View IFT /PQ / REOI / RFP / PPS Notice Details
Ministry : Ministry of Local Government, Rural Development and Co-operatives Division : Local Government Division
Organization : Local Government Engineering Department (LGED) Procuring Entity Name : Office of the Executive Engineer, LGED, Jamalpur
Procuring Entity Code : Procuring Entity District : Jamalpur
Procurement Nature : Works Procurement Type : NCT
Event Type : Invitation for : Tender - Single Lot
Invitation Reference No. : APP ID 33665 Tender/Proposal Status :
App ID : 33665 Tender/Proposal ID : 66450
Key Information and Funding Information :
Procurement Method : Open Tendering Method (OTM) Budget Type : Development
Source of Funds : Government
Particular Information :
Project Code : 5-3731-5143 Project Name : Important Rural Infrastructures Development Project on Priority Basis-2
Tender/Proposal Package No. and Description : IRIDP-2/JML/DW-46
Improvement of Bakshigonj Taltola- Kukrapar road. (Ch.1000-1700m).[339074036]
Category : Site preparation work; Construction work; Works for complete or part construction and civil engineering work; Hire of construction and civil engineering machinery and equipment with operator; Construction work;Building demolition and wrecking work and earthmoving work;Test drilling and boring work;Building construction work;Engineering works and construction works;Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork;Construction work for water projects;Construction works for plants, mining and manufacturing and for buildings relating to the oil and gas industry;Roof works and other special trade construction works;Hire of cranes with operator;Hire of earthmoving equipment with operator
Scheduled Tender/Proposal Publication
Date and Time :
21-Sep-2016 13:00 Tender/Proposal Document last selling /
downloading Date and Time :
17-Oct-2016 16:00
Pre - Tender/Proposal meeting Start
Date and Time :
22-Sep-2016 10:00 Pre - Tender/Proposal meeting End
Date and Time :
13-Oct-2016 17:00
Tender/Proposal Closing
Date and Time :
18-Oct-2016 12:00 Tender/Proposal Opening
Date and Time :
18-Oct-2016 12:30
Last Date and Time for Tender/Proposal Security
Submission :
17-Oct-2016 16:00    
Information for Tenderer/Consultant :
Eligibility of Tenderer :

Only e-GP Tenderer eligible

All data as state in TDS.

Brief Description of Works :

Improvement of Bakshigonj Taltola- Kukrapar road. (Ch.1000-1700m).[339074036]

Evaluation Type : Lot wise
Document Available : Package wise
Document Fees : Package wise
Tender/Proposal Document Price (In BDT) : 1000
Mode of Payment :
Tender/Proposal Security Valid Up to : 13-Feb-2017
Tender/Proposal Valid Up to : 16-Jan-2017
Lot No. Identification of Lot Location Tender/Proposal security
(Amount in BDT)
Tentative Start Date Tentative Completion Date
01 Improvement of Bakshigonj Taltola- Kukrapar road. (Ch.1000-1700m).[339074036] Bakshiganj 100000 01-Nov-2016 30-Apr-2017
Procuring Entity Details:
Name of Official Inviting Tender/Proposal : Md. Nazrul Islam Designation of Official Inviting Tender/Proposal : Executive Engineer
Address of Official Inviting Tender/Proposal :
Address: XEN Office, LGED Bhaban, Pathalia, Jamalpur
City: Jamalpur
Thana: Jamalpur Sadar
District: Jamalpur - 2000
Country: Bangladesh
Contact details of Official Inviting Tender/Proposal :
Phone No: 0981-63698
Fax No:
The procuring entity reserves the right to accept or reject all Tenders/Proposals / Pre-Qualifications / EOIs
Note: Bank will update the payment transactions only at the end of the day, so the tenderers should make sure the securities and other payments are made at least one day before the submission date.
Documents
Amendment / Corrigendum Detail
 Amendment / Corrigendum No. :  1 
Amendment / Corrigendum Text :

Corrigendum

Field Name Old Value New Value
PCC--A. General--

The Procuring Entity is
[Name, address]
 

The Procuring Entity is
The Executive Engineer
Local Government Engineering Department
District: Jamalpur
 

PCC--A. General--

The Works consist of
[state brief summary]
 

The Works consist of The Works consist of Earth work, AS,ISG,WBM and Bituminus.Surfacing Work
 

PCC--A. General--

The Project Manager is
[Name, address]
 

The Project Manager is
Upazila Engineer
Local Government Engineering Department
Upazila:Bakshigonj
District: Jamalpur
 

PCC--A. General--

Other documents forming part of the Contract are;

[list other documents viz. Site Investigation Reports, relevant correspondences prior to signing of the Contract agreement etc.]
 

Other documents forming part of the Contract are;n/a

PCC--A. General--

Possession of the Site to the Contractor shall be given on the following date;

[state date of possession of site]
 

Possession of the Site to the Contractor shall be given on the following date;within 7 (seven) days from the signing of contract agreement.

