| PCC--A. General--
|
|
1. |
INTRODUCTIONS: The Contractor shall perform CONSTRUCTION OF 12 INCHES DIAMETER, 140 PSIG PRESSURE AND 8.0 K.M. LONG DISTRIBUTION-MAIN GAS PIPELINE FROM GAZARIA TBS TO ABDUL MONEM ECONOMIC ZONE LIMITED in accordance with Route Maps, Alignment sheets, Special drawings for Highway/railway crossings, standard drawings, Standard technical specifications of TITAS GAS and other terms and conditions of the Tender document.
|
|
2. |
SCOPE OF WORK TO BE EXECUTED BY THE CONTRACTOR: The Contractor is to mobilize equipment and personnel at site. Materials listed in the bill of materials will be issued free of cost from the Company's store at different places, and Contractor shall convey, haul or otherwise transport those materials to job site. The Contractor shall provide pipe storage yards along the pipeline route from which pipe will be strung along the ROW. Contractor shall provide, among others but not restricted to the following services related to the Construction of the Natural Gas Pipeline: (a) Clear and grade the ROW SPECIFICATION NO. TR. CON. 0130.0; (b) String the line pipe & casing pipe along the ROW; (c) Excavate the trench mechanically; (d) Weld pipe joints, valves, fittings, etc.; (e) Apply protective coating to pipeline; (f) Bend pipe joints for sag over & side bends of the pipe; (g) Lowering and tie-in pipeline segments; (h) Backfill the trench with tamped backfill; (i) Grade and clean; (j) Cleaning, purging testing, of pipeline; (k) Holiday Inspection. (l) Construct bored, cased, uncased pipeline crossing of roads/rail roads, if required; (m) Perform soil/sub-soil test, Construction of foundations, basements, stairs, walkways, fencings etc. as per requirement. (n) Unit supports, valve pit Construction; and (o) Contractor shall provide all fuels, materials (other than those of free issue) and services required for this work.
|
|
3. |
The work shall have to be done in the following specifications: 3(1) The pipeline shall have a minimum cover as per standard drawing and design from the top of pipeline surface. 3(2) Hauling of Pipes and Materials: Technical Specification TR CON 0010.0 shall govern for handling, hauling, stringing and storage of pipe and materials transportation and storage. 3(3) Excavation of trench and back filling, finish grade and clean up of ROW. 3(4) Protective Coating: All pipes, fittings and field joints are to receive a protective coating as specified in technical specification TR CON 0040. 0. 3(5) Concrete Coating for negative buoyancy required by the pipe line in the form of continuous Reinforced Concrete Coating (RCC) for special crossings shall be provided in accordance with technical specification on TR. CON 0050.0 3(6) Welding and Welding Inspection: Butt welded joints in the line pipes and fittings done above/or below ground shall include beveling, cutting, fabrication, end wall thickness reducing/ re-beveling required for any reason and cost of all electrode Welding and the inspection of welding shall be governed by Technical specification TR. CON. 0030.0. 3(7) Special Crossing: Pipeline crossing of roads/highways, any water way crossing are discussed in Technical Specification TR. CON. 0080.0. Each crossing shall be performed in accordance with specific standard drawing for each crossing. 3(8)Tie-in: Tie-in means, Tie-in of the newly constructed pipe line with existing pipe line as per drawing & technical specification. Existing pipeline shall have to be cut in Cold Cutting Method. 3(9) Commissioning: On acceptance by the Engineer after cleaning, purging and testing tie-in of all sections of the line, the Contractor shall provide assistance to the Engineer in commissioning the pipeline without extra charge to the Company.
|
|
4. |
PROVISION BY THE COMPANY: The Company shall provide the followings in connection with the work: 4(1) Right of way (ROW) for construction of pipeline and valve stations, as shown in alignment sheets. 4(2) Line pipe, pipeline fittings, coating & wrapping materials, valves, vent stacks, insulating joints, thinsulator, casing seal etc. 4(3) Permission for road crossings. 4(4) Destructive Testing 4(5) Recorder for final testing on intimation from the Contractor.
