| TDS/PDS--C. Qualification Criteria--
|
15.1(a) The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 10 (eight) years. Years counting backward from the date of publication of IFT.
15.1 (b) The minimum specific experience as a Prime Contractor or Management Contractor in construction of Road Works in a single contract of similar nature, complexity and methods/construction technology successfully completed within the last 5 (five) years (Years counting backward from the date of publication of IFT with a value of at least Tk. 35.00 crore (Thirty five crore) only in single contract. The work (the single contract) must be included with DBS Base/Wearing Course of minimum value Tk. 10.00 (Ten) Crore or minimum quantity 5000 cum, Aggregate Base Type-I Tk. 6.00 (Six) crore or minimum quantity 9000 cum & Structure (Culvert/Bridge/Divider/Retaining wall/Slab) Work of minimum value Tk.8.00 (Eight) crore.
The Tenderer or JVCA Partner outside Bangladesh must satisfy the above mentioned work experience outside Bangladesh.
The tenderer must submit with the tender the above mentioned work certificate form the concerned Executive Engineer/Project Manager/Project Director.
In case of the experience in Roads and Highways Department the attested copy of the requisite certificate for experience as stated above shall be from concerned Executive Engineer/ Project Manger/Project Director of Roads and Highways Department and shall be submitted along with tender.
In case of the experience in an organization other than Roads and Highways Department in Bangladesh, the above mentioned certificate shall be from the concerned Executive Engineer/ Project Manger/Project Director and the same certificate shall also be examined and countersigned by the Executive Engineer, RHD where the Work has been constructed. The Original or attested copy of the above certificate is acceptable.
In the experience as sought above is from outside Bangladesh, the experience certificate of the tenderer shall have to be authenticated by his/her Embassy/High commission Office.
Note : (1) The Works Certificate(s) shall clearly state
(a) Name of Work.
(b) Name of the Contractor.
(c) Location of the Work.
(d) Date of signing the Contract.
(e) Time for Completion of the Work as per Contract Agreement.
(f) Value of the Work as per contract Agreement.
(g) Value of the Work after Completion
(h) Date of Actual Completion.
(i) Quantity of completed Base Type-I item of work
(j) Quantity of completed Carpeting item of work
k) Work certificate shall clearly be stated the Value of work, Quantity of Base Type-I & Carpeting Item of work.
|
15.1(a) The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 10 (eight) years. Years counting backward from the date of publication of IFT.
15.1 (b) The minimum specific experience as a Prime Contractor or Management Contractor in construction of Road Works in a single contract of similar nature, complexity and methods/construction technology successfully completed within the last 5 (five) years (Years counting backward from the date of publication of IFT with a value of at least Tk. 35.00 crore (Thirty five crore) only in single contract. The work (the single contract) must be included with DBS Base/Wearing Course of minimum value Tk. 10.00 (Ten) Crore or minimum quantity 5000 cum, Aggregate Base Type-I Tk. 6.00 (Six) crore or minimum quantity 9000 cum & Structure (Culvert/Bridge/Divider/Retaining wall/Slab) Work of minimum value Tk.8.00 (Eight) crore or minimum quantity 4500.00 cum.
The Tenderer or JVCA Partner outside Bangladesh must satisfy the above mentioned work experience outside Bangladesh.
The tenderer must submit with the tender the above mentioned work certificate form the concerned Executive Engineer/Project Manager/Project Director.
In case of the experience in Roads and Highways Department the attested copy of the requisite certificate for experience as stated above shall be from concerned Executive Engineer/ Project Manger/Project Director of Roads and Highways Department and shall be submitted along with tender.
In case of the experience in an organization other than Roads and Highways Department in Bangladesh, the above mentioned certificate shall be from the concerned Executive Engineer/ Project Manger/Project Director and the same certificate shall also be examined and countersigned by the Executive Engineer, RHD where the Work has been constructed. The Original or attested copy of the above certificate is acceptable.
In the experience as sought above is from outside Bangladesh, the experience certificate of the tenderer shall have to be authenticated by his/her Embassy/High commission Office.
Note : (1) The Works Certificate(s) shall clearly state
(a) Name of Work.
(b) Name of the Contractor.
(c) Location of the Work.
(d) Date of signing the Contract.
(e) Time for Completion of the Work as per Contract Agreement.
(f) Value of the Work as per contract Agreement.
(g) Value of the Work after Completion
(h) Date of Actual Completion.
(i) Quantity of completed Base Type-I item of work
(j) Quantity of completed Carpeting item of work
k) Work certificate shall clearly be stated the Value of work, Quantity of Base Type-I & Carpeting Item of work.
|
| TDS/PDS--D. Tender Preparation--
|
The Tenderer shall submit with its Tender the following additional documents:
(1) Money receipt of purchasing tender document.
