| TDS/PDS--C. Qualification Criteria--
|
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be BDT. 2,00,00,000/- ( Tk.Two core) only.
Tenderers shall submit the liquid asset only supported by any of the following documents:
(a) Working Capital: authenticated by Audit Report not earlier than FY 2020-2021.
(b) Credit line(s): authenticated by any scheduled Bank of Bangladesh shall be furnished unconditional credit line without alternation in accordance with the form e-PW3-7 uploaded in Section:9-Drawing.
(c) Credit Facilities: authenticated by credit sanctioned letter and bank statement of the credit amount from any scheduled bank of Bangladesh issued not earlier than 28 days prior to the day of the original deadline for submission of Tenders for this contract.
(d) Bank balance: Substantiated by up-to-date bank statement showing the required amount at least for 02 (two) consecutive days with day end closing balance from any scheduled bank of Bangladesh issued not earlier than 28 days prior to the day of the original deadline for submission of tender for this contract. |
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be BDT. 15,00,000/- ( Tk. Fifteen Lakh) only.
Tenderers shall submit the liquid asset only supported by any of the following documents:
(a) Working Capital: authenticated by Audit Report not earlier than FY 2020-2021.
(b) Credit line(s): authenticated by any scheduled Bank of Bangladesh shall be furnished unconditional credit line without alternation in accordance with the form e-PW3-7 uploaded in Section:9-Drawing.
(c) Credit Facilities: authenticated by credit sanctioned letter and bank statement of the credit amount from any scheduled bank of Bangladesh issued not earlier than 28 days prior to the day of the original deadline for submission of Tenders for this contract.
(d) Bank balance: Substantiated by up-to-date bank statement showing the required amount at least for 02 (two) consecutive days with day end closing balance from any scheduled bank of Bangladesh issued not earlier than 28 days prior to the day of the original deadline for submission of tender for this contract.
|
| TDS/PDS--C. Qualification Criteria--
|
The minimum capacity shall be: BDT.1,60,00,000.00 (Tk. One core Sixty lakh) only.
The following formulae shall be used to calculate the Tender Capacity
Assessed Tender Capacity = (A*N*1.5-B)
Where
A=Maximum value of Works performed in any one year during last five years
N= Completion time of the proposed work in years
B= Value of Existing commitments and works to be completed during the next N Years
For Tenders where the package contains more than one (1) Lot, this qualification requirement shall be mentioned separately for each lot in the package
Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one) |
The minimum capacity shall be: BDT.18,00,000.00 (Tk. Eighteen lakh) only.
The following formulae shall be used to calculate the Tender Capacity
Assessed Tender Capacity = (A*N*1.5-B)
Where
A=Maximum value of Works performed in any one year during last five years
N= Completion time of the proposed work in years
B= Value of Existing commitments and works to be completed during the next N Years
For Tenders where the package contains more than one (1) Lot, this qualification requirement shall be mentioned separately for each lot in the package
Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one)
|
| TDS/PDS--C. Qualification Criteria--
|
The required average annual construction turnover shall be greater than BDT. 2,10,00,000.00 ( Tk. Two core ten lakh) only over the last best three (3) years in the last five (5)years.
Note: 1. Years will be counted backward from the date of publication of IFT in the e-GP system;
2. Payment received Certificate for construction works, issued by relevant Procuring Entity(ies) will be considered as construction turnover |
The required average annual construction turnover shall be greater than BDT. 50,00,000.00 ( Tk. Fifty lakh) only over the last best three (3) years in the last five (5)years.
Note: 1. Years will be counted backward from the date of publication of IFT in the e-GP system;
2. Payment received Certificate for construction works, issued by relevant Procuring Entity(ies) will be considered as construction turnover
|
| TDS/PDS--C. Qualification Criteria--
|
A satisfactory completion of similar works of at least Tk 1,50,00,000/- (Tk. One Core Fifty lakh) under maximum 01 (one) contract over a period of 5 (Five) years shall be required. i.e.yearscounting backward from the date of publication of IFT in the e-GP system |
A satisfactory completion of similar works of at least Tk 18,00,000/- (Tk. Eighteen lakh) under maximum 01 (one) contract over a period of 5 (Five) years shall be required. i.e.yearscounting backward from the date of publication of IFT in the e-GP system
|