View IFT /PQ / REOI / RFP / PPS Notice Details
Ministry : Ministry of Water Resources Division :
Organization : Bangladesh Water Development Board (BWDB) Procuring Entity Name : Nawabganj O&M Division
Procuring Entity Code : Procuring Entity District : Chapai Nawabganj
Procurement Nature : Works Procurement Type : NCT
Event Type : Invitation for : Tender - Single Lot
Invitation Reference No. : EE/WDB/Chapainawabganj/Da-2/503; Date:15/03/2022 Tender/Proposal Status :
App ID : 181236 Tender/Proposal ID : 672606
Key Information and Funding Information :
Procurement Method : Open Tendering Method (OTM) Budget Type : Development
Source of Funds : Government
Particular Information :
Project Code : 224313300 Project Name : Protection of Charbagdanga and Shajahanpur Area in Sadar Upazila of Chapainawabganj District from the erosion of the Padma River
Tender/Proposal Package No. and Description : RSWP-1
Re-Section of Embankment at Durlovpur- Bhakher Ali from Km. 12.470 to Km. 20.470 = 8000.00 M in connection with "Protection of Charbagdanga and Shajahanpur Area in Sadar Upazila of Chapainawabganj District from the erosion of the Padma River" in Upazila Shibganj & Sadar, Dist. Chapainawabganj Under Nawabganj O&M Division BWDB,Chapainawabganj During the FY 2021-2022 & 2022-2023.
Category : Construction work for water projects; Works for complete or part construction and civil engineering work;
Scheduled Tender/Proposal Publication
Date and Time :
16-Mar-2022 12:00 Tender/Proposal Document last selling /
downloading Date and Time :
17-Apr-2022 11:00
Pre - Tender/Proposal meeting Start
Date and Time :
16-Mar-2022 16:00 Pre - Tender/Proposal meeting End
Date and Time :
23-Mar-2022 17:00
Tender/Proposal Closing
Date and Time :
17-Apr-2022 15:00 Tender/Proposal Opening
Date and Time :
17-Apr-2022 15:00
Last Date and Time for Tender/Proposal Security
Submission :
17-Apr-2022 11:30    
Information for Tenderer/Consultant :
Eligibility of Tenderer :

A) General Instruction:
1) Valid Trade Licence
2) TIN number.
3) VAT Registration.
4) Nationality.
5) Declaration about legal capacity to enter in to the contract.
6) Work plan, Statement of work method, equipment & Personnel
(Necessary supporting documents shall be submitted with the Tender)
B) Special Instruction:
1. In case of Working Certificate/Performance Certificate/Payment Certificate; Name of works, planned Commencement & Completion date and also Actual Completion date should be mentioned /Writen down on the certificate. It is better to submite the certificate guided by CPTU.
2. The work of the package may be totally dropped, decreased or increased as per field condition/design/administrative approval/budget allocation for which no claim will be entertained for cancellation of the tender/Issuance of work order.
3. Payment will be made subject to the availability of fund. No claim in this regard will be entertained.
4. Continuation of work could not be hampered by the bidder showing the cause of insufficient Budget Provision & Fund Allocation.
5. If the Tenderer(s) submit(s) any false/incorrect or forged certificate, the tender will be outright rejected and action as per PPR-2008 will be initiated.
6. The Procuring entity reserves the right to accept or reject any or all Tenders without assigning any reason whatsoever.
7. Letter of Commitment for Banks Undertaking for Line of Credit must be submitted in the specific form PW3-7. Otherwise Tender will be non-responsive. (Letter of Commitment enclosed in General Specification).
8. VAT/Income Taxes shall be implied as per latest circular of NBR.
9. Latest circular of CPTU & CPC of BWDB will be followed.
 

Brief Description of Works :

Re-Section of Embankment at Durlovpur- Bhakher Ali from Km. 12.470 to Km. 20.470 = 8000.00 M in connection with "Protection of Charbagdanga and Shajahanpur Area in Sadar Upazila of Chapainawabganj District from the erosion of the Padma River" in Upazila Shibganj & Sadar, Dist. Chapainawabganj Under Nawabganj O&M Division BWDB,Chapainawabganj During the FY 2021-2022 & 2022-2023.

