Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Due to unavoidable circumstances, a corrigendum has been made in "Section No.2: Tender Data Sheet" and "Section No.6: Bill of Quantities (Part-1)". Please use "Bill of Quantities (Part-1) (Corrected)" form insted of "Bill of Quantities" form and follow the corrected TDS. |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 27/09/2022 12:00 | 02/10/2022 12:00 |
| Eligibility of Consultant | 1. Tenderer must has to be registered on e-GP Portal with a valid trade license, TIN certificate. 2. Tenderer only from Bangladesh can participate to the tender. 3. Tenderer must need to submit similar nature work certificate, annual construction turnover certificate and liquid assets certificate. 4. Payment will be made after availability of fund. 5. Any individual Tender (s)/firm (s) who fulfill the qualification (s) criteria stipulated in the Standard Tender Document including Tender data sheet and PPR-2008. 6.Tenderer must need to be submitted line of credit certificate in PW3-7 prescribed format which is attached n the general section of this tender. 7. Work certificate which is issued by the PE (Procuring Entity) only is considered for turnover calculation. Other work certificates are not being considered. 8. Tender evaluation will be conducted by the basis of uploaded documents of tenderer. Outside or offline documents will not being considered 9. Contractor must need to take still pictures and video before starting the work and after completion of work byhis/ her own cost. These still pictures and videos need to enclose with the bill of work. |
1. Tenderer must has to be registered on e-GP Portal with a valid trade license, TIN certificate. 2. Tenderer only from Bangladesh can participate to the tender. 3. Tenderer must need to submit similar nature work certificate, annual construction turnover certificate and liquid assets certificate. 4. Payment will be made after availability of fund. 5. Any individual Tender (s)/firm (s) who fulfill the qualification (s) criteria stipulated in the Standard Tender Document including Tender data sheet and PPR-2008. 6.Tenderer must need to be submitted line of credit certificate in PW3-7 prescribed format which is attached n the general section of this tender. 7. Work certificate which is issued by the PE (Procuring Entity) only is considered for turnover calculation. Other work certificates are not being considered. 8. Tender evaluation will be conducted by the basis of uploaded documents of tenderer. Outside or offline documents will not being considered 9. Contractor must need to take still pictures and video before starting the work and after completion of work byhis/ her own cost. These still pictures and videos need to enclose with the bill of work. |
| Opening Date & Time | 27/09/2022 14:00 | 02/10/2022 14:00 |
| Last date & time for Tender/Proposal Security Submission | 27/09/2022 13:00 | 02/10/2022 13:00 |
| Closing Date & Time | 27/09/2022 14:00 | 02/10/2022 14:00 |
| TDS/PDS--C. Qualification Criteria-- |
The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 5 (five) years. The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least 1 (One) contract of similar nature, complexity and methods/construction technology successfully completed within the last 5 (five) years, each with a value of at least Tk 900.00 lakh (Taka Seven hundred Lakh) lakh only. Similar Works mean construction of regulator, sluice gate, combine hydaulic structure, barrage |
The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 5 (five) years. The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least 1 (One) contract of similar nature, complexity and methods/construction technology successfully completed within the last 5 (five) years, each with a value of at least Tk 850.00 lakh (Taka Eight hundred Fifty Lakh) only. Construction/repair of regulator/sluice/ weir/spillway/rubber dam/syphon/aqucduct/barrage/combined water control structure/hydraulic elevator dam/ inlet/outlet. |
| TDS/PDS--C. Qualification Criteria-- | The required average annual construction turnover shall be greater than Tk 1700.00 Lakh (Taka One thousand Seven hundred lakh) only over the last 5(five) years. [Years counting backward from the date of publication of IFT in the newspaper] The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 900.00 lakh (Taka Seven hundred Lakh) lakh only. Strictly, Credit Commitment (s) substantiated by any scheduled Bank of Bangladesh in the format as specified (Form PW3-7), without alteration, issued not earlier than 28 (Twenty Eight) days prior to the day of the original deadline for submission of this Tender, will be accepted. The Credit line format is uploaded in section-8 . |
The required average annual construction turnover shall be greater than Tk 1700.00 Lakh (Taka One thousand Seven hundred lakh) only over the last 5(five) years. [Years counting backward from the date of publication of IFT in the newspaper] The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk 850.00 lakh (Taka Eight hundred Fifty Lakh) only. Strictly, Credit Commitment (s) substantiated by any scheduled Bank of Bangladesh in the format as specified (Form PW3-7), without alteration, issued not earlier than 28 (Twenty Eight) days prior to the day of the original deadline for submission of this Tender, will be accepted. The Credit line format is uploaded in section-8 . |
| Brief Description of Goods,Works or Service | Construction of 1 No. (8-Vent) Regulator on Banmi Khal at Anantopur area in Upazila-Ulipur, District-Kurigram |
Construction of 1 No. (8-Vent) Regulator on Banmi Khal at Anantopur area in Upazila-Ulipur, District-Kurigram |
| Amendment / Corrigendum/ Addendum No. : | 1 | ||||
| S. No. | File Name | File Description | File Size (in KB) |
||
|---|---|---|---|---|---|
| 1 | Design regulator.pdf | Design | 2328988 | ||