| Eligibility of Tenderer : |
Any tenderer(s) who fulfill the requirements stated in TDS. The Tenderer with a poor performance, consistent history of litigation or arbitration awards against it shall not be eligible to tender.
* During evaluation if the quoted rate by any tenderer is found more than 5(Five) percent less/above than the Official Estimated price, then it is mandatory to submit Rate Analysis when asked by the Procuring Entity according to Memo No- 35.00.0000.015.14.049.16-516 Dated-31.07.2018 of Maintenance Wing, Road Transport & Highways Division, Ministry of Road Transport & Bridges
N:B:
* 60/70 Grade Bitumen shall be used in all DBS Wearing Course and DBS Base Course works in this project.
* For preparation of DBS materials Asphalt Batching Plant must be used by the contractor.
* The tenderers shall have their own Asphalt Batching Plant. If the tenderers do not have their own Asphalt Batching Plant they may hire it from any other source; But then the tenderers have to submit the contractual agreement to hire or lease of the Asphalt Batching Plant in non-judicial stamp of Tk. 300 affidavit by the notary public.
* The Additional Chief Engineer, RHD, Chattogram Zone will visit the plant during evaluation process to verify the location and condition of the plant.
* The Defects Liability Period is 1095 Days
|
| Brief Description of Works : |
Surfacing work by DBS Wearing Course at different Km. (Ch 270+000 to 271+009, Ch: 271+720 to 271+830, Ch: 272+645 to 272+860, Ch: 273+134 to 273+445, Ch: 276+459 to 277+645, Ch: 277+945 to 278+066, Ch: 279+309 to 280+500, Ch: 281+009 to 282+580, Ch: 284+510 to 285+060, Ch: 285+210 to 285+330, Ch: 285+509 to 286+800, Ch: 288+580 to 290+210, Ch: 295+809 to 295+992, Ch: 300+679 to 301+768, Ch: 301+845 to 302+548, Ch: 306+000 to 309+320) of Dhaka (Jatrabari)-Cumilla (Moinamoti)-Chattogram-Cox's Bazar-Teknaf National Highway (N-1) under Dohazari Road Division during the year 2021-2022.
|