|
|
5. |
PROVISION BY THE CONTRACTOR: The Contractor shall provide among others but not limited to the following for efficient execution of the work: 5(1) All necessary machinery & equipment, accessories, tools etc. 5(2) All consumable such as welding electrodes, paints, POL (Petroleum, Oil and Lubricants), skids, water for testing, Nitrogen etc. The category of electrodes to be used are : 3.15 mm dia to 3.25 mm dia Fleet weld 5P or equivalent Electrode as per AWS A5.1-69 of Code E 6010. 4.00 mm dia shield Arc-85 or equivalent Electrode as per AWS A5.5-69 of Code E 7010. 4.8 mm or 5.00 mm dia shield Arc-85 or equivalent Electrode as per AWS A 5.5-69 of Code E 7010. 5(3) All materials for Civil Works. 5(4) Required manpower. 5(5) Access to ROW. 5(6) Electricity for lighting and drinking water etc. at work site. 5(7) 2 (two) chauffeur driven 7 seated Air Conditioned Microbus and 1 (one) chauffeur driven Air Conditioned SUV with POL (Petroleum, Oil and Lubricants) for use of TGTDCLs personnel for the entire period of execution of the work until completion. The vehicle shall be in good running condition and should be 2014 or later model. In the event of any malfunction of the vehicle, a replacement shall be provided forthwith. In failure of supply of these vehicles, tk. 10,000.00 per day per vehicle will be deducted from contractor's bill. 5(8) Site offices with supply of sufficient drinking and running water at places suitably located of the construction site. The offices shall be air-conditioned with well furnished including toilet, washroom and accommodation for site visitors along with refreshment facilities. Rental agreement for site office and storage yard shall have to submit to Engineer in Charge.
|
|
6. |
Supply 1 (one) laptop and 3 (three) desktop computers (Dell/HP/Asus/Acer/Panasonic with intel core i7 or similar quality), 3 (three) printers (HP laserjet Pro M400 series) and 1 (one) mobile set for communication (LTE) 5(10) Provide 10 (ten) nos. of best quality crash proof helmets and 10 (ten) pairs of safety boots (Bata or similar quality) for Titas supervisory personnel working at site. Approval must be taken from the appropriate authority before supply of these items. 5(11) The Contractor shall supply all as-built drawings, including GPS data of the new pipeline, bends, valves under this contract. Upon completion of the work the Contractor shall make available 1(one) set reproducible (on tracing paper); 5(five) copies of each print and soft copy in pen-drive. As-built drawings are to be delivered to the Office of the Deputy General Manager, Pipeline Construction Department, Titas Gas Transmission & Distribution Co, Ltd. 105, Kazi Nazrul Islam Avenue Dhaka-1215, within 30 (thirty) days of the work completion
|
|
7. |
COSTS OF TEST / RETEST: 6(1) Cost of Repair: The cost of repairing a defect and of re-testing the pipeline shall be borne by the Contractor unless the Contractor is able to satisfy the Engineer that the defect was caused by circumstances beyond his control or otherwise specified in the schedule of rates. 6(2) Installation of Recorder: The test recorder will be provided by the Company in the first instance free of charge. The Company will Charge to the Contractor an amount of TK. 5,000.00 (Five Thousand Only) for every retest. If there is unnecessary delay or if the recorder cannot be installed because of default on the part of the Contractor, an amount of TK.1,000.00 (One Thousand Only) shall be charged to the Contractor for each such case. Safe keeping of the recorder is the responsibility of the Contractor for the period it remains installed in the pipeline laid by the Contractor. 7(0) Supply of PPE (Personal Protective Equipment) for both TGTDCLs & Contractors personnel during the construction period have to be made by the Contractor at his own cost. 8(0) The contractor will take necessary steps as a representative of TGTDCL to get permissions from RHD and Explosive Department, provided that all required fees and corresponding will be made by the PE.
