall also be the Compensation Events: None

PCC--D. Cost Control--

The Contract is not subject to price adjustment.
OR
The Contract is subject to price adjustment, the weightings or coefficients for adjustment are:

[Price Adjustment Formulae to be applicable if stated under ITT Sub Clause 27.10 shall be specified here]
Example:
P= A + a (Lm/Lo)+ b (BIm/BIo)+ c (CEm/CEo)+ d (RSm/RSo)+ e (STm/STo)+ f (BRm/BRo)+g (MIm/MIo) + h (FUm/FUo)+ etc
where;
L= Labor, BI=Bitumen, CE=Cement, RS=Reinforcing Steel, ST=Stone, BR=Bricks, MI=Miscellaneous, FU= Fuel ]
Weighting or Coefficient A equals between 0.10 and 0.15 and, B (a+b+c+d+e+f+g+h+etc) equals between 0.90 and 0.85.

[insert figure] non-adjustable component (coefficient A)
[insert figure] adjustable component (coefficient B)
[The sum of A+B shall equal ONE (1). It is usual to have value of A between 0.10 and 0.15 and that of B between 0.90 and 0.85. Breakdown of B shall be provided in Appendix to the Tender.]
[delete as appropriate]

[price adjustment clauses are usually only permitted for Works Contracts, execution of which will take more than eighteen (18) months from Start Date to Completion Date. The PE must consider each Contract on its individual merit; approval of HOPE required for Contracts of less than eighteen (18) months]
 

The Contract is not subject to price adjustment.

PCC--D. Cost Control--

The proportion of payments to be retained is [insert percent] percent.


[state “none’ if not applicable. If applicable then the proportion of Retention Money shall be equal to the percentage-shortfall of ten (10) percent of Performance Security determined at the time of signing the Contract. Again in case of unbalanced Tender or because of front loading, provision for Retention Money shall not be applicable]
 

The proportion of payments to be retained is [10%] percent.

PCC--D. Cost Control--

The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is [insert percentage] percent of its Contract price per day of delay.
[usually the percent-rate of liquidated damages is set at between 0.05 and 0.10 of ONE (1) percent of its Contract price per day of delay]
Guide to application of GCC Sub Clause 76.1 above
[ Liquidated damages is equivalent to an amount to be determined in accordance with the following formula
T LD = VUW x Px n
Where;
T LD = Total amount of Liquidated Damages
VUW = Value of Uncompleted Works (i.e. works not having been completed as of the expiry of the Intended Completion Date plus the works completed after the expiry of the Intended Completion Date). VUW shall be calculated by deducting the value of the completed works under the Contract from the total Contract price
P = Percent-rate at which the Liquidated Damages shall be imposed for every day of delay
n = No of days of delay for completion of works under the Contract]

 

The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works.


[ usually the total amount of liquidated damages shall not exceed ten (10) percent of the final Contract price for the whole of the Works]

 

The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is 0.10 (zero point one zero) percent of its Contract price per day of delay.

The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10 (ten) percent of the final Contract price of the whole of the Works

PCC--D. Cost Control--

The Bonus for the whole of the Works is [insert percentage] percent of the final Contract price per day.

The maximum amount of Bonus for the whole of the Works is [insert percentage] percent of the final Contract price.

[if early completion would provide benefits to the PE, this clause should remain, otherwise state “Not Applicable”. The bonus is usually numerically equal to the Liquidated Damages]
 

The Bonus for the whole of the Works is [insert percentage] percent of the final Contract price per day: Not be applicable.

PCC--D. Cost Control--

The Advance Payment shall be Tk [insert amount] and shall be paid to the Contractor not later than [insert date].

[for 100 percent GoB funded procurement, advance payments are not recommended unless otherwise specifically decided by the Government. An advance payment, if admissible, shall be made for mobilisation, considering the nature of the works. The recommended maximum advance payment is ten (10) percent of the original Contract price against an unconditional Bank Guarantee (Form e-PW3-10.) On the contrary, advance payments may be applicable for procurements under aided projects]
 

The Advance Payment shall not be applicable.

