View IFT /PQ / REOI / RFP Notice Details
Amendment / Corrigendum No. : 3
|
|
Amendment / Corrigendum Text : | OK |
Field Name | Old Value | New Value | |||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
PCC--.-- | The amount of Liquidated Damages is 0.10 of ONE (1) percent of the contract value of the undelivered Goods or any part thereof delivered after expiry of the Delivery and Completion Schedule or extended Delivery and Completion Schedule, as applicable, per day of delay.
Guide to application of GCC Sub Clause 35.1 above
The maximum amount of Liquidated Damages for the undelivered Goods or any part thereof is ten (10) percent of the final Contract Price of the whole of the Goods and related services. |
The amount of Liquidated Damages is 0.10 of ONE (1) percent of the contract value of the undelivered Goods or any part thereof delivered after expiry of the Delivery and Completion Schedule or extended Delivery and Completion Schedule, as applicable, per day of delay.
Guide to application of GCC Sub Clause 35.1 above
The maximum amount of Liquidated Damages for the undelivered Goods or any part thereof is ten (10) percent of the final Contract Price of the whole of the Goods and related services. |
|||||||||||||||
PCC--.-- | The method and conditions of payment to be made to the Supplier under this Contract shall be as follows: (a) Advance Payment: Not applicable. (b) Partial Supply and Partial Payment is allowed. For any Payment, i) delivery order against pre-delivery inspection report, ii) post-delivery inspection report, iii) Manufacturer warranty certificate, R&I and acceptance report from Procuring Entity (PE) have to be submitted.
|
The method and conditions of payment to be made to the Supplier under this Contract shall be as follows: (a) Advance Payment: Not applicable. (b) Partial Supply and Partial Payment is NOT allowed. For any Payment, i) delivery order against pre-delivery inspection report, ii) post-delivery inspection report, iii) Manufacturer warranty certificate, R&I and acceptance report from Procuring Entity (PE) have to be submitted. NO OF CONSIGNMENT -SINGLE |
Amendment / Corrigendum No. : 2
|
|
Amendment / Corrigendum Text : | OK |
Amendment / Corrigendum/ Addendum No. : | 2 | ||||
S. No. | File Name | File Description | File Size (in KB) |
||
---|---|---|---|---|---|
1 | GTP ACSR Grosbeak.pdf | GTP SPECIFICATION | 593414 |
Amendment / Corrigendum No. : 1
|
|
Amendment / Corrigendum Text : | ok |
Amendment / Corrigendum/ Addendum No. : | 1 | ||||
S. No. | File Name | File Description | File Size (in KB) |
||
---|---|---|---|---|---|
1 | Tech spec of ACSR Grosbeak for RANGPDP.pdf | Tech spec of ACSR Grosbeak for RANGPDP | 593414 |