View IFT /PQ / REOI / RFP / PPS Notice Details
Ministry : Ministry of Water Resources Division :
Organization : Bangladesh Water Development Board (BWDB) Procuring Entity Name : Shariatpur O&M Division
Procuring Entity Code : Procuring Entity District : Shariatpur
Procurement Nature : Works Procurement Type : NCT
Event Type : Invitation for : Tender - Single Lot
Invitation Reference No. : T-2/1583; Dated: 23-12-2021 Tender/Proposal Status :
App ID : 182029 Tender/Proposal ID : 641703
Key Information and Funding Information :
Procurement Method : Open Tendering Method (OTM) Budget Type : Development
Source of Funds : Government
Particular Information :
Project Code : 224346900 Project Name : Protection of The Right and Left Bank of Kirtinasha River in Shariatpur District
Tender/Proposal Package No. and Description : Kirtinasha/RBP-03
River Bank Protection Work along the Right Bank of the Kirtinasha River From Km 0.03 to Km 0.700 = 670m at Muktarer Char Union of Naria Upazilla, District Shariatpur, under Shariatpur O&M Division, BWDB, Shariatpur during the year 2021-2022.
Category : Construction work;Site preparation work;Building demolition and wrecking work and earthmoving work;Test drilling and boring work;Works for complete or part construction and civil engineering work;Building construction work;Engineering works and construction works;Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork;Construction work for water projects;Construction works for plants, mining and manufacturing and for buildings relating to the oil and gas industry;Roof works and other special trade construction works;Building installation work;Electrical installation work;Insulation work;Plumbing and sanitary works;Fencing, railing and safety equipment installation work;Mechanical installations;Building completion work;Plastering work;Joinery and carpentry installation work;Floor and wall covering work;Painting and glazing work;Other building completion work;Hire of construction and civil engineering machinery and equipment with operator;Hire of cranes with operator;Hire of earthmoving equipment with operator
Scheduled Tender/Proposal Publication
Date and Time :
23-Dec-2021 23:58 Tender/Proposal Document last selling /
downloading Date and Time :
31-Jan-2022 12:00
Pre - Tender/Proposal meeting Start
Date and Time :
23-Dec-2021 23:59 Pre - Tender/Proposal meeting End
Date and Time :
28-Dec-2021 15:33
Tender/Proposal Closing
Date and Time :
31-Jan-2022 15:30 Tender/Proposal Opening
Date and Time :
31-Jan-2022 15:30
Last Date and Time for Tender/Proposal Security
Submission :
31-Jan-2022 14:30    
Information for Tenderer/Consultant :
Eligibility of Tenderer :

1. Tenderer must have to be registered on e-GP Portal with valid trade license, TIN, and Vat certificate.
2. Tenderers only from Bangladesh can participate in the tender.
3. Payment will be made subject to budget allocation & availability of funds but the work must be continued and proportionate progress must be achieved.
4. Any individual Tender (s)/firm (s) who fulfill the qualification (s) criteria stipulated in the Standard Tender Document including Tender datasheet and PPR-2008 has to be considered.
5. Tender evaluation will be conducted on the basis of uploaded documents of the tenderer. Outside or offline documents will not be considered.
6. The work may be totally dropped, decreased, or increased.
7. The work order will be issued after approval from the Competent Authority.
8. There is no provision for land acquisition. The tenderer has to arrange land for the execution of other works on his own.
9. The tenderer has to capture pictures and videos of the work at his own cost as per the direction of the engineer in charge. He should submit pictures and videos during the time of bill submission.

Brief Description of Works :

Kirtinasha/RBP-03
River Bank Protection Work along the Right Bank of the Kirtinasha River From Km 0.03 to Km 0.700 = 670m at Muktarer Char Union of Naria Upazilla, District Shariatpur, under Shariatpur O&M Division, BWDB, Shariatpur during the year 2021-2022.