PCC--D. Cost Control--

The percentage for adjustment of Provisional Sums is

____% (_________percent)
[state none, if not applicable. Usually covers the VAT, profit and overhead costs]
 

The percentage for adjustment of Provisional Sums is Not be applicable.

PCC--E. Completion of the Contract--

The date by which “as-built” drawings are required is [insert date]

 

The date by which operating and maintenance manuals are required is [insert date]

The date by which “as-built” drawings are required is N/A.

PCC--E. Completion of the Contract--

The amount to be withheld for failing to produce “as-built” drawings and/or operating and maintenance manuals by the date required is Tk [insert amount]

[usually a very nominal amount]
 

The amount to be withheld for failing to produce “as-built” drawings and/or operating and maintenance manuals by the date required is N/A.

PCC--F. Termination and Settlement of Disputes--

The percentage to apply to the contract value of the works not completed, representing the PE’s additional cost for completing the uncompleted Works, is [state percentage] percent.

[ usually between ten (10) to twenty (20) percent depending on the nature of the Works]
 

The percentage to apply to the contract value of the works not completed, representing the PE’s additional cost for completing the uncompleted Works, is [between ten (10) to twenty (20) percent depending on the nature of the Works] percent.

PCC--G. Claims, Disputes and Arbitration--

The arbitration shall be conducted in the place mentioned below;
[state name of place with location and district ]

The arbitration shall be conducted in the place mentioned below:

Place will be decided by the PE and Contractor during contract signing

PCC--G. Claims, Disputes and Arbitration--

The Adjudicator jointly appointed by the parties is:
Name:
Address:
Tel No:
Fax No:
e-mail address:

 

In case of disagreement between the parties, the Appointing Authority for the Adjudicator is the President of the Institution of Project Managers, Bangladesh. 

The Adjudicator will be jointly appointed by the PE and Contractor during contract signing

TDS/PDS--A. General--

The PE is [state name of PE]

 

The Name of the Tender is:
Brief Description of the Works:

Tender Ref:

Lot No(s):

[if there is more than one(1) lot, individual lots are to be identified in conformity with Section 6: Bill of Quantities]
 

The PE is Engr. Md. Ali Akbar


The Name of the Tender is: Construction of Road by Asphalt at Naiorpool point to Tilagor Kani Chara.

Tender Ref: 46.07.0000.018.14.093.21.352
Lot No(s): 01

TDS/PDS--A. General--

The name of the Development Partner is

[state name of Development Partner]
 

The name of the Development Partner is: Not Applicable

TDS/PDS--A. General--

The source of public funds is

[state source, GoB or other source of funds].
 

The source of public funds is: GOB.

TDS/PDS--A. General--

Tenderers from the following countries are not eligible

[ state countries, if any ]
 

Tenderers from the following countries are not eligible: Israel

TDS/PDS--A. General--

Materials, Equipments and associated services from the following countries are not eligible:

[state countries, if any]
 

Materials, Equipment and associated services from the following countries are not eligible: Israel

TDS/PDS--B. e-Tender Document (e-TD)--

Allowed to post clarification till [Date and Time]

Allowed to post clarification N/A.

TDS/PDS--B. e-Tender Document (e-TD)--

Pre- Tender meeting [Date & Time]

Pre-Tender Meeting date and time for e-GP System: As mentioned in tender Notice

TDS/PDS--B. e-Tender Document (e-TD)--

A Pre-Tender meeting shall not be held
or
A Pre- Tender meeting shall be held through e-GP System

[delete whichever is not applicable]
 

Pre-Tender meeting shall also be held through e-GP System.

TDS/PDS--C. Qualification Criteria--

The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be [state number] years.

