Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Tender Preparation |
| Field Name | Old Value | New Value |
|---|---|---|
| Completion Date(Lot No : 1) | 30/06/2022 | 31/07/2022 |
| Document last selling date & time | 19/12/2021 17:00 | 26/12/2021 17:00 |
| Eligibility of Consultant | As per Tender document. |
As per Tender document. |
| Opening Date & Time | 20/12/2021 12:00 | 27/12/2021 12:00 |
| Last date & time for Tender/Proposal Security Submission | 19/12/2021 17:00 | 26/12/2021 17:00 |
| Start Date(Lot No : 1) | 30/12/2021 | 30/01/2022 |
| Closing Date & Time | 20/12/2021 12:00 | 27/12/2021 12:00 |
| TDS/PDS--D. Tender Preparation-- | The Tenderer shall submit with its e-Tender the following additional documents: 1. Up to date ABC electrical Contractory & Supervisory License. 2. Up to Date Income Tax clearance certificate of the tenderer. If tax clearance certificate is under process then the authentic proof has to be submitted. 3. The bidder must mention the Country of Origin, Make, and Model or Brand of the Fire Suppression Systems . 4. The tenderer is strongly instructed to visit and examine the site by maintaining proper procedure and obtain all necessary information that may be necessary for preparing the tender and entering into a contract for this work and have to do all kind of Civil Works whatever needed and The contractor will also submit a declaration that he has got the scope of work fully clarified. 5. The tender must submit authorization letter from the Manufacturer for Areosol Type Fire Suppression System to participate in this tender. 6. (a) Factory Acceptance Test (FAT): The Engineering Team (At least One (01) E/M Engineer) nominated by the Purchaser will witness the Factory test at the manufacturer’s plant of Fire Susppression System. Duration of this factory acceptance test will be 5 (Five) days. The contractor shall arrange this test before shipment and bear all the cost of such test including all cost related to air traveling, hotel accommodation etc. Expenses covering food and others amounting to US $ 250.00 (Two hundred fifty) per day for each Engineer of CAAB shall also be borne by the Contractor at its own cost for this purpose.
(b)Training at Site: 05 (Five) persons nominated by CAAB will be trained at site. The Training should be of “on the job” nature and duration will be at least 05(Five) days. All cost related to this training will be borne by the Contractor and upon successful completion of this training. The trainer will issue certificate to the trainees. A training allowance of Taka Two Thousand to be paid every day to each trainee by the Contractor. The contractor must submit a consent letterto carry out the TAT and Training at least to the extent specified above and submit it along with the tender. |
The Tenderer shall submit with its e-Tender the following additional documents: 1. Up to date ABC electrical Contractory & Supervisory License. 2. Up to Date Income Tax clearance certificate of the tenderer. If tax clearance certificate is under process then the authentic proof has to be submitted. 3. The bidder must mention the Country of Origin, Make, and Model or Brand of the Fire Suppression Systems . 4. The tenderer is strongly instructed to visit and examine the site by maintaining proper procedure and obtain all necessary information that may be necessary for preparing the tender and entering into a contract for this work and have to do all kind of Civil Works whatever needed and The contractor will also submit a declaration that he has got the scope of work fully clarified. 5. The tender must submit authorization letter from the Manufacturer for Areosol Type Fire Suppression System to participate in this tender. 6. (a) Factory Acceptance Test (FAT): The Engineering Team (At least One (01) E/M Engineer) nominated by the Purchaser will witness the Factory test at the manufacturer’s plant of Fire Susppression System. Duration of this factory acceptance test will be 5 (Five) days. The contractor shall arrange this test before shipment and bear all the cost of such test including all cost related to air traveling, hotel accommodation etc. Expenses covering food and others amounting to US $ 250.00 (Two hundred fifty) per day for each Engineer of CAAB shall also be borne by the Contractor at its own cost for this purpose. (b)Training at Site: 05 (Five) persons nominated by CAAB will be trained at site. The Training should be of “on the job” nature and duration will be at least 05(Five) days. All cost related to this training will be borne by the Contractor and upon successful completion of this training. The trainer will issue certificate to the trainees. A training allowance of Taka Two Thousand to be paid every day to each trainee by the Contractor. The contractor must submit a consent letterto carry out the TAT and Training at least to the extent specified above and submit it along with the tender. 7. The manufacturer of aerosol generator must have an updated ISO 9001:2015 and ISO 14001:2015 certifications, Latest 2022 updated. 8. The aerosol generator manufacturer's product must have a UL Certification for both thermal and electrical range and have to submit it along with the tender. 9. The aerosol generators should be certified with SNAP to be listed for normally occupied spaces and certificate shall have to submit along with the tender. 10. The aerosol electrical activator should be EMC electromagnetic compatibility tested and certified by any accredited body and certificate shall have to submit along with the tender. 11. The aerosol generators should have a certified lifetime of at least 15 years and necessary certificate from an independent laboratory/ certification company shall have to submit along with the tender. 12. The bidder must submit an warranty certificate from the manufacturer for at least 3 (three) years. 13. Design density of the aerosol generator unit should be done as per classification of fire hazard A and should be confirmed from UL distinguish between Extinguishing Application Density (EAD) and Design Application Density (DAD). 14. The brackets of the aerosol generators should have the option to be fitted within panels, using magnets to avoid drilling. Supporting document (like brochures/ catalogue) shall have to submit along with the tender. |
| Brief Description of Goods,Works or Service | Providing and Installation of ABC powder & clean agent Based Standalone (Modular) Fire Suppression system for different switch Room, Sub-station, chiller plant, lift room of TB-1, 2, Domestic Terminal and Boarding Bridge area at HSIA. |
Providing and Installation of ABC powder & clean agent Based Standalone (Modular) Fire Suppression system for different switch Room, Sub-station, chiller plant, lift room of TB-1, 2, Domestic Terminal and Boarding Bridge area at HSIA. |