Evaluation Type : Lot wise
Document Available : Package wise
Document Fees : Package wise
Tender/Proposal Document Price (In BDT) : 4000
Mode of Payment :
Tender/Proposal Security Valid Up to : 29-May-2022
Tender/Proposal Valid Up to : 01-May-2022
Lot No. Identification of Lot Location Tender/Proposal security
(Amount in BDT)
Tentative Start Date Tentative Completion Date
Lot No.: 01 River Bank Protection Work along the Right Bank of the Kirtinasha River From Km 0.03 to Km 0.700 = 670m at Muktarer Char Union of Naria Upazilla, District Shariatpur, under Shariatpur O&M Division, BWDB, Shariatpur during the year 2021-2022. Naria 4000000 01-Feb-2022 29-Dec-2022
Procuring Entity Details:
Name of Official Inviting Tender/Proposal : S. M Ahsan Habib Designation of Official Inviting Tender/Proposal : Executive Engineer
Address of Official Inviting Tender/Proposal :
Address: Shariatpur
City: Shariatpur
Thana: Shariatpur Sadar
District: Shariatpur - 8000
Country: Bangladesh
Contact details of Official Inviting Tender/Proposal :
Phone No: 0601-61561
Fax No:
The procuring entity reserves the right to accept or reject all Tenders/Proposals / Pre-Qualifications / EOIs
Note: Bank will update the payment transactions only at the end of the day, so the tenderers should make sure the securities and other payments are made at least one day before the submission date.
Documents
Amendment / Corrigendum Detail
 Amendment / Corrigendum No. :  2 
Amendment / Corrigendum Text :

All concerned are hereby informed that the following amendments is made to Tender ID No. 641703 invited vide this Office Memo. No.: T-2/1583 Date: 23/12/2021.
This Amendment notice shall be an integral part of the tender notice. There is some change in BoQ.

Field Name Old Value New Value
Document last selling date & time 27/01/2022 12:00 31/01/2022 12:00
Opening Date & Time 27/01/2022 15:30 31/01/2022 15:30
Last date & time for Tender/Proposal Security Submission 27/01/2022 14:30 31/01/2022 14:30
Closing Date & Time 27/01/2022 15:30 31/01/2022 15:30
 Amendment / Corrigendum No. :  1 
Amendment / Corrigendum Text :

All concerned are hereby informed that the following amendments is made to Tender ID No. 641703 invited vide this Office Memo. No.: T-2/1583 Date: 23/12/2021.
This Amendment notice shall be an integral part of the tender notice.

Field Name Old Value New Value
Document last selling date & time 23/01/2022 12:00 27/01/2022 12:00
Eligibility of Consultant

1. Tenderer must have to be registered on e-GP Portal with valid trade license, TIN, and Vat certificate.
2. Tenderers only from Bangladesh can participate in the tender.
3. Payment will be made subject to budget allocation & availability of funds but the work must be continued and proportionate progress must be achieved.
4. Any individual Tender (s)/firm (s) who fulfill the qualification (s) criteria stipulated in the Standard Tender Document including Tender datasheet and PPR-2008 has to be considered.
5. Tender evaluation will be conducted on the basis of uploaded documents of the tenderer. Outside or offline documents will not be considered.
6. The work may be totally dropped, decreased, or increased.
7. The work order will be issued after approval from the Competent Authority.
8. There is no provision for land acquisition. The tenderer has to arrange land for the execution of other works on his own.
9. The tenderer has to capture pictures and videos of the work at his own cost as per the direction of the engineer in charge. He should submit pictures and videos during the time of bill submission.

