View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Missing of BOQ Electrical Item |
| Field Name | Old Value | New Value | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| PCC--A. General-- | The Start Date shall be [insert date ]
[it is the last date when the Contractor shall commence execution of the Works under the Contract reasonably immediately after the Commencement Date; refer to GCC Clause 40] |
The Start Date shall within 7 (seven) days from the date of signing of contract |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | The Works consist of [state brief summary, including relationship to other Contracts under the Project] |
The Works consist of 19/e-GP/Rev/2021-22 Construction of 10 stored working women's hostel cum commercial building in front of Zila School Attached to Fulbaria old bus stand in Mymensingh district during the FY/2017-2018. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- |
The PE is The Development Partner is [Name of the DP] |
The Procuring Entity is Chief Executive officer, Zila Parishad, Mymensingh.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- |
The PE is |
The Procuring Entity is Chief Executive officer, Zila Parishad, Mymensingh. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | The original Contract price is [insert the amount in the NOA] |
The original Contract price is the same as total quoted price at BOQ. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- |
The Contractor is |
The Contractor is(This Clause will be filled up at the time of contract signing) |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- |
The Project Manager is
|
The Project Manager is Assistant Engineer, Zila Parishad, Mymensingh. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- |
The Site is located at [location] and is defined in drawings No: |
The Site is located at [location] and is defined in drawings No: None |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | Possession of the Site or part(s) of the Site, to the Contractor shall be given on the following date(s);
[state date or dates of possession of site] |
Possession of the Site or part(s) of the Site, to the Contractor shall be given on the following date(s); within 7 (seven) days from the signing of the contract agreement |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | Following Key Personnel to carry out the functions stated in the Schedule shall be employed by the Contractor;
[insert name(s)] |
Following Key Personnel to carry out the functions stated in the Schedule shall be employed by the Contractor; |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | The Sectional Completion Dates are:
[state part of the works and the corresponding dates, if applicable] |
The Sectional Completion Dates are: All section of the work have to be completed 730 days from the Commencement of work |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | Nominated Subcontractor(s) named below;
____[insert name(s)]___________________________________________
[state none ,if not applicable] |
Nominated Subcontractor(s) : Not Applicable |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | The Contractual matters between the PE and the Contractor shall be decided by
[state only if other than the Project Manager] |
The Contractual matters between the PE and the Contractor shall be decided by Chairman, Zila Parishad. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- |
The PE’s address for the purpose of communications under this contract is :
|
The PE’s is Chief Executive officer, Zila Parishad, Mymensingh.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | The minimum insurance cover shall be:
|
i) Insurance shall be done from Sadharan Bima Corporation at the Contractor's own cost. In this respect, Contract price shall be considerd to be inclusive of cost of premium for Insurance. ii) The minimum insurance cover shall be:
The minimum insurance cover shall be: The minimum cover for personal injury or death insurance:
(i) for the Contractor’s employees is as per the law and common practice in Bangladesh. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | Other documents forming part of the Contract are;
[list other documents viz. Schedule of other contractors, Schedule of Key Personnel, Site Investigation Reports, relevant correspondences prior to signing of the Contract agreement etc.] |
Other documents forming part of the Contract are; i. The Schedule of Key Personnel; ii.Work Program; iii. Joint Venture Agreement ( if applicable); iv.Joint Venture Information Sheet (if applicable); v. Insurance. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | Materials, Equipments Plants and supplies shall not have their origin in the following countries:
[state countries, if applicable] |
Materials, Equipments Plants and supplies shall not have their origin in the following countries: ISRAEL |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--A. General-- | A Contractor or a Subcontractor that is a national of, or registered in, the following countries are not eligible:
[state countries, if applicable] |
A Contractor or a Subcontractor that is a national of, or registered in, the following countries are not eligible: Israel |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--B. Time Control-- | Commencement Date of Works shall be as follows;
[insert different commencement dates for different parts of the Works, if deemed appropriate] |
Commencement Date of Works shall be as follows; 7 days from the signing of contract |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--B. Time Control-- | The Contractor shall submit a Programme for the Works within [insert days] days of signing the Contract.
[usually fifteen (15) days] |
The period between Programme updates is 30 days. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--B. Time Control-- | The period between Programme updates is [state interval]
[usually bi-monthly or quarterly depending on the nature of the Works] |
The period between Programme updates is bi-monthly |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--B. Time Control-- | The amount to be withheld for late submission of an updated Programme is [state amount]. |
The amount to be withheld for late submission of an updated Programme is 0.5% of the next payment certificate. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--C. Quality Control-- | The Defects Liability Period is [state months]
[usually Defect Liability Period is twelve (12) months to cover at least one complete monsoon season]. |
The Defects Liability Period is twelve (12) months. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- | The following additional events shall also be the Compensation Events:
|
The following additional events shall also be the Compensation Events: none |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- | The proportion of payments to be retained is [insert percent] percent.
|
The proportion of payments to be retained is10 percent. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- |
The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is [insert percentage] percent of its Contract price per day of delay.