Evaluation Type : Lot wise
Document Available : Package wise
Document Fees : Package wise
Tender/Proposal Document Price (In BDT) : 4000
Mode of Payment :
Tender/Proposal Security Valid Up to : 12-Sep-2022
Tender/Proposal Valid Up to : 15-Aug-2022
Lot No. Identification of Lot Location Tender/Proposal security
(Amount in BDT)
Tentative Start Date Tentative Completion Date
RSWP-1 Re-Section of Embankment at Durlovpur- Bhakher Ali from Km. 12.470 to Km. 20.470 = 8000.00 M in connection with "Protection of Charbagdanga and Shajahanpur Area in Sadar Upazila of Chapainawabganj District from the erosion of the Padma River" in Upazila Shibganj & Sadar, Dist. Chapainawabganj Under Nawabganj O&M Division BWDB,Chapainawabganj During the FY 2021-2022 & 2022-2023. Shibganj and Chapainawabganj Sadar Upazila 2500000 17-Jul-2022 15-Jun-2023
Procuring Entity Details:
Name of Official Inviting Tender/Proposal : MD. SARWAR JAHAN SUJAN Designation of Official Inviting Tender/Proposal : Executive Engineer
Address of Official Inviting Tender/Proposal :
Address: Nawabganj
City: Nawabganj
Thana: Nawabganj Sadar
District: Chapai Nawabganj - 6300
Country: Bangladesh
Contact details of Official Inviting Tender/Proposal :
Phone No: 0781-52268
Fax No:
The procuring entity reserves the right to accept or reject all Tenders/Proposals / Pre-Qualifications / EOIs
Note: Bank will update the payment transactions only at the end of the day, so the tenderers should make sure the securities and other payments are made at least one day before the submission date.
Documents
Amendment / Corrigendum Detail
 Amendment / Corrigendum No. :  1 
Amendment / Corrigendum Text :

Amendment/ Corrigendum - 1

1. ITT 15.1(b) The minimum value of specific experience as a Prime Contractor in construction works of at least One (1) contract will be Tk. 480.00 (Four Hundred Eighty point Zero Zero) Lakh Instead of Tk. 700.00 (Seven Hundred point Zero Zero) Lakh.

2. ITT 16.1 (a) The required average annual construction turnover will be greater than Tk 1000.00 (One Thousand point Zero Zero) Lakh over the last 5 (Five) years. instead of Tk. 1500.00 (One Thousand Five Hundred point Zero Zero) Lakh over the last 5 (Five) years.

Field Name Old Value New Value
Eligibility of Consultant

A) General Instruction:
1) Valid Trade Licence
2) TIN number.
3) VAT Registration.
4) Nationality.
5) Declaration about legal capacity to enter in to the contract.
6) Work plan, Statement of work method, equipment & Personnel
(Necessary supporting documents shall be submitted with the Tender)
B) Special Instruction:
1. In case of Working Certificate/Performance Certificate/Payment Certificate; Name of works, planned Commencement & Completion date and also Actual Completion date should be mentioned /Writen down on the certificate. It is better to submite the certificate guided by CPTU.
2. The work of the package may be totally dropped, decreased or increased as per field condition/design/administrative approval/budget allocation for which no claim will be entertained for cancellation of the tender/Issuance of work order.
3. Payment will be made subject to the availability of fund. No claim in this regard will be entertained.
4. Continuation of work could not be hampered by the bidder showing the cause of insufficient Budget Provision & Fund Allocation.
5. If the Tenderer(s) submit(s) any false/incorrect or forged certificate, the tender will be outright rejected and action as per PPR-2008 will be initiated.
6. The Procuring entity reserves the right to accept or reject any or all Tenders without assigning any reason whatsoever.
7. Letter of Commitment for Banks Undertaking for Line of Credit must be submitted in the specific form PW3-7. Otherwise Tender will be non-responsive. (Letter of Commitment enclosed in General Specification).
8. VAT/Income Taxes shall be implied as per latest circular of NBR.
9. Latest circular of CPTU & CPC of BWDB will be followed.
 