|
|
8. |
Civil Works: Site improvement with carted earth, excavation for foundation and Back filling, Brick flat soling & C.C. works, Construction of retaining wall with bricks and cement mortar, R.C.C works (1:2:4) with picked jhama brick chips and stone chips, having minimum cylinder crushing strength 17MPa at 28(twenty eight) days. Fencing with MS angle, flat bar, chain link mesh, Barbed wire as well as dismantling and re-fixing of existing fencing.
|
|
|
1. |
INTRODUCTIONS: The Contractor shall perform SHIFTING OF EXISTING 2-8 INCHES DIAMETER 4.650 KM LONG DISTRIBUTION GAS PIPELINE AND 3/4-6 INCHES DIAMETER 0.396 KM LONG SERVICE GAS PIPELINE ALONG HATIRJHEEL (RAMPURA BRIDGE)-SHEKHERJAIGA-AMULIA-DEMRA ROAD (WITH LINK TO TARABO AND CHITTAGONG ROAD) 4 LANE HIGHWAY PROJECT in accordance with Route Maps, Alignment sheets, Special drawings for Highway/railway crossings, standard drawings, Standard technical specifications of TITAS GAS and other terms and conditions of the Tender document.
|
|
2. |
SCOPE OF WORK TO BE EXECUTED BY THE CONTRACTOR: The Contractor is to mobilize equipment and personnel at site. Materials listed in the bill of materials will be issued free of cost from the Company's store at different places, and Contractor shall convey, haul or otherwise transport those materials to job site. The Contractor shall provide pipe storage yards along the pipeline route from which pipe will be strung along the ROW. Contractor shall provide, among others but not restricted to the following services related to the Construction of the Natural Gas Pipeline: (a) Clear and grade the ROW SPECIFICATION NO. TR. CON. 0130.0; (b) String the line pipe & casing pipe along the ROW; (c) Excavate the trench mechanically; (d) Weld pipe joints, valves, fittings, etc.; (e) Apply protective coating to pipeline; (f) Bend pipe joints for sag over & side bends of the pipe; (g) Lowering and tie-in pipeline segments; (h) Backfill the trench with tamped backfill; (i) Grade and clean; (j) Cleaning, purging testing, of pipeline; (k) Holiday Inspection. (l) Construct bored, cased, uncased pipeline crossing of roads/rail roads, if required; (m) Perform soil/sub-soil test, Construction of foundations, basements, stairs, walkways, fencings etc. as per requirement. (n) Unit supports, valve pit Construction; and (o) Contractor shall provide all fuels, materials (other than those of free issue) and services required for this work.
|
|
3. |
The work shall have to be done in the following specifications: 3(1) The pipeline shall have a minimum cover as per standard drawing and design from the top of pipeline surface. 3(2) Hauling of Pipes and Materials: Technical Specification TR CON 0010.0 shall govern for handling, hauling, stringing and storage of pipe and materials transportation and storage. 3(3) Excavation of trench and back filling, finish grade and clean up of ROW. 3(4) Protective Coating: All pipes, fittings and field joints are to receive a protective coating as specified in technical specification TR CON 0040. 0. 3(5) Concrete Coating for negative buoyancy required by the pipe line in the form of continuous Reinforced Concrete Coating (RCC) for special crossings shall be provided in accordance with technical specification on TR. CON 0050.0 3(6) Welding and Welding Inspection: Butt welded joints in the line pipes and fittings done above/or below ground shall include beveling, cutting, fabrication, end wall thickness reducing/ re-beveling required for any reason and cost of all electrode Welding and the inspection of welding shall be governed by Technical specification TR. CON. 0030.0. 3(7) Special Crossing: Pipeline crossing of roads/highways, any water way crossing are discussed in Technical Specification TR. CON. 0080.0. Each crossing shall be performed in accordance with specific standard drawing for each crossing. 3(8)Tie-in: Tie-in means, Tie-in of the newly constructed pipe line with existing pipe line as per drawing & technical specification. Existing pipeline shall have to be cut in Cold Cutting Method. 3(9) Commissioning: On acceptance by the Engineer after cleaning, purging and testing tie-in of all sections of the line, the Contractor shall provide assistance to the Engineer in commissioning the pipeline without extra charge to the Company.
