View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Correction From TDS & PCC |
| Field Name | Old Value | New Value |
|---|---|---|
| Completion Date(Lot No : 1) | 26/01/2023 | 24/01/2023 |
| Document last selling date & time | 09/03/2022 14:00 | 15/03/2022 14:00 |
| Eligibility of Consultant | As per TDS |
As per TDS |
| Location(Lot No : 1) | Madupur Upazila | Madhupur Upazila |
| Opening Date & Time | 10/03/2022 12:00 | 16/03/2022 12:00 |
| PCC--A. General-- | The PE is: Bidyut Kumer Das Upazila Engineer, Madhupur,Tangail |
The PE is: Md. Joynal Abedin Upazila Engineer, Madhupur,Tangail |
| PCC--A. General-- | The PE is: Bidyut Kumer Das Upazila Engineer, Madhupur,Tangail
GCC 1.1 (tt)
GCC 39.2(b) please read the following instead of existing:
GCC 39.2(c) please read the following instead of existing:
GCC 39.2(d) please read the following instead
GCC 39.2(e) please read the following in addition to the existing: |
The PE is: Md. Joynal Abedin Upazila Engineer, Madhupur,Tangail
GCC 1.1 (tt)
GCC 39.2(b) please read the following instead of existing:
GCC 39.2(c) please read the following instead of existing:
GCC 39.2(d) please read the following instead
GCC 39.2(e) please read the following in addition to the existing: |
| PCC--A. General-- | The PE is: Bidyut Kumer Das Upazila Engineer, Madhupur,Tangail |
The PE is: Md. Joynal Abedin Upazila Engineer, Madhupur,Tangail |
| PCC--A. General-- |
The PE’s address for the purpose of communications under this contract is :
Address: Madhupur,Tangail.
|
The PE’s address for the purpose of communications under this contract is :
Address: Madhupur,Tangail.
|
| PCC--C. Quality Control-- | The Defects Liability Period is [state months] [usually Defect Liability Period is twelve (12) months to cover at least one complete monsoon season]. |
The Defects Liability Period is: 12 (Twelve) Months. |
| PCC--D. Cost Control-- | The following additional events shall also be the Compensation Events:
|
The following additional events shall also be the Compensation Events: None |
| PCC--D. Cost Control-- |
The Contract is not subject to price adjustment.
[Price Adjustment Formulae to be applicable if stated under ITT Sub Clause 27.10 shall be specified here]
[insert figure] non-adjustable component (coefficient A) [price adjustment clauses are usually only permitted for Works Contracts, execution of which will take more than eighteen (18) months from Start Date to Completion Date. The PE must consider each Contract on its individual merit; approval of HOPE required for Contracts of less than eighteen (18) months] |
The Contract is not subject to price adjustment. |
| PCC--D. Cost Control-- | The proportion of payments to be retained is [insert percent] percent.
|
The proportion of payments to be retained is 5 (Five) percent from each progressive payment & 10 (Ten) percent from final account (total final billed amount). |
| PCC--D. Cost Control-- |
The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is [insert percentage] percent of its Contract price per day of delay.
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works.