A) General Instruction:
1) Valid Trade Licence
2) TIN number.
3) VAT Registration.
4) Nationality.
5) Declaration about legal capacity to enter in to the contract.
6) Work plan, Statement of work method, equipment & Personnel
(Necessary supporting documents shall be submitted with the Tender)
B) Special Instruction:
1. In case of Working Certificate/Performance Certificate/Payment Certificate; Name of works, planned Commencement & Completion date and also Actual Completion date should be mentioned /Writen down on the certificate. It is better to submite the certificate guided by CPTU.
2. The work of the package may be totally dropped, decreased or increased as per field condition/design/administrative approval/budget allocation for which no claim will be entertained for cancellation of the tender/Issuance of work order.
3. Payment will be made subject to the availability of fund. No claim in this regard will be entertained.
4. Continuation of work could not be hampered by the bidder showing the cause of insufficient Budget Provision & Fund Allocation.
5. If the Tenderer(s) submit(s) any false/incorrect or forged certificate, the tender will be outright rejected and action as per PPR-2008 will be initiated.
6. The Procuring entity reserves the right to accept or reject any or all Tenders without assigning any reason whatsoever.
7. Letter of Commitment for Banks Undertaking for Line of Credit must be submitted in the specific form PW3-7. Otherwise Tender will be non-responsive. (Letter of Commitment enclosed in General Specification).
8. VAT/Income Taxes shall be implied as per latest circular of NBR.
9. Latest circular of CPTU & CPC of BWDB will be followed.
 

TDS/PDS--C. Qualification Criteria--

The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 5 (Five) years. [years counting backward from the date of publication of IFT in the newspaper]

The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least 1 (One) contract(s) of similar nature, complexity and methods/construction technology successfully completed within the last 5 (Five) years, with a value of at least Tk. 700.00 (Seven Hundred point Zero Zero) Lakh. [years counting backward from the date of publication of IFT in the newspaper]

The contractor must have similar experince in contruction in any of the following activities

1.  Construction/Resectioning/Repair of Embankment/Dyke/Cross Dam/Closiure/Earthen Road/Flood Bypass, Earth Work in Road Construction..

[the minimum number of contracts will depend upon the size and type of construction work, and the PE should make its own judgement based upon its experience in the sector and construction industry. For example, for large works, it could be one (1) contract of similar nature during the last three (3) years or five (5) years or ten (10) years (whichever appropriate); years counting backward from the date of publication of IFT in the newspaper]
 

[for Tenders where the package contains more than one (1) lot, this qualification requirements, only when applicable, shall be mentioned separately for each lot in the package]
[the minimum value of the similar works is recommended to be between 50 and 75 percent of the estimated cost of the proposed work]

 

The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 5 (Five) years. [years counting backward from the date of publication of IFT in the newspaper]

The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least 1 (One) contract(s) of similar nature, complexity and methods/construction technology successfully completed within the last 5 (Five) years, with a value of at least Tk. 480.00 (Four Hundred Eighty point Zero Zero) Lakh. [years counting backward from the date of publication of IFT in the newspaper]

The contractor must have similar experince in contruction in any of the following activities

1.  Construction/Resectioning/Repair of Embankment/Dyke/Cross Dam/Closiure/Earthen Road/Flood Bypass, Earth Work in Road Construction..

