View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | ok |
| Field Name | Old Value | New Value |
|---|---|---|
| TDS/PDS--C. Qualification Criteria-- |
The required average annual construction turnover shall be greater than Tk best 5(five) yearsover the last 10 (ten) years.
The minimum amount of liquid assets i.e. banking instrument or working capital or credit facilities or credit lineof theTenderer shall be Tk -Tenderer shall demonstrate the resources sufficient to meet the aggregate of the value for the individual contracts/contractual commitments, in case, participation is more than one package/lot from same procuring entity and other procuring entity(ies). |
The required average annual construction turnover shall be greater than Tk 26.00 lakh best 5(five) yearsover the last 10 (ten) years.
The minimum amount of liquid assets i.e. banking instrument or working capital or credit facilities or credit lineof theTenderer shall be Tk 19.30 lakh -Tenderer shall demonstrate the resources sufficient to meet the aggregate of the value for the individual contracts/contractual commitments, in case, participation is more than one package/lot from same procuring entity and other procuring entity(ies). |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | corri |
| Field Name | Old Value | New Value |
|---|---|---|
| TDS/PDS--C. Qualification Criteria-- | The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be [state number] years. [a minimum of three (3) years would be deemed reasonable; years counting backward from the date of publication of IFT in the newspaper]
The minimum specific experience as a Prime Contractor or Subcontractor or Management Contractor in construction works of at least [state number] contract(s) of similar nature, complexity and methods/construction technology successfully completed within the last [state number] years, each with a value of at least Tk. [state amount].
[the minimum number of contracts will depend upon the size and type of construction work, and the PE should make its own judgement based upon its experience in the sector and construction industry. For example, for large works, it could be one (1) contract of similar nature during the last three (3) years or five (5) years or ten (10) years (whichever appropriate); years counting backward from the date of publication of IFT in the newspaper]
[for Tenders where the package contains more than one (1) lot, this qualification requirements, only when applicable, shall be mentioned separately for each lot in the package] |
The minimum number of years of general experience of the Tenderer in the construction works as Prime Contractor or Subcontractor or Management Contractor shall be 3 years.
A satisfactory completion of similar works of at least Tk 39.00 lakh under max. 4 (four) numbers of contracts over a period of last 10 (ten) years shall be required. |
| TDS/PDS--C. Qualification Criteria-- | The required average annual construction turnover shall be greater than Tk [insert amount] over the last [state number] years.
[ the required average annual construction turn over is recommended to be about twice the estimated annual cash flow for the Contract; however the multiplier may vary from 1.0 to 2.0, the larger the Contract size the lesser the multiplier should be. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate) ; years counting backward from the date of publication of IFT in the newspaper]
The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk [state amount]
[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractorâ??s monthly certificate, allowing time to prepare an invoice, for the Project Managerâ??s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Therefore, the minimum required liquid asset will be Tk 4 Cr., i.e. 3 months cash flow based on the above assumptions.] |
The required average annual construction turnover shall be greater than Tk best 5(five) yearsover the last 10 (ten) years.
The minimum amount of liquid assets i.e. banking instrument or working capital or credit facilities or credit lineof theTenderer shall be Tk -Tenderer shall demonstrate the resources sufficient to meet the aggregate of the value for the individual contracts/contractual commitments, in case, participation is more than one package/lot from same procuring entity and other procuring entity(ies). |
| TDS/PDS--C. Qualification Criteria-- |
The minimum Tender Capacity shall be: :[70%-80% of the official estimated cost]
Where
For Tenders where the package contains more than one (1) Lot, this qualification requirement shall be mentioned separately for each lot in the package] |
The minimum Tender Capacity shall be: : 68.00
Where
For Tenders where the package contains more than one (1) Lot, this qualification requirement shall be mentioned separately for each lot in the package] |