1. Tenderer must have to be registered on e-GP Portal with valid trade license, TIN, and Vat certificate.
2. Tenderers only from Bangladesh can participate in the tender.
3. Payment will be made subject to budget allocation & availability of funds but the work must be continued and proportionate progress must be achieved.
4. Any individual Tender (s)/firm (s) who fulfill the qualification (s) criteria stipulated in the Standard Tender Document including Tender datasheet and PPR-2008 has to be considered.
5. Tender evaluation will be conducted on the basis of uploaded documents of the tenderer. Outside or offline documents will not be considered.
6. The work may be totally dropped, decreased, or increased.
7. The work order will be issued after approval from the Competent Authority.
8. There is no provision for land acquisition. The tenderer has to arrange land for the execution of other works on his own.
9. The tenderer has to capture pictures and videos of the work at his own cost as per the direction of the engineer in charge. He should submit pictures and videos during the time of bill submission.

Opening Date & Time 23/01/2022 15:30 27/01/2022 15:30
PCC--A. General--

The Site is located at [location] and is defined in drawings No: 
[insert numbers]
 

The Site is located at Naria, Shariatpur .


The Tenderers are requested to visit the site before submitting the Tender.
 

PCC--A. General--

Nominated Subcontractor(s)  named below;

____[insert name(s)]___________________________________________
shall be entitled to execute the following specific components of the Works

[state none ,if not applicable]
 

Nominated Subcontractor(s)  named below; None.

 

PCC--A. General--

The minimum insurance cover shall be:

(a)

The maximum deductible for insurance of the Works and of Plant and Materials is Tk [state amount]


[the Contractor shall provide this amount at the time of Contract signing].
 

(b)

The minimum cover for insurance of the Works and of Plant and Materials in respect of the Contractor’s faulty design is Tk [state amount].


[the amount could be 110% of the value of the works, plant and materials that may be lost in a worst case scenario].
 

(c)

The maximum deductible for insurance of Equipment is Tk [state amount].


[the Contractor shall provide this amount at the time of Contract signing].
 

(d)

The minimum cover for loss or damage to Equipment is Tk [state amount].


[the amount could be 110% of the replacement value of the equipment]
 

(e)

The maximum deductible for insurance of other property is Tk [state amount].


[the Contractor shall state this amount at the time of Contract signing].
 

(f)

The minimum cover for insurance of other property is Tk [state amount].


[it is the responsibility of the Contractor to obtain adequate insurance cover for such risks – recommended value 10% of contract price].
 

(g)

The minimum cover for personal injury or death insurance:


(i) for the Contractor’s employees is as per the law and common practice in Bangladesh.


(ii) and for third parties is as per the law and common practice in Bangladesh.
 

The minimum insurance cover shall be:  As per Government Rule.

(a)

The maximum deductible for insurance of the Works and of Plant and Materials is Tk [state amount]


[the Contractor shall provide this amount at the time of Contract signing].
 

(b)

The minimum cover for insurance of the Works and of Plant and Materials in respect of the Contractor’s faulty design is Tk [state amount].


[the amount could be 110% of the value of the works, plant and materials that may be lost in a worst case scenario].
 

(c)

The maximum deductible for insurance of Equipment is Tk [state amount].


[the Contractor shall provide this amount at the time of Contract signing].
 

(d)

The minimum cover for loss or damage to Equipment is Tk [state amount].


[the amount could be 110% of the replacement value of the equipment]
 

(e)

The maximum deductible for insurance of other property is Tk [state amount].


[the Contractor shall state this amount at the time of Contract signing].
 

(f)

The minimum cover for insurance of other property is Tk [state amount].


[it is the responsibility of the Contractor to obtain adequate insurance cover for such risks – recommended value 10% of contract price].
 

(g)

The minimum cover for personal injury or death insurance:


(i) for the Contractor’s employees is as per the law and common practice in Bangladesh.


(ii) and for third parties is as per the law and common practice in Bangladesh.
 

PCC--C. Quality Control--

The Defects Liability Period is [state months]

[usually Defect Liability Period is twelve (12) months to cover at least one complete monsoon season].
 

The Defects Liability Period is twelve (12) months.


