View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | PCC Correction |
| Field Name | Old Value | New Value |
|---|---|---|
| PCC--A. General-- |
The Project Manager is |
The Project Manager is Upazila Engineer, Shyamnagar, Satkhira. |
| PCC--A. General-- |
The Site is located at [location] and is defined in drawings No: |
The Site is located at Shyamnagar, Satkhira. |
| PCC--A. General-- |
The Procuring Entity is |
The PE is A.S.M. Shahedur Rahim, Executive Engineer, LGED Satkhira. |
| PCC--A. General-- |
The Works consist of |
The Works consist of Improvement of Ramzibonpur more-Harinagar road at Ch: 2500-3869m by BC under Shyamnagar Upazila, District : Satkhira (Road ID : 287864026), |
| PCC--A. General-- | Other documents forming part of the Contract are;
[list other documents viz. Site Investigation Reports, relevant correspondences prior to signing of the Contract agreement etc.] |
Other documents forming part of the Contract are; Site Investigation Reports, relevant correspondences prior to signing of the Contract agreement etc. |
| PCC--A. General-- | Possession of the Site to the Contractor shall be given on the following date;
[state date of possession of site] |
Possession of the Site to the Contractor shall be given on the following date : Within 07 days after signing contract. |
| PCC--B. Time Control-- |
The Start Date shall be [insert date ] |
The Start Date shall be ............................................ |
| PCC--B. Time Control-- |
The Intended Completion Date for the whole of the Works shall be [insert date] |
The Intended Completion Date for the whole of the Works shall be ...................................................... |
| PCC--B. Time Control-- |
The Contractor shall submit a Programme for the Works within [insert days] days of signing the Contract. |
The Contractor shall submit a Programmed for the Works within 10 days of signing the Contract. |
| PCC--C. Quality Control-- |
The Defects Liability Period is [state months] |
The Defects Liability Period is 12 (Twelve) months. |
| PCC--D. Cost Control-- |
The following additional events shall also be the Compensation Events: |
28. The following additional events shall also be the Compensation Events: N/A |
| PCC--D. Cost Control-- | The proportion of payments to be retained is [insert percent] percent. |
The proportion of payments to be retained is five percent. |
| PCC--D. Cost Control-- |
The amount of Liquidated Damages or in other words Delay Damages is [insert percentage] percent of final Contract price of the uncompleted Works or any part there of itâ??s per day of delay. |
The amount of Liquidated Damages or in other words Delay Damages is 0.01 percent of final Contract price of the uncompleted Works or any part there of it’s per day of delay. |
| PCC--D. Cost Control-- |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works. |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is10 percent of the final Contract price of the whole of the Works. |
| PCC--F. Termination-- | The percentage to apply to the contract value of the works not completed, representing the Procuring Entityâ??s additional cost for completing the uncompleted Works, is [state percentage] percent.
[ usually between ten (10) to twenty (20) percent depending on the nature of the Works] |
The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted Works, is 10 percent. |
| PCC--G. Disputes and Settlement-- |
The arbitration shall be conducted in the place mentioned below; |
Rubaiyat Nurul Hasan |