View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | Last Date and Time for Tender Security Submission Change |
| Field Name | Old Value | New Value |
|---|---|---|
| Last date & time for Tender/Proposal Security Submission | 01/01/2023 13:30 | 11/01/2023 14:30 |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Tender submission date changing for participating more tenderers. |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 01/01/2023 12:00 | 11/01/2023 12:00 |
| Eligibility of Consultant | Tenderer Must have experience in power transformer (132 kV or above) Transportation, Installation, Testing & Commissioning works within last 05 years. |
Tenderer Must have experience in power transformer (132 kV or above) Transportation, Installation, Testing & Commissioning works within last 05 years. |
| Opening Date & Time | 01/01/2023 14:00 | 11/01/2023 15:00 |
| Closing Date & Time | 01/01/2023 14:00 | 11/01/2023 15:00 |
| Brief Description of Goods,Works or Service | Dismantling of 01 No. 25/41 MVA Transformer and transportation, Installation, Testing & Commissioning of 01 No. 132/33 kV, 50/75MVA, Power Transformer at Patuakhali 132/33 kV Grid SS Under GMD, PGCB, Barishal. |
Dismantling of 01 No. 25/41 MVA Transformer and transportation, Installation, Testing & Commissioning of 01 No. 132/33 kV, 50/75MVA, Power Transformer at Patuakhali 132/33 kV Grid SS Under GMD, PGCB, Barishal. |