[a minimum of three (3) years would be deemed reasonable; years counting backward from the date of publication of IFT in the newspaper]

 

The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least [state number] contract(s) of similar nature, complexity and methods/construction technology successfully completed within the last [state number] years, each with a value of at least Tk. [state amount].

[the minimum number of contracts will depend upon the size and type of construction work, and the PE should make its own judgement based upon its experience in the sector and construction industry. For example, for large works, it could be one (1) contract of similar nature during the last three (3) years or five (5) years or ten (10) years (whichever appropriate); years counting backward from the date of publication of IFT in the newspaper]
 

[for Tenders where the package contains more than one (1) lot, this qualification requirements, only when applicable, shall be mentioned separately for each lot in the package]
[the minimum value of the similar works is recommended to be between 50 and 75 percent of the estimated cost of the proposed work]

 

The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor shall be 05 (Five) years.

NOTE:

1. Years will be counted backward from the date of publication of IFT in the website.

2. The start date of the earliest/First construction works completed satisfactorily under public sector will be considered for calculating the period of general experience. Tenderer shall attach relevant certificate issued by concerned PE.


The minimum specific experience as a Prime Contractor in construction works under public sector shall be at least 01 (One) contract of [Asphalt Work] successfully completed within the last [05 (five)] years with a value of at least [Tk. 2.50 (Crore)]

NOTE:

1. Years will be counted backward from the date of publication of IFT in the website.

2. Tenderers shall attach relevant certificate issued by the Procuring Entity(ies).

TDS/PDS--C. Qualification Criteria--

The required average annual construction turnover shall be greater than Tk [insert amount] over the last [state number] years.

[ the required average annual construction turn over is recommended to be about twice the estimated annual cash flow for the Contract; however the multiplier may vary from 1.0 to 2.0, the larger the Contract size the lesser the multiplier should be. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate) ; years counting backward from the date of publication of IFT in the newspaper]
Example:


Estimated Contract Value: Tk 24 Cr.
Contract period: 18 months
Estimated Annual Cash Flow: Tk 16 Cr.
Required average annual construction turn over: Tk 24 Cr., using a multiplier of 1.5.
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]

  

The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk [state amount]

[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Example:


Contract Value: Tk 24 Cr.
Contract period: 18 months
Assuming work time: 1 month
Invoice period: 0.5 month
Certification Time: 0.5 month
Contingency Time: 1 month

Therefore, the minimum required liquid asset will be Tk 4 Cr., i.e. 3 months cash flow based on the above assumptions.]
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]

 

The required average annual construction turnover shall be greater than Tk: 17,90,00,000/- over the last 05 (Five) years.

NOTE:

1. Years will be counted backward from the date of publication of IFT in the newspaper.

2. Payment received Certificates for construction works, issued by relevant Procuring Entity(ies) will be considered as construction turnover.

3. Tenderers shall submit their information as per Form PW3A-2.1: Turnover Information Form (Attached to Section 8) and attach relevant certificate issued by the Procuring Entity(ies).


The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk: 3,00,00,000/-

NOTE: Tenderers shall submit the liquid asset in one or combination of more than one of the following four options. Please also note that in case of joint venture, Lead and individual partners must submit liquid asset individually :

1. Working capital: authenticated by Audit Report not earlier than FY 2019-20.
2. Credit line: authenticated by any scheduled bank shall be furnished unconditional credit line without alteration in accordance with the format as specified in the Form PW3A-7 (Attached to Section 8).
3. Credit facilities: authenticated by credit sanctioned letter and bank statement of the credit account issued not earlier than 28 days prior to the day of the original deadline for submission of Tenders for this Contract.
4. Bank Balance: authenticated by bank statement with at least one day-end closing balance from any scheduled bank issued not earlier than 28 days prior to the day of the original deadline for submission of Tenders for this Contract.