PCC--B. Time Control--

The Start Date shall be [insert date ]
[it is the last date when the Contractor shall commence execution of the Works under the Contract]
 

The Start Date shall be within 7 (seven) days from the signing of contract agreement.

PCC--B. Time Control--

The Intended Completion Date for the whole of the Works shall be [insert date]
[to be calculated from the start Date]
 

The Intended Completion Date for the whole of the Works shall be 180days

PCC--B. Time Control--

The Contractor shall submit a Programme for the Works within [insert days] days of signing the Contract.
[usually ten (10) days or may be less]
 

The Contractor shall submit a Programme for the Works within 14 days of signing the Contract.
 

PCC--C. Quality Control--

The Defects Liability Period is [state months]
[usually Defect Liability Period is twelve (12) months to cover at least one complete monsoon season].
 

The Defects Liability Period is 12 months.
 

PCC--D. Cost Control--

The following additional events shall also be the Compensation Events:
[list events or state none ]
 

The following additional events shall also be the Compensation Events:
If the contract is terminated following the fundamental breach of conract by the contractor .
To quantify such Compensation the steps mentioned below shall apply:

(i) (i) A Compensation Assessment Committee comprising of minimum 03 (Three) members shall be formed by the Procuring Entity / Project Manager to assess the Compensation to complete the remaining works as per latest LGED rate schedule. This Assessed Compensation would be the Estimated Cost of Uncompleted Contract Quantity as per latest LGED rate schedule less the Quoted amount of the same by the Terminated Contractor representing in percent (%) w.r.t. Uncompleted Contract Amount of the Terminated Contract but in no case it shall be less than minimum 10(Ten)% of the Uncompleted Contract Amount.

(ii) The Assessed Compensation as recommended by the Compensation Assessment Committee shall be recoverable as instructed in GCC clause 47.

(ii) (iii) In case of failure to realize such Compensation by the Contractor, the Procuring Entity / Project Manager shall take necessary measure to recover the same from any dues remained in his office (Such as Performance Security,RetentionMoney,TenderSecurity,Pending Bill of other contract etc.).Furthermore If the total amount due to the Procuring Entity still exceeds any payment due to the Contractor, the difference shall be a debt payable to the Procuring Entity.
(iii)
(iv) (iv)The Procuring Entity / Project Manager shall however proceed to complete the remaining work engaging new contractor.
 

PCC--D. Cost Control--

The proportion of payments to be retained is [insert percent] percent.

The proportion of payments to be retained is 05 percent.

PCC--D. Cost Control--

The amount of Liquidated Damages or in other words Delay Damages is [insert percentage] percent of final Contract price of the uncompleted Works or any part there of itâ??s per day of delay.
[usually the percent-rate of liquidated damages is set at between 0.05 and 0.10 of ONE (1) percent of final Contract price of the uncompleted Works or any part there of itâ??s per day of delay]
Guide to application of GCC Sub Clause 28.1 above
[ Liquidated damages is equivalent to an amount to be determined in accordance with the following formula
T LD = VUW x P x n
Where;
T LD = Total amount of Liquidated Damages
VUW = Value of Uncompleted Works (i.e. works not having been completed as of the expiry of the Intended Completion Date plus the works completed after the expiry of the Intended Completion Date). VUW shall be calculated by deducting the value of the completed works under the Contract from the total Contract price.
P = Percent-rate at which the Liquidated Damages shall be imposed for every day of delay of the final Contract price of the uncompleted Works or any part there of.
n = No of days of delay for completion of works under the Contract]
 

The amount of Liquidated Damages or in other words Delay Damages is 0.10 percent of final Contract price of the uncompleted Works or any part there of it’s per day of delay.
 

PCC--D. Cost Control--

The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works.
[ usually the total amount of liquidated damages shall not exceed ten (10) percent of the final Contract price for the whole of the Works]
 

The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is10 percent of the final Contract price of the whole of the Works.
 

PCC--F. Termination--

The percentage to apply to the contract value of the works not completed, representing the Procuring Entityâ??s additional cost for completing the uncompleted Works, is [state percentage] percent.

[ usually between ten (10) to twenty (20) percent depending on the nature of the Works]
 

The percentage to apply to the contract value of the works not completed, representing the Procuring Entity’s additional cost for completing the uncompleted Works, is 10 percent.

PCC--G. Disputes and Settlement--

The arbitration shall be conducted in the place mentioned below;
[state name of place with location and district ]
 


The arbitration shall be conducted in the place mentioned below;
PD,IRIDP-2,Lged,HQ,Dhaka.
 

