| Field Name |
Old Value |
New Value |
| Eligibility of Consultant
|
1. Tenderer must be registered on e-GP Portal with a valid trade license, TIN Certificate.
2. Tenderer must submit similar nature work certificate,annual construction turnover
certificate and liquid assets certificate 3. Payment will be made after availability of fund. 4.
Any individual Tender/Bangladeshi Tenderer(s)/firm(s) who fulfill the qualification(s) criteria
stipulated in the Tender Document PPA-2006 and PPR-2008. 5. Tenderer must submit line
of credit certificate in PW3-7 prescribed format which is to be uploaded in section
8.Strictly, Credit commitment(s) substantiated by any scheduled bank of Bangladesh in the
specified format (PW3-7) without alteration, issued not earlier than 28 days prior to the day
of the original deadline for submission of the tender will be accepted. The format also
uploaded at Section 8 of the Tender Document of this tender. 6. All the
information,clarification and documents submitted by the tenderer must comply with
declaration given. 7. Tenderer shall own or have proven access to hire or lease of the
major construction equpments, in full working order (required documents must be
submitted).8. Work Order will be issued after getting approval from competant authority.
|
1. Tenderer must be registered on e-GP Portal with a valid trade license, TIN Certificate.
2. Tenderer must submit similar nature work certificate,annual construction turnover
certificate and liquid assets certificate 3. Payment will be made after availability of fund. 4.
Any individual Tender/Bangladeshi Tenderer(s)/firm(s) who fulfill the qualification(s) criteria
stipulated in the Tender Document PPA-2006 and PPR-2008. 5. Tenderer must submit line
of credit certificate in PW3-7 prescribed format which is to be uploaded in section
8.Strictly, Credit commitment(s) substantiated by any scheduled bank of Bangladesh in the
specified format (PW3-7) without alteration, issued not earlier than 28 days prior to the day
of the original deadline for submission of the tender will be accepted. The format also
uploaded at Section 8 of the Tender Document of this tender. 6. All the
information,clarification and documents submitted by the tenderer must comply with
declaration given. 7. Tenderer shall own or have proven access to hire or lease of the
major construction equpments, in full working order (required documents must be
submitted).8. Work Order will be issued after getting approval from competant authority.
|
| PCC 1. Definitions(rr)Works
|
| Works |
|---|
| Protective Work along the Left Bank of Madhumati River from KM 0.300 to KM 0.700 = 400.00 M at West Salamatpur in C/W " Bank Protective works along the left bank of Madhumati River to Protect the Connecting road to Shahid Bir Shresta Munshi Abdur Rouf Smriti Museum including other areas" in upzallia- Madhukhali, District- Faridpur Under Faridpur O & M Division, BWDB, Faridpur During the FY 2023-24 & 2024-25 | |
| Works |
|---|
| Protective Work along the Left Bank of Madhumati River from KM 0.300 to KM 0.700 = 400.00 M at West Salamatpur in C/W " Bank Protective works along the left bank of Madhumati River to Protect the Connecting road to Shahid Bir Shresta Munshi Abdur Rouf Smriti Museum including other areas and Dredging Project" in upzallia- Madhukhali, District- Faridpur Under Faridpur O & M Division, BWDB, Faridpur During the FY 2023-24 & 2024-25 | |
| PCC 13. Possession of the Site13.1 Possession of the Site
|
| Name of the Parts of Works | Possession Dates | | Protective Work along the Left Bank of Madhumati River from KM 0.300 to KM 0.700 = 400.00 M at West Salamatpur in C/W " Bank Protective works along the left bank of Madhumati River to Protect the Connecting road to Shahid Bir Shresta Munshi Abdur Rouf Smriti Museum including other areas" in upzallia- Madhukhali, District- Faridpur Under Faridpur O & M Division, BWDB, Faridpur During the FY 2023-24 & 2024-25 | 2023-12-03 | |
| Name of the Parts of Works | Possession Dates | | Protective Work along the Left Bank of Madhumati River from KM 0.300 to KM 0.700 = 400.00 M at West Salamatpur in C/W " Bank Protective works along the left bank of Madhumati River to Protect the Connecting road to Shahid Bir Shresta Munshi Abdur Rouf Smriti Museum including other areas and Dredging Project" in upzallia- Madhukhali, District- Faridpur Under Faridpur O & M Division, BWDB, Faridpur During the FY 2023-24 & 2024-25 | 2023-12-03 | |
| PCC 37. Insurance37.1 Insurance
|
| The maximum deductible for insurance of the Works and of Plant and Materials | The minimum cover for insurance of the Works and of Plant and Materials | The maximum deductible for insurance of Equipment | The minimum cover for loss or damage to Equipment | The maximum deductible for insurance of other property | The minimum cover for insurance of other property | | 0.000 | 0.000 | 0.000 | 0.000 | 0.000 | 0.000 | The minimum cover for personal injury or death insurance: (i) for the Contractor’s employees is as per the law and common practice in Bangladesh. (ii) and for third parties is as per the law and common practice in Bangladesh. | |
| The maximum deductible for insurance of the Works and of Plant and Materials | The minimum cover for insurance of the Works and of Plant and Materials | The maximum deductible for insurance of Equipment | The minimum cover for loss or damage to Equipment | The maximum deductible for insurance of other property | The minimum cover for insurance of other property | | 21500000 | 215000000 | 500000 | 5000000 | 2000000 | 20000000 | The minimum cover for personal injury or death insurance: (i) for the Contractor’s employees is as per the law and common practice in Bangladesh. (ii) and for third parties is as per the law and common practice in Bangladesh. | |
| Brief Description of Goods,Works or Service
|
Protective Work along the Left Bank of Madhumati River from KM 0.300 to KM 0.700 = 400.00 M at West Salamatpur in C/W " Bank Protective works along the left bank of Madhumati River to Protect the Connecting road to Shahid Bir Shresta Munshi Abdur Rouf Smriti Museum including other areas" in upzallia- Madhukhali, District- Faridpur Under Faridpur O & M Division, BWDB, Faridpur During the FY 2023-24 & 2024-25
|
Protective Work along the Left Bank of Madhumati River from KM 0.300 to KM 0.700 = 400.00 M at West Salamatpur in C/W " Bank Protective works along the left bank of Madhumati River to Protect the Connecting road to Shahid Bir Shresta Munshi Abdur Rouf Smriti Museum including other areas and Dredging Project" in upzallia- Madhukhali, District- Faridpur Under Faridpur O & M Division, BWDB, Faridpur During the FY 2023-24 & 2024-25
|