TDS/PDS--C. Qualification Criteria--

The minimum capacity shall be:[70%-80% of the official estimated cost]
The following formulae shall be used to calculate the Tender Capacity
Assessed Tender Capacity = (A*N*1.5-B)

Where
A=Maximum value of Works performed in any one year during last five years
N= Completion time of the proposed work in years
B= Value of Existing commitments and works to be completed during the next N Years

Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one)
Note 2: In case of JV tender capacity requirement for leading partner shall be minimum 40% and for other partners shall be minimum 25%.
 

The minimum capacity shall be: Tk: 3,00,00,000/-
The following formulae shall be used to calculate the Tender Capacity
Assessed Tender Capacity = (A*N*1.5-B)

Where
A=Maximum value of Works performed in any one year during last five years
N= Completion time of the proposed work in years
B= Value of Existing commitments and works to be completed during the next N Years

Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one)
Note 2: In case of JV tender capacity requirement for leading partner shall be minimum 40% and for other partners shall be minimum 25%.


NOTE:

1. Tenderer shall submit the information for calculating A & B as per form no. PW3A-2.2: Tender Capacity Informaion Form (Attached to Section 8) and attach relevant certificate issued by the Procuring Entity(ies). In case of Zero (0%) percent progress, Tenderers shall submit the copy of NOA or Contract Agreement.

TDS/PDS--C. Qualification Criteria--

A Construction Project Manager, Engineer, and other key staff shall have the following qualifications and experience:

 

No Position Total Works Experience (years) In Similar
Works
Experience
(years)
 
       
       
       
       
       
       

 

 

 

 


 

 

 

 

 

 

 

 

 

 

 

 

[ qualification of an alternative Construction Project Manager may also be requested]
[ for Tenders where the package contains more than one (1) lot, this qualification requirement may be necessary for each lot in the package, subject to the nature of the control required over each package]
 

A Construction Project Manager, Engineer, and other key staff shall have the following qualifications and experience:

 

No Position Total Works Experience (years) In Similar
Works
Experience
(years)
 
01 Construction Project Manager B. Sc. in Civil Engineering or Diploma in Civil Engineering 05 years / 10 years 03 years / 05 years
02 Project Engineer Civil (B.Sc.)-1 Nos. 5 years 3 years
03 Site Engineer (Diploma) -Civil - 2 Nos. 5 years 3 years
04 Surveyor-2 Nos 5 years 5 years
05 Foreman-2 Nos. 5 years 5 years
       

 

 

 

 


 

 

 

 

NOTE:

1. Academic & Experience qualification of the key staff must be supported by Certificates with the Tender.

2. Tenderers shall submit their information as per Form PW3A-2.3: Personnel Information Form (Attached to Section 8) and attach relevant certificates

TDS/PDS--C. Qualification Criteria--

A Construction Project Manager, Engineer, and other key staff shall have the following qualifications and experience:

 

No Position Total Works Experience (years) In Similar
Works
Experience
(years)
 
       
       
       
       
       
       

 

 

 

 


 

 

 

 

 

 

 

 

 

 

 

 

[ qualification of an alternative Construction Project Manager may also be requested]
[ for Tenders where the package contains more than one (1) lot, this qualification requirement may be necessary for each lot in the package, subject to the nature of the control required over each package]
 

A Construction Project Manager, Engineer, and other key staff shall have the following qualifications and experience:

 

No Position Total Works Experience (years) In Similar
Works
Experience
(years)
 
01 Construction Project Manager B. Sc. in Civil Engineering or Diploma in Civil Engineering 05 years / 10 years 03 years / 05 years
02 Project Engineer Civil (B.Sc.)-1 Nos. 5 years 3 years
03 Site Engineer (Diploma) -Civil - 2 Nos. 5 years 3 years
04 Surveyor-2 Nos 5 years 5 years
05 Foreman-2 Nos. 5 years 5 years
       

 

 

 

 


 

 

 

 

NOTE:

