View IFT /PQ / REOI / RFP / PPS Notice Details
Ministry : Ministry of Local Government, Rural Development and Co-operatives Division : Local Government Division
Organization : Local Government Engineering Department (LGED) Procuring Entity Name : Office of the Executive Engineer, LGED, Satkhira
Procuring Entity Code : Procuring Entity District : Satkhira
Procurement Nature : Works Procurement Type : NCT
Event Type : Invitation for : Tender - Single Lot
Invitation Reference No. : APP ID : 33211 Tender/Proposal Status :
App ID : 33211 Tender/Proposal ID : 66268
Key Information and Funding Information :
Procurement Method : Open Tendering Method (OTM) Budget Type : Development
Source of Funds : Government
Particular Information :
Project Code : 5060 Project Name : Union Infrastructure Development Project (Khulna, Bagerhat & Sathkhira District)
Tender/Proposal Package No. and Description : UIDP(KBS)/VR(BC)-14/Sat/2016-17
Improvement of Ramzibonpur more-Harinagar road at Ch: 2500-3869m by BC under Shyamnagar Upazila, District : Satkhira (Road ID : 287864026), Salvage Amount Tk.=12,580.00
Category : Construction work;Site preparation work;Building demolition and wrecking work and earthmoving work;Test drilling and boring work;Works for complete or part construction and civil engineering work;Building construction work;Engineering works and construction works;Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork;Construction work for water projects;Construction works for plants, mining and manufacturing and for buildings relating to the oil and gas industry;Roof works and other special trade construction works;Building installation work;Electrical installation work;Insulation work;Plumbing and sanitary works;Fencing, railing and safety equipment installation work;Mechanical installations;Building completion work;Plastering work;Joinery and carpentry installation work;Floor and wall covering work;Painting and glazing work;Other building completion work;Hire of construction and civil engineering machinery and equipment with operator;Hire of cranes with operator;Hire of earthmoving equipment with operator
Scheduled Tender/Proposal Publication
Date and Time :
04-Oct-2016 15:15 Tender/Proposal Document last selling /
downloading Date and Time :
26-Oct-2016 17:00
Pre - Tender/Proposal meeting Start
Date and Time :
05-Oct-2016 15:20 Pre - Tender/Proposal meeting End
Date and Time :
16-Oct-2016 15:00
Tender/Proposal Closing
Date and Time :
27-Oct-2016 11:00 Tender/Proposal Opening
Date and Time :
27-Oct-2016 11:05
Last Date and Time for Tender/Proposal Security
Submission :
27-Oct-2016 10:45    
Information for Tenderer/Consultant :
Eligibility of Tenderer :

As per ITT.

Brief Description of Works :

UIDP(KBS)/VR(BC)-14/Sat/2016-17
Improvement of Ramzibonpur more-Harinagar road at Ch: 2500-3869m by BC under Shyamnagar Upazila, District : Satkhira (Road ID : 287864026), Salvage Amount Tk.=12,580.00

Evaluation Type : Lot wise
Document Available : Package wise
Document Fees : Package wise
Tender/Proposal Document Price (In BDT) : 2000
Mode of Payment :
Tender/Proposal Security Valid Up to : 22-Feb-2017
Tender/Proposal Valid Up to : 25-Jan-2017
Lot No. Identification of Lot Location Tender/Proposal security
(Amount in BDT)
Tentative Start Date Tentative Completion Date
01 Improvement of Ramzibonpur more-Harinagar road at Ch: 2500-3869m by BC under Shyamnagar Upazila, District : Satkhira (Road ID : 287864026), Salvage Amount Tk.=12,580.00 Shyamnagar 160000 30-Nov-2016 29-Nov-2017
Procuring Entity Details:
Name of Official Inviting Tender/Proposal : A.S.M. Shahedur Rahim Designation of Official Inviting Tender/Proposal : Executive Engineer
Address of Official Inviting Tender/Proposal :
Address: XEN Office, LGED, Satkhira
City: Satkhira
Thana: Satkhira Sadar
District: Satkhira - 9400
Country: Bangladesh
Contact details of Official Inviting Tender/Proposal :
Phone No: 0471-63413
Fax No:
The procuring entity reserves the right to accept or reject all Tenders/Proposals / Pre-Qualifications / EOIs
Note: Bank will update the payment transactions only at the end of the day, so the tenderers should make sure the securities and other payments are made at least one day before the submission date.
Documents
Amendment / Corrigendum Detail
 Amendment / Corrigendum No. :  1 
Amendment / Corrigendum Text :

PCC Correction

Field Name Old Value New Value
PCC--A. General--

The Project Manager is
[Name, address]
 

The Project Manager is Upazila Engineer, Shyamnagar, Satkhira.

PCC--A. General--

The Site is located at [location] and is defined in drawings No:
[insert numbers]
 

The Site is located at Shyamnagar, Satkhira.

PCC--A. General--

The Procuring Entity is
[Name, address]
 

The PE is A.S.M. Shahedur Rahim, Executive Engineer, LGED Satkhira.