|
|
4. |
PROVISION BY THE COMPANY: The Company shall provide the followings in connection with the work: 4(1) Right of way (ROW) for construction of pipeline and valve stations, as shown in alignment sheets. 4(2) Line pipe, pipeline fittings, coating & wrapping materials, valves, vent stacks, insulating joints, thinsulator, casing seal etc. 4(3) Permission for road crossings. 4(4) Destructive Testing 4(5) Recorder for final testing on intimation from the Contractor.
|
|
5. |
PROVISION BY THE CONTRACTOR: The Contractor shall provide among others but not limited to the following for efficient execution of the work: 5(1) All necessary machinery & equipment, accessories, tools etc. 5(2) All consumable such as welding electrodes, paints, POL (Petroleum, Oil and Lubricants), skids, water for testing, Nitrogen etc. The category of electrodes to be used are : 3.15 mm dia to 3.25 mm dia Fleet weld 5P or equivalent Electrode as per AWS A5.1-69 of Code E 6010. 4.00 mm dia shield Arc-85 or equivalent Electrode as per AWS A5.5-69 of Code E 7010. 4.8 mm or 5.00 mm dia shield Arc-85 or equivalent Electrode as per AWS A 5.5-69 of Code E 7010. 5(3) All materials for Civil Works. 5(4) Required manpower. 5(5) Access to ROW. 5(6) Electricity for lighting and drinking water etc. at work site. 5(7) 2 (two) chauffeur driven 7 seated Air Conditioned Microbus with POL (Petroleum, Oil and Lubricants) for use of TGTDCLs personnel for the entire period of execution of the work until completion. The vehicle shall be in good running condition and should be 2010 or later model. In the event of any malfunction of the vehicle, a replacement shall be provided forthwith. In failure of supply of these vehicles, tk. 10,000.00 per day per vehicle will be deducted from contractor's bill. 5(8) Site offices with supply of sufficient drinking and running water at places suitably located of the construction site. The offices shall be well furnished including toilet, washroom and accommodation for site visitors along with refreshment facilities. Rental agreement for site office and storage yard shall have to submit to Engineer in Charge.
|
|
6. |
6(1) The Contractor shall supply all as-built drawings, including GPS data of the new pipeline, bends, valves under this contract. Upon completion of the work the Contractor shall make available 1(one) set reproducible (on tracing paper); 5(five) copies of each print and soft copy in pen-drive. As-built drawings are to be delivered to the Office of the Deputy General Manager, Pipeline Construction Department, Titas Gas Transmission & Distribution Co, Ltd. 105, Kazi Nazrul Islam Avenue Dhaka-1215, within 30 (thirty) days of the work completion
|
|
7. |
COSTS OF TEST / RETEST: 7(1) Cost of Repair: The cost of repairing a defect and of re-testing the pipeline shall be borne by the Contractor unless the Contractor is able to satisfy the Engineer that the defect was caused by circumstances beyond his control or otherwise specified in the schedule of rates. 7(2) Installation of Recorder: The test recorder will be provided by the Company in the first instance free of charge. The Company will Charge to the Contractor an amount of TK. 5,000.00 (Five Thousand Only) for every retest. If there is unnecessary delay or if the recorder cannot be installed because of default on the part of the Contractor, an amount of TK.1,000.00 (One Thousand Only) shall be charged to the Contractor for each such case. Safe keeping of the recorder is the responsibility of the Contractor for the period it remains installed in the pipeline laid by the Contractor.
|
|
8. |
8(1) The contractor will take necessary steps as a representative of TGTDCL to get permissions from RHD and Explosive Department, provided that all required fees and corresponding will be made by the PE.
8(2) Civil Works: Site improvement with carted earth, excavation for foundation and Back filling, Brick flat soling & C.C. works, Construction of retaining wall with bricks and cement mortar, R.C.C works (1:2:4) with picked jhama brick chips and stone chips, having minimum cylinder crushing strength 17MPa at 28(twenty eight) days. Fencing with MS angle, flat bar, chain link mesh, Barbed wire as well as dismantling and re-fixing of existing fencing.
|
|