Qualification Criteria : As per TDS
The Intended Completion Date for the whole of the Works shall be 6.00 month after starting the work. [ Intended completeion date of the work may be 12 (twelve) Month if project duration increased ]
GDIRIIP/Kotali/SP/VR-SR/21-22/216 Construction of 18.00m Long RCC Girder Bridge on Srifolbari Shitla Mondir to Jotiarbari Road at Ch. 2270m (Road ID No: 335515485) under Kotwalipara Upazila, District: Gopalganj.