1. Academic & Experience qualification of the key staff must be supported by Certificates with the Tender.

2. Tenderers shall submit their information as per Form PW3A-2.3: Personnel Information Form (Attached to Section 8) and attach relevant certificates

TDS/PDS--C. Qualification Criteria--

Tenderer shall own or have proven access to hire or lease of the major construction  equipments, in full working order as follows :

 

No Equipment Type and Characteristics Minimum Number
Required
 
     
     
     
     
     
     

 

 [for Tenders where the package contains more than one (1) lot, this qualification requirement may be necessary  for each lot in the package, subject to the nature of the control required over each package]

Tenderer shall own or have proven access to hire or lease of the major construction  equipments, in full working order as follows :

 

No Equipment Type and Characteristics Minimum Number
Required
 
01 Asphalt Plant 01
     
     
     
     
     

 

NOTE:

1. Ownership, lease or hiring documents must be submitted with the Tender.

2. Tenderers shall submit their information as per Form PW3A-2.4: Equipment Information Form (Attached to Section 8) and attach relevant documents

TDS/PDS--C. Qualification Criteria--

 

TDS Clauses References Requirements by summation Requirements for Lead Partner of JVCA Requirements for other Partner(s) of JVCA
ITT-15.1(a) Summation not applicable Same as stated in TDS Same as for
Leading Partner
 
ITT-15.1(b) 100% At least one Contract Minimum requirement not applicable
ITT-16.1(a) 100% 40% 25%
ITT-16.1(b) 100% 40% 25%
ITT-17.1 100% Minimum requirement not applicable Minimum requirement not applicable
ITT-18.1 100% Minimum requirement not applicable Minimum requirement not applicable

 

The value of non-judicial stamp for execution of the Joint Venture agreement shall be Tk [state amount]
[the value of the non-judicial stamp shall be Tk.300.00]
 

The value of non-judicial stamp for execution of the Joint Venture agreement shall be Tk 300.00 (In Word: Three Hundred only).

The Maximum number of partners in the JV shall be 3 (three).

 

TDS Clauses References Requirements by summation Requirements for Lead Partner of JVCA Requirements for other Partner(s) of JVCA
ITT-15.1(a) Summation not applicable Same as stated in TDS Same as for
Leading Partner
 
ITT-15.1(b) 100% At least one Contract Minimum requirement not applicable
ITT-16.1(a) 100% 40% 25%
ITT-16.1(b) 100% 40% 25%
ITT-16.1(d) 100% 40% 25%
ITT-17.1 100% Minimum requirement not applicable Minimum requirement not applicable
ITT-18.1 100% Minimum requirement not applicable Minimum requirement not applicable
TDS/PDS--C. Qualification Criteria--

The minimum qualification requirements of Leading Partner and other Partner(s) of a JVCA shall be as follows :

[it is suggested that the PE adheres to the above proportion of minimum qualifying requirements to meet the specific procurement needs. Percent share of business of the JVCA partners shall not be taken into account in determining the qualification of a JVCA]
 

The minimum qualification requirements of Leading Partner and other Partner(s) of a JVCA shall be as follows : as per ITT 19.1

NOTE:

1. The documentary evidence of Leading and other partner must be submitted separately; otherwise the tender will be treated as non-responsive.

TDS/PDS--C. Qualification Criteria--

The Nominated Subcontractor(s) named [insert name(s)] shall execute the following specific components of the proposed Works:


[state the components of the proposed works ; if not applicable state ‘none’]
 

The Nominated Subcontractor(s) named [insert name(s)] shall execute the following specific components of the proposed Works: N/A

TDS/PDS--D. Tender Preparation--

The Tenderer shall submit with its Tender the following additional documents:


[in case of purchase of capital equipment by the Contractor as part of the overall Contract, a Performance Statement of the capital equipment in Bangladesh may be necessary and may be requested. if no other documents are required then specify “none”]

 

The Tenderer shall submit with its Tender the following additional documents:

 

Technical proposal as stated under ITT Clause 30.

