View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | TDS Missing |
| Field Name | Old Value | New Value | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Eligibility of Consultant | As Per TDS |
As Per TDS |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | The required average annual construction turnover shall be greater than Tk [insert amount] over the last [state number] years.
[ the required average annual construction turn over is recommended to be about twice the estimated annual cash flow for the Contract; however the multiplier may vary from 1.0 to 2.0, the larger the Contract size the lesser the multiplier should be. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate) ; years counting backward from the date of publication of IFT in the newspaper]
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk [state amount]
[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Therefore, the minimum required liquid asset will be Tk 4 Cr., i.e. 3 months cash flow based on the above assumptions.] |
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk. 22,00,000.00 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- |
The minimum capacity shall be:[70%-80% of the official estimated cost]
Where
Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one) |
The minimum capacity shall be:Tk. 56,00,000.00
Where
Note 1: In case the value of N is less than 12 (twelve) months the value of N shall be considered as 01 (one) |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | A Construction Project Manager, Engineer, and other key staff shall have the following qualifications and experience:
[ qualification of an alternative Construction Project Manager may also be requested] |
A Construction Project Manager, Engineer, and other key staff shall have the following qualifications and experience:
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | Tenderer shall own or have proven access to hire or lease of the major construction equipments, in full working order as follows :
[for Tenders where the package contains more than one (1) lot, this qualification requirement may be necessary for each lot in the package, subject to the nature of the control required over each package] |
Tenderer shall own or have proven access to hire or lease of the major construction equipments, in full working order as follows :
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- |
The minimum qualification requirements of Leading Partner and other Partner(s) of a JVCA shall be as follows : |
The minimum qualification requirements of Leading Partner and other Partner(s) of a JVCA shall be as follows : As stated in ITT 19.1 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- |
The value of non-judicial stamp for execution of the Joint Venture agreement shall be Tk [state amount] |
The value of non-judicial stamp for execution of the Joint Venture agreement shall be Tk 300.00 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TDS/PDS--C. Qualification Criteria-- | The Nominated Subcontractor(s) named [insert name(s)] shall execute the following specific components of the proposed Works:
|
The Nominated Subcontractor(s) named [insert name(s)] shall execute the following specific components of the proposed Works:None. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Brief Description of Goods,Works or Service | Construction of additional class room Sarabaria GPS under PEDP4. |
Construction of additional class room Sarabaria GPS under PEDP4. |