(2) Tender security in the form of Pay order, Bank Draft or Bank Guarantee.
(3) Up-to-date Income tax clearance certificate (Attested by first class Gazetted Officer).
(4) VAT Registration & TIN Certificate (Attested by first class Gazetted Officer).
(5) Up-to-date renewed trade license (Attested by first class Gazetted Officer).
(6) Duly Notarised declaration of eligibility of tenderer as per Clause no. 5 of Section 1: Instructions to Tenderers (Attested by first class Gazetted Officer).
(7).Evidence of Annual Construction Turnover (Payment certificate attested by first class Gazetted Officer).
(8) Evidence of availability of Liquid Asset or Working Capital or Credit facility (Bank statement/ Certificate or Loan agreement with a Bank )
(9) List of key personnel as specified in ITT 16.1a.
(10) List of Construction Equipment as specified in ITT 17.1.
(11) JVCA agreement as specified in ITT 18.1, ITT 18.2
(12) Works plan and statement of work method.
(13) Tenderer legal Status & National ID Card.
(14) Power of Attorney for authorizing signatory /Capacity of Signatory.
(15) Value of works underway or committed.
(16) Tenderer shall have their own Asphalt Batching Plant, or in case of highering the plant tenderer must submit an aggrement on non-judicial stamp of Tk. 300.00 with the owenr of the plant.
(17) The Tenderer shall submit the undertaking in the format shown in Section 7 : General Specifications of the Tender Documents.
* If the tenderer Quote Rate more than 10% less or above the tender will not be acceptble as per amendment of PPR 2008.
The tenderer shall have to submit the following information clearly about Past Performance Evaluation and rating matrix for different aspects as follows :
1. Number of court cases filed and won against PE during last 5 years:
(a) No of Cases filed
(b) Cases won
2. Debarred by PE during last 5 years
3. Termination of incomplete contract for poor performance by PE during last 5 years
4. Extension of Time beyond original contract period by PE during last 5 years
5. Imposition of Liquidity Damages (LD) by PE during last 5 years
6. Extension of contracted Defects Liability Period (DLP) by PE during last 5 years
7. Declared bankrupt during last 5 years
Note: Any misinformation/disinformation or hiding information as sought above shall affect the qualification of tenderer.
|
The Tenderer shall submit with its Tender the following additional documents:
(1) Money receipt of purchasing tender document.
(2) Tender security in the form of Pay order, Bank Draft or Bank Guarantee.
(3) Up-to-date Income tax clearance certificate (Attested by first class Gazetted Officer).
(4) VAT Registration & TIN Certificate (Attested by first class Gazetted Officer).
(5) Up-to-date renewed trade license (Attested by first class Gazetted Officer).
(6) Duly Notarised declaration of eligibility of tenderer as per Clause no. 5 of Section 1: Instructions to Tenderers (Attested by first class Gazetted Officer).
(7).Evidence of Annual Construction Turnover (Payment certificate attested by first class Gazetted Officer).
(8) Evidence of availability of Liquid Asset or Working Capital or Credit facility (Bank statement/ Certificate or Loan agreement with a Bank )
(9) List of key personnel as specified in ITT 16.1a.
(10) List of Construction Equipment as specified in ITT 17.1.
(11) JVCA agreement as specified in ITT 18.1, ITT 18.2
(12) Works plan and statement of work method.
(13) Tenderer legal Status & National ID Card.
(14) Power of Attorney for authorizing signatory /Capacity of Signatory.
(15) Value of works underway or committed.
(16) Tenderer shall have their own Asphalt Batching Plant, or in case of highering the plant tenderer must submit an aggrement on non-judicial stamp of Tk. 300.00 with the owenr of the plant.
(17) The Tenderer shall submit the undertaking in the format shown in Section 7 : General Specifications of the Tender Documents.
(18) Incase of Joint Venture (JV) Tenderer's have to mention full name of firm.
(19) Bitumun grad to be used 60/70
(20) Tenderer is required to provide rate analysis if the quoted rate 5% above or below.
* If the tenderer Quote Rate more than 10% less or above the tender will not be acceptble as per amendment of PPR 2008.
The tenderer shall have to submit the following information clearly about Past Performance Evaluation and rating matrix for different aspects as follows :
1. Number of court cases filed and won against PE during last 5 years:
(a) No of Cases filed
(b) Cases won
2. Debarred by PE during last 5 years
3. Termination of incomplete contract for poor performance by PE during last 5 years
4. Extension of Time beyond original contract period by PE during last 5 years
5. Imposition of Liquidity Damages (LD) by PE during last 5 years
6. Extension of contracted Defects Liability Period (DLP) by PE during last 5 years
7. Declared bankrupt during last 5 years
Note: Any misinformation/disinformation or hiding information as sought above shall affect the qualification of tenderer.
|