 

PCC--D. Cost Control--

The Contract is not subject to price adjustment.
OR
The Contract is subject to price adjustment, the weightings or coefficients for adjustment are:

[Price Adjustment Formulae to be applicable if stated under ITT Sub Clause 27.10 shall be specified here]
Example:
P= A + a (Lm/Lo)+ b (BIm/BIo)+ c (CEm/CEo)+ d (RSm/RSo)+ e (STm/STo)+ f (BRm/BRo)+g (MIm/MIo) + h (FUm/FUo)+ etc
where;
L= Labor, BI=Bitumen, CE=Cement, RS=Reinforcing Steel, ST=Stone, BR=Bricks, MI=Miscellaneous, FU= Fuel ]
Weighting or Coefficient A equals between 0.10 and 0.15 and, B (a+b+c+d+e+f+g+h+etc) equals between 0.90 and 0.85.

[insert figure] non-adjustable component (coefficient A)
[insert figure] adjustable component (coefficient B)
[The sum of A+B shall equal ONE (1). It is usual to have value of A between 0.10 and 0.15 and that of B between 0.90 and 0.85. Breakdown of B shall be provided in Appendix to the Tender.]
[delete as appropriate]

[price adjustment clauses are usually only permitted for Works Contracts, execution of which will take more than eighteen (18) months from Start Date to Completion Date. The PE must consider each Contract on its individual merit; approval of HOPE required for Contracts of less than eighteen (18) months]
 

The Contract is not subject to price adjustment.

PCC--D. Cost Control--

The proportion of payments to be retained is [insert percent] percent.


[state “none’ if not applicable. If applicable then the proportion of Retention Money shall be equal to the percentage-shortfall of ten (10) percent of Performance Security determined at the time of signing the Contract. Again in case of unbalanced Tender or because of front loading, provision for Retention Money shall not be applicable]
 

The proportion of payments to be retained is five (5) percent in addition to the Performance Security.


 

PCC--D. Cost Control--

The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is [insert percentage] percent of its Contract price per day of delay.
[usually the percent-rate of liquidated damages is set at between 0.05 and 0.10 of ONE (1) percent of its Contract price per day of delay]
Guide to application of GCC Sub Clause 76.1 above
[ Liquidated damages is equivalent to an amount to be determined in accordance with the following formula
T LD = VUW x Px n
Where;
T LD = Total amount of Liquidated Damages
VUW = Value of Uncompleted Works (i.e. works not having been completed as of the expiry of the Intended Completion Date plus the works completed after the expiry of the Intended Completion Date). VUW shall be calculated by deducting the value of the completed works under the Contract from the total Contract price
P = Percent-rate at which the Liquidated Damages shall be imposed for every day of delay
n = No of days of delay for completion of works under the Contract]

 

The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works.


[ usually the total amount of liquidated damages shall not exceed ten (10) percent of the final Contract price for the whole of the Works]

 

The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is 0.01 percent of its Contract price per day of delay.
 

Guide to application of GCC Sub Clause 76.1 above
[ Liquidated damages is equivalent to an amount to be determined in accordance with the following formula
T LD = VUW x Px n
Where;
T LD = Total amount of Liquidated Damages
VUW = Value of Uncompleted Works (i.e. works not having been completed as of the expiry of the Intended Completion Date plus the works completed after the expiry of the Intended Completion Date). VUW shall be calculated by deducting the value of the completed works under the Contract from the total Contract price
P = Percent-rate at which the Liquidated Damages shall be imposed for every day of delay
n = No of days of delay for completion of works under the Contract]

 

The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10.00 percent of the final Contract price of the whole of the Works.

PCC--D. Cost Control--

The Bonus for the whole of the Works is [insert percentage] percent of the final Contract price per day.

The maximum amount of Bonus for the whole of the Works is [insert percentage] percent of the final Contract price.

