View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 2
|
|
| Amendment / Corrigendum Text : | Correction of PCC Section-B, C, D & F. |
| Field Name | Old Value | New Value |
|---|---|---|
| Eligibility of Consultant | As stated in Tender Document.
As stated in ITT |
As stated in Tender Document.
As stated in ITT |
| PCC--B. Time Control-- |
The Start Date shall be [insert date ] |
The Start Date shall be : As stated in tender notice. |
| PCC--B. Time Control-- |
The Intended Completion Date for the whole of the Works shall be [insert date] |
The Intended Completion Date for the whole of the Works shall be : As stated in tender notice. |
| PCC--B. Time Control-- |
The Contractor shall submit a Programme for the Works within [insert days] days of signing the Contract. |
The Contractor shall submit a Programme for the Works within Seven (07) days of signing the Contract. |
| PCC--C. Quality Control-- |
The Defects Liability Period is [state months] |
The Defects Liability Period is twelve (12) months. |
| PCC--D. Cost Control-- |
The following additional events shall also be the Compensation Events: |
The following additional events shall also be the Compensation Events :
If the contract is terminated following the fundamental breach of contract by the contractor
(ii) The Assessed Compensation as recommended by the Compensation Assessment Committee shall be recoverable as instructed in GCC clause 38.
(iv) The Procuring Entity/Project Manager shall however proceed to complete the remaining work engaging new contractor. |
| PCC--D. Cost Control-- | The proportion of payments to be retained is [insert percent] percent. |
The proportion of payments to be retained is five(5) percent. |
| PCC--D. Cost Control-- |
The amount of Liquidated Damages or in other words Delay Damages is [insert percentage] percent of final Contract price of the uncompleted Works or any part there of itâ??s per day of delay. |
The amount of Liquidated Damages or in other words Delay Damages is 0.05 percent of final Contract price of the uncompleted Works or any part there of it’s per day of delay. |
| PCC--D. Cost Control-- |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is [insert percentage] percent of the final Contract price of the whole of the Works. |
The maximum amount of Liquidated Damages for the uncompleted Works or any part thereof is ten (10) percent of the final Contract price of the whole of the Works. |
| PCC--F. Termination-- | The percentage to apply to the contract value of the works not completed, representing the Procuring Entityâ??s additional cost for completing the uncompleted Works, is [state percentage] percent.
[ usually between ten (10) to twenty (20) percent depending on the nature of the Works] |
The Percentage to apply to the contract value of the works not completed representing the Procuring Entity’s additional cost for completing the uncompleted works, is compensation assessed as mentioned in PCC 28.f |
| PCC--H. Disputes and Settlement-- |
The arbitration shall be conducted in the place mentioned below; |
The arbitration shall be conducted in the place mentioned below; |
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | Amendment for Tender Notice. |
| Field Name | Old Value | New Value |
|---|---|---|
| Eligibility of Consultant | As stated in Tender Document. |
As stated in Tender Document.
As stated in ITT |