| Amendment / Corrigendum Text : | Amendment/ Corrigendum - 1 1. ITT 15.1(b) The minimum value of specific experience as a Prime Contractor in construction works of at least One (1) contract will be Tk. 480.00 (Four Hundred Eighty point Zero Zero) Lakh Instead of Tk. 700.00 (Seven Hundred point Zero Zero) Lakh. 2. ITT 16.1 (a) The required average annual construction turnover will be greater than Tk 1000.00 (One Thousand point Zero Zero) Lakh over the last 5 (Five) years. instead of Tk. 1500.00 (One Thousand Five Hundred point Zero Zero) Lakh over the last 5 (Five) years. |
| Field Name | Old Value | New Value |
|---|---|---|
| Eligibility of Consultant | A) General Instruction: |
A) General Instruction: |
| TDS/PDS--C. Qualification Criteria-- | The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 5 (Five) years. [years counting backward from the date of publication of IFT in the newspaper] The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least 1 (One) contract(s) of similar nature, complexity and methods/construction technology successfully completed within the last 5 (Five) years, with a value of at least Tk. 700.00 (Seven Hundred point Zero Zero) Lakh. [years counting backward from the date of publication of IFT in the newspaper] The contractor must have similar experince in contruction in any of the following activities 1. Construction/Resectioning/Repair of Embankment/Dyke/Cross Dam/Closiure/Earthen Road/Flood Bypass, Earth Work in Road Construction..
[the minimum number of contracts will depend upon the size and type of construction work, and the PE should make its own judgement based upon its experience in the sector and construction industry. For example, for large works, it could be one (1) contract of similar nature during the last three (3) years or five (5) years or ten (10) years (whichever appropriate); years counting backward from the date of publication of IFT in the newspaper]
[for Tenders where the package contains more than one (1) lot, this qualification requirements, only when applicable, shall be mentioned separately for each lot in the package] |
The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 5 (Five) years. [years counting backward from the date of publication of IFT in the newspaper] The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least 1 (One) contract(s) of similar nature, complexity and methods/construction technology successfully completed within the last 5 (Five) years, with a value of at least Tk. 480.00 (Four Hundred Eighty point Zero Zero) Lakh. [years counting backward from the date of publication of IFT in the newspaper] The contractor must have similar experince in contruction in any of the following activities 1. Construction/Resectioning/Repair of Embankment/Dyke/Cross Dam/Closiure/Earthen Road/Flood Bypass, Earth Work in Road Construction..
[the minimum number of contracts will depend upon the size and type of construction work, and the PE should make its own judgement based upon its experience in the sector and construction industry. For example, for large works, it could be one (1) contract of similar nature during the last three (3) years or five (5) years or ten (10) years (whichever appropriate); years counting backward from the date of publication of IFT in the newspaper]
[for Tenders where the package contains more than one (1) lot, this qualification requirements, only when applicable, shall be mentioned separately for each lot in the package] |
| TDS/PDS--C. Qualification Criteria-- | The required average annual construction turnover shall be greater than Tk 1500.00 (One Thousand Five Hundred point Zero Zero) Lakh over the last 5 (Five) years. [years counting backward from the date of publication of IFT in the newspaper]
[ the required average annual construction turn over is recommended to be about twice the estimated annual cash flow for the Contract; however the multiplier may vary from 1.0 to 2.0, the larger the Contract size the lesser the multiplier should be. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate) ; years counting backward from the date of publication of IFT in the newspaper]
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 300.00 (Three Hundred point Zero Zero) Lakh. Letter of Commitment for Bank’s Undertaking for Line of Credit must be submitted in the specific form PW3-7 (Enclosed in General Specification).
[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Therefore, the minimum required liquid asset will be Tk 4 Cr., i.e. 3 months cash flow based on the above assumptions.] |
The required average annual construction turnover shall be greater than Tk 1000.00 (One Thousand point Zero Zero) Lakh over the last 5 (Five) years. [years counting backward from the date of publication of IFT in the newspaper]
[ the required average annual construction turn over is recommended to be about twice the estimated annual cash flow for the Contract; however the multiplier may vary from 1.0 to 2.0, the larger the Contract size the lesser the multiplier should be. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate) ; years counting backward from the date of publication of IFT in the newspaper]
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 300.00 (Three Hundred point Zero Zero) Lakh. Letter of Commitment for Bank’s Undertaking for Line of Credit must be submitted in the specific form PW3-7 (Enclosed in General Specification). Otherwise the tenderer will be Non-Responsive
[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Therefore, the minimum required liquid asset will be Tk 4 Cr., i.e. 3 months cash flow based on the above assumptions.] |
| Brief Description of Goods,Works or Service | Re-Section of Embankment at Durlovpur- Bhakher Ali from Km. 12.470 to Km. 20.470 = 8000.00 M in connection with "Protection of Charbagdanga and Shajahanpur Area in Sadar Upazila of Chapainawabganj District from the erosion of the Padma River" in Upazila Shibganj & Sadar, Dist. Chapainawabganj Under Nawabganj O&M Division BWDB,Chapainawabganj During the FY 2021-2022 & 2022-2023. |
Re-Section of Embankment at Durlovpur- Bhakher Ali from Km. 12.470 to Km. 20.470 = 8000.00 M in connection with "Protection of Charbagdanga and Shajahanpur Area in Sadar Upazila of Chapainawabganj District from the erosion of the Padma River" in Upazila Shibganj & Sadar, Dist. Chapainawabganj Under Nawabganj O&M Division BWDB,Chapainawabganj During the FY 2021-2022 & 2022-2023. |