[if early completion would provide benefits to the PE, this clause should remain, otherwise state “Not Applicable”. The bonus is usually numerically equal to the Liquidated Damages]
 

The Bonus for the whole of the Works is [insert percentage] percent of the final Contract price per day. Not Applicable

 

PCC--D. Cost Control--

The Advance Payment shall be Tk [insert amount] and shall be paid to the Contractor not later than [insert date].

[for 100 percent GoB funded procurement, advance payments are not recommended unless otherwise specifically decided by the Government. An advance payment, if admissible, shall be made for mobilisation, considering the nature of the works. The recommended maximum advance payment is ten (10) percent of the original Contract price against an unconditional Bank Guarantee (Form e-PW3-10.) On the contrary, advance payments may be applicable for procurements under aided projects]
 

 


The Advance Payment is not applicable here as the fund is GOB only.

PCC--F. Termination and Settlement of Disputes--

The percentage to apply to the contract value of the works not completed, representing the PE’s additional cost for completing the uncompleted Works, is [state percentage] percent.

[ usually between ten (10) to twenty (20) percent depending on the nature of the Works]
 

The percentage to apply to the contract value of the works not completed, representing the PE’s additional cost for completing the uncompleted Works, is Fifteen (15) percent.


 

Last date & time for Tender/Proposal Security Submission 23/01/2022 14:30 27/01/2022 14:30
Closing Date & Time 23/01/2022 15:30 27/01/2022 15:30
TDS/PDS--A. General--

The PE is [state name of PE]

 

The Name of the Tender is:
Brief Description of the Works:

Tender Ref:

Lot No(s):

[if there is more than one(1) lot, individual lots are to be identified in conformity with Section 6: Bill of Quantities]
 

The PE is

The Executive Engineer
Shariatpur O&M Division
BWDB, Shariatpur .
E-mail: xen.shariatpurbwdb@gmail.com

The Name of the Tender is:River Bank Protection Work along the Right Bank of the Kirtinasha River From Km 0.03 to Km 0.700 = 670m at Muktarer Char Union of Naria Upazilla, District Shariatpur, under Shariatpur O&M Division, BWDB, Shariatpur during the year 2021-2022.


Brief Description of the Works: Bank revetment work etc.

Tender Ref: as per tender notice. 

Lot No(s): as per tender notice.

[if there is more than one(1) lot, individual lots are to be identified in conformity with Section 6: Bill of Quantities]
 

TDS/PDS--A. General--

The source of public funds is

[state source, GoB or other source of funds].
 

The source of public funds is GoB


 

TDS/PDS--A. General--

The name of the Development Partner is

[state name of Development Partner]
 

The name of the Development Partner is None.


 

TDS/PDS--A. General--

Tenderers from the following countries are not eligible

[ state countries, if any ]
 

Tenderers from the following countries are not eligible As tender is NCT, only tenderers from Bangladesh are allowed.


 

TDS/PDS--A. General--

Tenderers from the following countries are not eligible

[ state countries, if any ]
 

Tenderers from the following countries are not eligible As tender is NCT, only tenderers from Bangladesh are allowed.


 

TDS/PDS--A. General--

Materials, Equipments and associated services from the following countries are not eligible:

[state countries, if any]
 

Materials, Equipments and associated services from the following countries are not eligible: Not Applicable.


 

TDS/PDS--B. e-Tender Document (e-TD)--

Allowed to post clarification till [Date and Time]

Allowed to post clarification till: Not Applicable.

TDS/PDS--B. e-Tender Document (e-TD)--

Pre- Tender meeting [Date & Time]

Pre- Tender meeting As per IFT.

TDS/PDS--C. Qualification Criteria--

The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be [state number] years.

[a minimum of three (3) years would be deemed reasonable; years counting backward from the date of publication of IFT in the newspaper]

 

The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least [state number] contract(s) of similar nature, complexity and methods/construction technology successfully completed within the last [state number] years, each with a value of at least Tk. [state amount].