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works.
|
The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is [insert percentage] percent of its Contract price per day of delay.
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is 10 percent of the final Contract price of the whole of the Works. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- | The Bonus for the whole of the Works is [insert percentage] percent of the final Contract price per day. The maximum amount of Bonus for the whole of the Works is [insert percentage] percent of the final Contract price.
[if early completion would provide benefits to the PE, this clause should remain, otherwise state “Not Applicable”. The bonus is usually numerically equal to the Liquidated Damages] |
The Bonus for the whole of the Works is [insert percentage] percent of the final Contract price per day : Not Applicable The maximum amount of Bonus for the whole of the Works is [insert ≤ ten (10)] percent of the final Contract Price : Not Applicable |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- | The Advance Payment shall be Tk [insert amount] and shall be paid to the Contractor not later than [insert date].
[for 100 percent GoB funded procurement, advance payments are not recommended unless otherwise specifically decided by the Government. An advance payment, if admissible, shall be made for mobilisation, considering the nature of the works. The recommended maximum advance payment is ten (10) percent of the original Contract price against an unconditional Bank Guarantee (Form e-PW3-10.) On the contrary, advance payments may be applicable for procurements under aided projects] |
The Advance Payment shall be Tk [insert amount] and shall be paid to the Contractor not later than [insert date].Not Applicable |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--D. Cost Control-- | The percentage for adjustment of Provisional Sums is
____% (_________percent) |
The percentage for adjustment of Provisional Sums is : None |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--E. Completion of the Contract-- | The date by which “as-built” drawings are required is [insert date]
The date by which operating and maintenance manuals are required is [insert date] |
The date by which “as-built” drawings are required is Not Applicable |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--E. Completion of the Contract-- | The amount to be withheld for failing to produce “as-built” drawings and/or operating and maintenance manuals by the date required is Tk [insert amount]
[usually a very nominal amount] |
The amount to be withheld for failing to produce “as-built” drawings and/or operating and maintenance manuals by the date required is Tk. maximum 0.01% ( zero one percent) of the final amount. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--F. Termination and Settlement of Disputes-- | The percentage to apply to the contract value of the works not completed, representing the PE’s additional cost for completing the uncompleted Works, is [state percentage] percent.
[ usually between ten (10) to twenty (20) percent depending on the nature of the Works] |
The percentage to apply to the contract value of the works not completed, representing the PE’s additional cost for completing the uncompleted Works, is 20 percent. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--G. Claims, Disputes and Arbitration-- |
The arbitration shall be conducted in the place mentioned below; |
The arbitration shall be conducted in the place mentioned below; |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| PCC--G. Claims, Disputes and Arbitration-- |
The Adjudicator jointly appointed by the parties is:
In case of disagreement between the parties, the Appointing Authority for the Adjudicator is the President of the Institution of Project Managers, Bangladesh. |
The arbitration shall be conducted in the place mentioned below; |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- |
The minimum capacity shall be:[70%-80% of the official estimated cost]
Where
Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one) |
The minimum capacity shall be:16,00,00,000 (Sixteen crore) taka
Where
Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one) |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | A Construction Project Manager, Engineer, and other key staff shall have the following qualifications and experience:
[ qualification of an alternative Construction Project Manager may also be requested] |
A Construction Project Manager, Engineer, and other key staff shall have the following qualifications and experience:
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | Tenderer shall own or have proven access to hire or lease of the major construction equipments, in full working order as follows :
[for Tenders where the package contains more than one (1) lot, this qualification requirement may be necessary for each lot in the package, subject to the nature of the control required over each package] |
Tenderer shall own or have proven access to hire or lease of the major construction equipments, in full working order as follows : |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--D. Tender Preparation-- | The Tenderer shall submit with its Tender the following additional documents:
|
The Tenderer shall submit with its Tender the following additional documents:
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--D. Tender Preparation-- |
The prices quoted by the Tenderer shall be fixed for the duration of the Contract.
Iif prices shall be adjustable, the methodology for adjustment should be specified] |
The prices quoted by the Tenderer shall be fixed for the duration of the Contract. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--E. Tender e-Submission-- | The deadline for lodgement of e-Tenders is [state time, and identify a.m or p.m, i.e 10.30 a.m]
|
The deadline for lodgement of e-Tenders is As per tender Notice |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--G. Contract Award-- | The amount of Performance Security shall be [state percentage] percent of the Contract Price.
[usually ten(10) percent of the Contract price, however, should not be less than 5% if retention money is kept at least 5% of contract price; Maximum twenty five (25) percent of the total Contract price in case the Tender price is significantly below the updated official estimate or seriously unbalanced as a result of front loading ] |
The amount of Performance Security shall be10 percent of the Contract Price. |