 

  • ITT 30.1 Technical Proposal must include the following chapters:

a. Statement of work methods:

Tenderer will describe the methodology of the main activities to be performed under the contract. Tenderer should identify the risk and explain the mitigation procedures in technical proposal to address them. The number of labor groups to be engaged to complete the contract within the stipulated time must be described in the technical proposal with use of equipment types. Materials procurement, source, procurement plan, mobilization & Demobilization plan, etc. will be described in the technical proposal.

b. Equipment:

Tenderer will provide the list of equipment (lease or own with proof of documents with source) that will be used if the contract is awarded and its time frame. The statement should be realistic enough that not only satisfy the ITT Clause but also satisfy the equipment schedule (time and activities involved, number of equipment like Asphalt Plant, Rotary-rig, square meter of steel shuttering materials and type, number of batching plant and its capacity, equipment brand and year of manufacture, etc.) for ensuring the progress of the contract as per work plan. Tenderer will mention the brand of the equipment as well as engine number where applicable. The equipment, with detail description, mobilization schedule will be submitted by the tenderer which will be an integral part of the contract. Before submitting the tender, tenderer shall visit the proposed site and submit the construction equipment accessibility plan and also mentioned the mode of construction equipment mobilization.

c. Personnel:

Tenderer will provide the list of experienced personnel which will be available during execution of the contract as specified if awarded. The responsibility and availability of the personnel to execute the contract will be submitted in the proposal. The statement should be realistic enough that not only satisfy the ITT Clause but also satisfy the personnel schedule (time and activities involved) for ensuring the progress of the contract as per work plan. Availability of personnel must confirm before signing the contract. If replacement require procuring entity’s prior approval will be obtained and replaced person must possess equal or higher qualification.

d. Work plan:

Tenderer will provide a work plan in details as well as list all activities/sub activities to be performed under the contract within the given time frame. Please provide the date of every milestone/components also. Only bar chart is not acceptable. In work plan tenderer will describe each activities/sub activities with duration, milestones/components and predecessor & successor actions of every activity. PERT/CPM using MS Project will be more acceptable.

e. Method of ensuring Safety, security, Environmental Measures, avoidance of Health Hazard & using Child Labor etc.:
Tenderer needs to explain the Method of ensuring Safety, security, Environmental Measures, avoiding Health Hazard, Avoidance of using Child Labor etc. Any other statement or documents that tenderer needs to describe the Technical proposal to satisfy his/her proposal may be mentioned in the technical proposal. Any tenderer may be invited to present the technical proposal to TEC/or LGED expert group and Procuring Entity’s comments must be incorporated in final technical proposal which will then be an integral part of the contract.

TDS/PDS--D. Tender Preparation--

The prices quoted by the Tenderer shall be fixed for the duration of the Contract.
OR
The prices quoted by the Tenderer shall be adjustable as follows:

Iif prices shall be adjustable, the methodology for adjustment should be specified]
 

The prices quoted by the Tenderer shall be fixed for the duration of the Contract.

TDS/PDS--E. Tender e-Submission--

The deadline for lodgement of e-Tenders is [state time, and identify a.m or p.m, i.e 10.30 a.m]


[state date i,e. 15 june,2011 ].
 

The deadline for lodgment of e-Tenders is: As stated in the tender notice

TDS/PDS--G. Contract Award--

The amount of Performance Security shall be [state percentage] percent of the Contract Price.

[usually ten(10) percent of the Contract price, however, should not be less than 5% if retention money is kept at least 5% of contract price; Maximum twenty five (25) percent of the total Contract price in case the Tender price is significantly below the updated official estimate or seriously unbalanced as a result of front loading ]
 

The amount of Performance Security shall be [5%] of the Contract Price.

Maximum twenty five (25) percent of the total Contract price in case the Tender price is significantly below the updated official estimate or seriously unbalanced as a result of front loading.

 