|
The amount of Liquidated Damages or in other words Delay Damages for the uncompleted Works or any part thereof is: 0.01 (Zero point zero one) percent of its Contract price per day of delay. The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is: 10 (Ten) percent of the final Contract price of the whole of the Works. |
| PCC--D. Cost Control-- | The Bonus for the whole of the Works is [insert percentage] percent of the final Contract price per day. The maximum amount of Bonus for the whole of the Works is [insert percentage] percent of the final Contract price. [if early completion would provide benefits to the PE, this clause should remain, otherwise state “Not Applicable”. The bonus is usually numerically equal to the Liquidated Damages] |
The Bonus for the whole of the Works is: N/A] |
| PCC--D. Cost Control-- | The Advance Payment shall be Tk [insert amount] and shall be paid to the Contractor not later than [insert date]. [for 100 percent GoB funded procurement, advance payments are not recommended unless otherwise specifically decided by the Government. An advance payment, if admissible, shall be made for mobilisation, considering the nature of the works. The recommended maximum advance payment is ten (10) percent of the original Contract price against an unconditional Bank Guarantee (Form e-PW3-10.) On the contrary, advance payments may be applicable for procurements under aided projects] |
The Advance Payment shall be Tk. N/A |
| PCC--D. Cost Control-- | The percentage for adjustment of Provisional Sums is
____% (_________percent) |
The percentage for adjustment of Provisional Sums is: N/A |
| PCC--E. Completion of the Contract-- | The date by which “as-built” drawings are required is [insert date]
The date by which operating and maintenance manuals are required is [insert date] |
The date by which “as-built” drawings are required is: N/A |
| PCC--E. Completion of the Contract-- | The amount to be withheld for failing to produce “as-built” drawings and/or operating and maintenance manuals by the date required is Tk [insert amount] [usually a very nominal amount] |
The amount to be withheld for failing to produce “as-built” drawings and/or operating and maintenance manuals by the date required is: N/A |
| PCC--F. Termination and Settlement of Disputes-- | The percentage to apply to the contract value of the works not completed, representing the PE’s additional cost for completing the uncompleted Works, is [state percentage] percent. [ usually between ten (10) to twenty (20) percent depending on the nature of the Works] |
The percentage to apply to the contract value of the works not completed, representing the PE’s additional cost for completing the uncompleted Works, is 10 [Ten] percent. |
| PCC--G. Claims, Disputes and Arbitration-- |
The arbitration shall be conducted in the place mentioned below; |
The arbitration shall be conducted in the place mentioned below; LGED Bhaban, Agargaon, Sher-E- Bangla nagar, Dhaka 1207. |
| PCC--G. Claims, Disputes and Arbitration-- |
The Adjudicator jointly appointed by the parties is:
In case of disagreement between the parties, the Appointing Authority for the Adjudicator is the President of the Institution of Project Managers, Bangladesh. |
The Adjudicator jointly appointed by the parties is: |
| Meeting End Date & Time | 08/03/2022 17:00 | 13/03/2022 17:00 |
| Last date & time for Tender/Proposal Security Submission | 10/03/2022 11:00 | 15/03/2022 15:00 |
| Closing Date & Time | 10/03/2022 12:00 | 16/03/2022 12:00 |
| TDS/PDS--A. General-- | The PE is Bidyut Kumer Das
The Name of the Tender is: Construction of additional class room CHARALJANI GPS under PEDP4. Tender Ref: APP ID : 182802 Lot No(s): 01 |
The PE is Md. Joynal Abedin
The Name of the Tender is: Construction of additional class room CHARALJANI GPS under PEDP4. Tender Ref: APP ID : 182802 Lot No(s): 01 |
| TDS/PDS--C. Qualification Criteria-- | The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 5 (Five) years. The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least 01 (One) contract(s) of similar nature, complexity and methods/construction technology successfully completed within the last 5 (Five) years, each with a value of at least Tk. 6,300,000 (Sixty Three lac ) |
The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 5 (Five) years. The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least 01 (One) contract(s) of similar nature, complexity and methods/construction technology successfully completed within the last 5 (Five) years, each with a value of at least Tk. 63,00,000.00 (Sixty Three lac ) |
| TDS/PDS--C. Qualification Criteria-- | The required average annual construction turnover shall be greater than Tk. 11,200,000 (One Crorer Twelve Lac) over the last 05 (Five) years. The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk. 2,500,000 (Twenty Five lac) |
The required average annual construction turnover shall be greater than Tk. 1,12,00,000.00 (One Crore Twelve Lac) over the last 05 (Five) years. The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk. 25,00,000.00 (Twenty Five lac) |
| TDS/PDS--C. Qualification Criteria-- | The minimum capacity shall be: 6,720,000 (Sixty Seven Lac Twenty Thousand)
Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one) |
The minimum capacity shall be: 67,20,000 (Sixty Seven Lac Twenty Thousand)
Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one) |
| Brief Description of Goods,Works or Service | Construction of additional class room CHARALJANI GPS under PEDP4. |
Construction of additional class room CHARALJANI GPS under PEDP4. |