PCC--A. General--

The Works consist of
[state brief summary]
 

The Works consist of Improvement of Ramzibonpur more-Harinagar road at Ch: 2500-3869m by BC under Shyamnagar Upazila, District : Satkhira (Road ID : 287864026),
 

PCC--A. General--

Other documents forming part of the Contract are;

[list other documents viz. Site Investigation Reports, relevant correspondences prior to signing of the Contract agreement etc.]
 

Other documents forming part of the Contract are; Site Investigation Reports, relevant correspondences prior to signing of the Contract agreement etc.

PCC--A. General--

Possession of the Site to the Contractor shall be given on the following date;

[state date of possession of site]
 

Possession of the Site to the Contractor shall be given on the following date : Within 07 days after signing contract.

PCC--B. Time Control--

The Start Date shall be [insert date ]
[it is the last date when the Contractor shall commence execution of the Works under the Contract]
 

The Start Date shall be ............................................

PCC--B. Time Control--

The Intended Completion Date for the whole of the Works shall be [insert date]
[to be calculated from the start Date]
 

The Intended Completion Date for the whole of the Works shall be ......................................................

PCC--B. Time Control--

The Contractor shall submit a Programme for the Works within [insert days] days of signing the Contract.
[usually ten (10) days or may be less]
 

The Contractor shall submit a Programmed for the Works within 10 days of signing the Contract.

PCC--C. Quality Control--

The Defects Liability Period is [state months]
[usually Defect Liability Period is twelve (12) months to cover at least one complete monsoon season].
 

The Defects Liability Period is 12 (Twelve) months.

PCC--D. Cost Control--

The following additional events shall also be the Compensation Events:
[list events or state none ]
 

28. The following additional events shall also be the Compensation Events: N/A
GCC27:
Earth Work Should be done After starting the works. If the contractors not complete the earth work, the rest item of work will not be started. Bill of earth work will be pay at the time of final bill.
The payment retained for uncompleted earth work/or any other item of work is estimated rate (In case of less quoted rate for earth work/ or any other item of work), and the payment retained for uncompleted earth / or any other item of work is quoted rate (In case of above quoted rate for earth work/ or any other item of work).
In case of running bill, the payment of front loaded item will be paid using overall above/less rate (official rate plus percentage above/less than the official rate) and the other items which are less than the overall average rate given by the contractor will be paid as per quoted rate i.e.BOQ rate.
After successful completion of contract final payment will be made using BOQ rates.
If the contract is terminated for breach of contract the payment will be made as criteria mentioned in case of running bills.
Black stone should be use in case of carpeting and seal coat work. Materials analysis should be comply for Item (A) 25 mm thick carpeting, (Item code 3.06.4.1) , (B) 25 mm thick dence carpeting, (Item code 3.06.4.2) , (C) 12 mm thick seal coat (Item code 3.10.09), and (D) 7 mm thick seal coat (Item code 3.06.3) ."

PCC--D. Cost Control--

The proportion of payments to be retained is [insert percent] percent.

 

The proportion of payments to be retained is five percent.

PCC--D. Cost Control--

The amount of Liquidated Damages or in other words Delay Damages is [insert percentage] percent of final Contract price of the uncompleted Works or any part there of itâ??s per day of delay.
[usually the percent-rate of liquidated damages is set at between 0.05 and 0.10 of ONE (1) percent of final Contract price of the uncompleted Works or any part there of itâ??s per day of delay]
Guide to application of GCC Sub Clause 28.1 above
[ Liquidated damages is equivalent to an amount to be determined in accordance with the following formula
T LD = VUW x P x n
Where;
T LD = Total amount of Liquidated Damages
VUW = Value of Uncompleted Works (i.e. works not having been completed as of the expiry of the Intended Completion Date plus the works completed after the expiry of the Intended Completion Date). VUW shall be calculated by deducting the value of the completed works under the Contract from the total Contract price.
P = Percent-rate at which the Liquidated Damages shall be imposed for every day of delay of the final Contract price of the uncompleted Works or any part there of.
n = No of days of delay for completion of works under the Contract]
 

The amount of Liquidated Damages or in other words Delay Damages is 0.01 percent of final Contract price of the uncompleted Works or any part there of it’s per day of delay.

PCC--D. Cost Control--

The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works.
[ usually the total amount of liquidated damages shall not exceed ten (10) percent of the final Contract price for the whole of the Works]
 

The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is10 percent of the final Contract price of the whole of the Works.

PCC--F. Termination--

The percentage to apply to the contract value of the works not completed, representing the Procuring Entityâ??s additional cost for completing the uncompleted Works, is [state percentage] percent.

[ usually between ten (10) to twenty (20) percent depending on the nature of the Works]
 

The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted Works, is 10 percent.

PCC--G. Disputes and Settlement--

The arbitration shall be conducted in the place mentioned below;
[state name of place with location and district ]
 

Rubaiyat Nurul Hasan
13/13 Shamoli, Road No :02, Dhaka-1207
The arbitration shall be conducted in the place mentioned below:
LGED HQ, Agargaon, Dhaka-1207".

 
Save As PDF