[the minimum number of contracts will depend upon the size and type of construction work, and the PE should make its own judgement based upon its experience in the sector and construction industry. For example, for large works, it could be one (1) contract of similar nature during the last three (3) years or five (5) years or ten (10) years (whichever appropriate); years counting backward from the date of publication of IFT in the newspaper]
 

[for Tenders where the package contains more than one (1) lot, this qualification requirements, only when applicable, shall be mentioned separately for each lot in the package]
[the minimum value of the similar works is recommended to be between 50 and 75 percent of the estimated cost of the proposed work]

 

The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 5 (Five) years.

The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least 01 (One) contracts of similar nature,
complexity and methods/construction technology successfully completed within the last 5 (Five) years with a total value of at least Tk. 850.00 Lakh.

[ years counting backward from the date of publication of IFT in the newspaper]

TDS/PDS--C. Qualification Criteria--

The minimum capacity shall be:[70%-80% of the official estimated cost]
The following formulae shall be used to calculate the Tender Capacity
Assessed Tender Capacity = (A*N*1.5-B)

Where
A=Maximum value of Works performed in any one year during last five years
N= Completion time of the proposed work in years
B= Value of Existing commitments and works to be completed during the next N Years

Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one)
Note 2: In case of JV tender capacity requirement for leading partner shall be minimum 40% and for other partners shall be minimum 25%.
 

The minimum capacity shall be Tk. 13,00,00,000.00 (Therteen crore taka only)
The following formulae shall be used to calculate the Tender Capacity
Assessed Tender Capacity = (A*N*1.5-B)

Where
A=Maximum value of Works performed in any one year during last five years
N= Completion time of the proposed work in years
B= Value of Existing commitments and works to be completed during the next N Years

Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one)
Note 2: In case of JV tender capacity requirement for leading partner shall be minimum 40% and for other partners shall be minimum 25%.

TDS/PDS--C. Qualification Criteria--

The required average annual construction turnover shall be greater than Tk [insert amount] over the last [state number] years.

[ the required average annual construction turn over is recommended to be about twice the estimated annual cash flow for the Contract; however the multiplier may vary from 1.0 to 2.0, the larger the Contract size the lesser the multiplier should be. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate) ; years counting backward from the date of publication of IFT in the newspaper]
Example:


Estimated Contract Value: Tk 24 Cr.
Contract period: 18 months
Estimated Annual Cash Flow: Tk 16 Cr.
Required average annual construction turn over: Tk 24 Cr., using a multiplier of 1.5.
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]

  

The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk [state amount]

[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Example:


Contract Value: Tk 24 Cr.
Contract period: 18 months
Assuming work time: 1 month
Invoice period: 0.5 month
Certification Time: 0.5 month
Contingency Time: 1 month

Therefore, the minimum required liquid asset will be Tk 4 Cr., i.e. 3 months cash flow based on the above assumptions.]
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]

 

The required average annual construction turnover shall be greater than Tk. 1600.00 Lakh over the last 5 (Five) years.

 

The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk. 900.00 Lakh.

Liquid asset has to be submitted in format of "Letter of Commitment for Bank’s Undertaking for Line of Credit". This "Letter of Commitment for Bank’sUndertaking for Line of Credit" format has been uploaded in Section 8 : Particular Specifications


 

TDS/PDS--C. Qualification Criteria--

 

TDS Clauses References Requirements by summation Requirements for Lead Partner of JVCA Requirements for other Partner(s) of JVCA
ITT-15.1(a) Summation not applicable Same as stated in TDS Same as for
Leading Partner
 
ITT-15.1(b) 100% At least one Contract Minimum requirement not applicable
ITT-16.1(a) 100% 40% 25%
ITT-16.1(b) 100% 40% 25%
ITT-17.1 100% Minimum requirement not applicable Minimum requirement not applicable
ITT-18.1 100% Minimum requirement not applicable Minimum requirement not applicable

 

The value of non-judicial stamp for execution of the Joint Venture agreement shall be Tk [state amount]
[the value of the non-judicial stamp shall be Tk.300.00]
 