[the minimum number of contracts will depend upon the size and type of construction work, and the PE should make its own judgement based upon its experience in the sector and construction industry. For example, for large works, it could be one (1) contract of similar nature during the last three (3) years or five (5) years or ten (10) years (whichever appropriate); years counting backward from the date of publication of IFT in the newspaper]
 

[for Tenders where the package contains more than one (1) lot, this qualification requirements, only when applicable, shall be mentioned separately for each lot in the package]
[the minimum value of the similar works is recommended to be between 50 and 75 percent of the estimated cost of the proposed work]

 

TDS/PDS--C. Qualification Criteria--

The required average annual construction turnover shall be greater than Tk 1500.00 (One Thousand Five Hundred point Zero Zero) Lakh over the last 5 (Five) years. [years counting backward from the date of publication of IFT in the newspaper]

[ the required average annual construction turn over is recommended to be about twice the estimated annual cash flow for the Contract; however the multiplier may vary from 1.0 to 2.0, the larger the Contract size the lesser the multiplier should be. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate) ; years counting backward from the date of publication of IFT in the newspaper]
Example:


Estimated Contract Value: Tk 24 Cr.
Contract period: 18 months
Estimated Annual Cash Flow: Tk 16 Cr.
Required average annual construction turn over: Tk 24 Cr., using a multiplier of 1.5.
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]

  

The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 300.00 (Three Hundred point Zero Zero) Lakh. Letter of Commitment for Bank’s Undertaking for Line of Credit must be submitted in the specific form PW3-7 (Enclosed in General Specification).

[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Example:


Contract Value: Tk 24 Cr.
Contract period: 18 months
Assuming work time: 1 month
Invoice period: 0.5 month
Certification Time: 0.5 month
Contingency Time: 1 month

Therefore, the minimum required liquid asset will be Tk 4 Cr., i.e. 3 months cash flow based on the above assumptions.]
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]

 

The required average annual construction turnover shall be greater than Tk 1000.00 (One Thousand point Zero Zero) Lakh over the last 5 (Five) years. [years counting backward from the date of publication of IFT in the newspaper]

[ the required average annual construction turn over is recommended to be about twice the estimated annual cash flow for the Contract; however the multiplier may vary from 1.0 to 2.0, the larger the Contract size the lesser the multiplier should be. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate) ; years counting backward from the date of publication of IFT in the newspaper]
Example:


Estimated Contract Value: Tk 24 Cr.
Contract period: 18 months
Estimated Annual Cash Flow: Tk 16 Cr.
Required average annual construction turn over: Tk 24 Cr., using a multiplier of 1.5.
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]

  

The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 300.00 (Three Hundred point Zero Zero) Lakh. Letter of Commitment for Bank’s Undertaking for Line of Credit must be submitted in the specific form PW3-7 (Enclosed in General Specification). Otherwise the tenderer will be Non-Responsive

[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Example:


Contract Value: Tk 24 Cr.
Contract period: 18 months
Assuming work time: 1 month
Invoice period: 0.5 month
Certification Time: 0.5 month
Contingency Time: 1 month

Therefore, the minimum required liquid asset will be Tk 4 Cr., i.e. 3 months cash flow based on the above assumptions.]
[for Tenders where the package contains more than one (1) lot, this qualification requirements shall be mentioned separately for each lot in the package]

 

Brief Description of Goods,Works or Service

Re-Section of Embankment at Durlovpur- Bhakher Ali from Km. 12.470 to Km. 20.470 = 8000.00 M in connection with "Protection of Charbagdanga and Shajahanpur Area in Sadar Upazila of Chapainawabganj District from the erosion of the Padma River" in Upazila Shibganj & Sadar, Dist. Chapainawabganj Under Nawabganj O&M Division BWDB,Chapainawabganj During the FY 2021-2022 & 2022-2023.

Re-Section of Embankment at Durlovpur- Bhakher Ali from Km. 12.470 to Km. 20.470 = 8000.00 M in connection with "Protection of Charbagdanga and Shajahanpur Area in Sadar Upazila of Chapainawabganj District from the erosion of the Padma River" in Upazila Shibganj & Sadar, Dist. Chapainawabganj Under Nawabganj O&M Division BWDB,Chapainawabganj During the FY 2021-2022 & 2022-2023.

 
Save As PDF