TDS/PDS--A. General--

 

The PE is [state name of PE]

 

 

 

The Name of the Tender is:
Brief Description of the Works:

Tender Ref:
Lot No(s):

[if there is more than one(1) lot, individual lots are to be identified in conformity with Section 6: Bill of Quantities]
 

 

The PE is The Executive Engineer
Local Government Engineering Department
District: Jamalpur
 

 

 

:
Brief Description of the Works:Improvement of Bakshigonj Taltola- Kukrapar road. (Ch.1000-1700m).[339074036]


 

TDS/PDS--B. Tender Document--

Allowed to post clarification till [Date and Time]

Allowed to post clarification till [Date and Time] N/A

TDS/PDS--C. Qualification Criteria--

The required average annual construction turnover shall be greater than Tk [insert amount] over the last [state number] years.

[ the required average annual construction  turn over is recommended to be about less than or equal to the estimated annual cash flow for the Contract; however the multiplier may vary from 0.30 to 1.00 ; [ years counting backward from the date of publication of IFT in the newspaper. The period may be  best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate)]
Example:
Estimated Contract Value:  Tk 24 lakh
Contract period:   12 months
Estimated Annual Cash Flow:  Tk 24 lakh
Required average annual construction turn over: Tk 12 lakh, using a multiplier of 0.5.
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]
 

The required average annual construction turnover shall be greater than Tk15 (Fifteen)Lacs best 5(five) years.
-Tenderer shall demonstrate the resources sufficient to meet the aggregate of the value for the individual contracts/contractual commitments, incase, participation is more than one package/lot from same procuring entity and other procuring entity(ies).
-Apart from payment received for construction works, the certified public works in progress (financialprogress) or completed year wise by relevant procuring entity(ies) will be considered as construction turnover.
 

TDS/PDS--C. Qualification Criteria--

The minimum amount of liquid assets or working capital or credit facilities of the  Tenderer shall be Tk [state amount]

[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractorâ??s monthly certificate, allowing time to prepare an invoice, for the Project Managerâ??s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Example:
Contract Value:   Tk 24 lakh
Contract period:   12 months
Assuming work time:  1 month
Invoice period:    0.5 month
Certification Time:   0.5 month
Contingency Time:   1 month

Therefore, the minimum required liquid asset will be Tk. 6 lakh, i.e. 3 months cash flow based on the above assumptions.]
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]
 

The minimum amount of liquid assets or working capital or credit facilities of the  Tenderer shall be Tk [state amount]

The minimum amount of liquid assets i.e. banking instrument or working capital or credit facilities or credit line of Credit the Tenderer shall be Tk.12,.00,000.00 (Twelve lacs ) .
-Tenderer shall demonstrate the resources sufficient to meet the aggregate of the value for the individual contracts/contractual commitments, in case, participation is more than one package/lot from same procuring entity and other procuring entity(ies).
-Banking instrument - authenticated bybank statement, savings instrument from any scheduled bank.
-Working capital - authenticated by recent past Audit Reports.
-Credit facilities - authenticated by credit sanctioned letter and bank statement of the credit account.
-Credit line - authenticated by any scheduled bank in the format as specified (Form PW2a-3), without alteration.
-Banking instrument, statement of Credit facilities and Credit line issued not earlier than 28(twenty eight) days prior to the day of the original deadline for submission of Tenders for this Contract.
 

TDS/PDS--C. Qualification Criteria--

A satisfactory completion of similar works of at least Tk [insert amount] under [state number] of contract(s) over a period of [state number] years shall be required.

[the minimum value of the similar works under a single or multiple number of  contract(s) is recommended to be between 50  and 75 percent of the estimated cost, rounded off to nearest Taka  thousand, of the proposed work. years counting backward from the date of publication of IFT in the newspaper]

[for Tenders where the package contains more than one (1) lot, this qualification requirements, shall be mentioned separately for each lot in the package]
 

The minimum specific experience as a Prime Contractor in construction works under public sector of at least 01 (One) road contract of similar nature, complexity and methods/construction technology successfully at within the last 05 (Five) years value of at least Tk30,50,000.00 (Thirty Lacs fifty thousand only). (years counting backward from the date of publication of IFT in the e-GP web portal) -Authenticated by completion certificate issued by relevant procuring entity(ies)
-Experience as a subcontractor will not be taken into account.
 

TDS/PDS--D. Tender Preparation--

Tenderer shall submit with its Tender, the following additional documents:

Tenderer shall submit with its Tender, the following additional documents:n/a

TDS/PDS--D. Tender Preparation--

The Tender Validity period shall be [state number] days.

[normally 60 to 90 days deemed reasonable]
 

The Tender Validity period shall be 90 days.

TDS/PDS--D. Tender Preparation--

The amount of the Tender Security shall be [ state amount ]
[note: Not exceeding three percent (3%) of the official estimated cost but as a fixed amount] 

 

The amount of the Tender Security shall beas per tender notice.

 