 

TDS Clauses References Requirements by summation Requirements for Lead Partner of JVCA Requirements for other Partner(s) of JVCA
ITT-15.1(a) Summation not applicable Same as stated in TDS Same as for
Leading Partner
 
ITT-15.1(b) 100% At least one Contract Minimum requirement not applicable
ITT-16.1(a) 100% 40% 25%
ITT-16.1(b) 100% 40% 25%
ITT-17.1 100% Minimum requirement not applicable Minimum requirement not applicable
ITT-18.1 100% Minimum requirement not applicable Minimum requirement not applicable

 

The value of non-judicial stamp for execution of the Joint Venture agreement shall be Tk.300.00
[the value of the non-judicial stamp shall be Tk.300.00]
 

TDS/PDS--C. Qualification Criteria--

The minimum qualification requirements of Leading Partner and other Partner(s) of a JVCA shall be as follows :

[it is suggested that the PE adheres to the above proportion of minimum qualifying requirements to meet the specific procurement needs. Percent share of business of the JVCA partners shall not be taken into account in determining the qualification of a JVCA]
 

The minimum qualification requirements of Leading Partner and other Partner(s) of a JVCA shall be as follows : as mentioned in clause ITT-19.1
 

TDS/PDS--C. Qualification Criteria--

The Nominated Subcontractor(s) named [insert name(s)] shall execute the following specific components of the proposed Works:


[state the components of the proposed works ; if not applicable state ‘none’]
 

The Nominated Subcontractor(s) named [insert name(s)] shall execute the following specific components of the proposed Works: None


 

TDS/PDS--D. Tender Preparation--

The Tenderer shall submit with its Tender the following additional documents:


[in case of purchase of capital equipment by the Contractor as part of the overall Contract, a Performance Statement of the capital equipment in Bangladesh may be necessary and may be requested. if no other documents are required then specify “none”]

 

The Tenderer shall submit with its Tender the following additional documents: none



 

TDS/PDS--D. Tender Preparation--

The prices quoted by the Tenderer shall be fixed for the duration of the Contract.
OR
The prices quoted by the Tenderer shall be adjustable as follows:

Iif prices shall be adjustable, the methodology for adjustment should be specified]
 

The prices quoted by the Tenderer shall be fixed for the duration of the Contract.

TDS/PDS--E. Tender e-Submission--

The deadline for lodgement of e-Tenders is [state time, and identify a.m or p.m, i.e 10.30 a.m]


[state date i,e. 15 june,2011 ].
 

The deadline for lodgement of e-Tenders is as stated in tender notice.

TDS/PDS--G. Contract Award--

The amount of Performance Security shall be [state percentage] percent of the Contract Price.

[usually ten(10) percent of the Contract price, however, should not be less than 5% if retention money is kept at least 5% of contract price; Maximum twenty five (25) percent of the total Contract price in case the Tender price is significantly below the updated official estimate or seriously unbalanced as a result of front loading ]
 

The amount of Performance Security shall be Five (5) percent of the Contract Price.

N.B. The Maximum amount of Performance Security shall be twenty five (25) percent of the total Contract price including retention money in case the Tender price is significantly
below the updated official estimate or seriously unbalanced as a result of front loading.

Brief Description of Goods,Works or Service

Kirtinasha/RBP-03
River Bank Protection Work along the Right Bank of the Kirtinasha River From Km 0.03 to Km 0.700 = 670m at Muktarer Char Union of Naria Upazilla, District Shariatpur, under Shariatpur O&M Division, BWDB, Shariatpur during the year 2021-2022.

Kirtinasha/RBP-03
River Bank Protection Work along the Right Bank of the Kirtinasha River From Km 0.03 to Km 0.700 = 670m at Muktarer Char Union of Naria Upazilla, District Shariatpur, under Shariatpur O&M Division, BWDB, Shariatpur during the year 2021-2022.

 
Save As PDF