| Eligibility of Tenderer : |
Only eligible Bidders with the following key qualifications should participate in this bidding :
(a) The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Management Contractor shall be 5 (Five) years, counting backward from the date of publication of IFT in the newspaper.
(b) The minimum specific experience as a Prime Contractor or Management Contractor in similar construction works of at least 1(One) contract(s) successfully completed within the last 5 (Five) years with a value of at least BDT 7,20,00,000 , years counting backward from the date of publication of IFT in the newspaper.
(c) The required average annual construction turnover shall be greater than BDT 9,00,00,000 over the last 5( Five) years, counting backward from the date of publication of IFT in the newspaper.
(d) The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be BDT 1,20,00,000
|
| Brief Description of Works : |
Construction 9 ( Nine) nos RCC Drain ( 4893 m) at Bhola Pourashava
Brief Description of the Works: Construction of RCC drain at
(1) Construction of RCC drain from Haron Hawlader's House to Balia Kandi Khal via Prof. Enayet Miah's House. (Ch. 0+000 to 0+388m) and Link drains 152m under Ward No: 03. Length: 0.540 Km.
(2) Construction of RCC drain from BAVS Road to Bhola Khal via Noor Cycle House and Kalibari Road. (Ch. 0+000 to 0+754m) under Ward No 06 &
07. Length: 0.754 Km.
(3) Construction of RCC drain from Safi Mia's House to Bhola Khal via Billah Mosque and Kalibari Road (Ch. 0+085 to 0+435m) under Ward No 02&
03. Length: 0.350 Km.
(4) mConstruction of RCC drain from PTI Boundary to Kathali Khal. (Ch. 0+000 to 0+773m) under Ward No: 08. Length: 0.773 Km.
(5) Construction of RCC drain from Pandit bari Road to Muslim Para Big Drain via Doctor Bari (Ch. 0+000 to 0+458m) And Link Drain 222m under Ward No 08. Length: 0.680 Km.
(6) Construction of RCC drain from R&H Office Campus to Ratanpur Khal via HEED Bangladesh. (Ch. 0+000 to 0+546m) under Ward No 09. Length:
0.546 Km.
(7) Construction of RCC drain from Bida Liton's House to Bhola Khal via Tarek Miah's House and Inspector's House (Ch. 0+000 to 0+262m) under Ward No 03. Length: 0.262 Km.
(8) Construction of RCC drain from Back Side of Nabi Mosque (Ch. 0+000 to 0+283m) under Ward No 03. Length: 0.283 Km
(9) Construction of RCC drain from Sikder Bari to Muslim Para Big Drain via Azgor Chowdhury's House and Sekandar Ali Madrassa. (Ch. 0+000 to 0+610m) And Link Drain 95m under Ward No: 07. Length: 0.705 Km. under Bhola Pourashava; Upazila - Bhola Sadar ; District – Bhola
|