View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | To correct the official cost estimate. |
| Field Name | Old Value | New Value |
|---|---|---|
| Document last selling date & time | 30/11/2023 12:30 | 07/12/2023 12:30 |
| Eligibility of Consultant |
(A) The Minimum Number of Years of General Experience of The Tenderer in Civil Works Shall be 5 years. (B) (i) The minimum specific experience as a Contractor in successful completion of atleast 1(one) number of Building Construction works including Electrification Works of Tk 80.00(Eighty) lakh in a single contract in Government /Semi-Government/ Autonomous Organization of Bangladesh during last 5 (Five) years. (ii) In Case of Work Done Under PWD The Certifying and Authenticating Authority Shouldbe The Concerned Executive Engineer and In Case of Works Under anyGovernment/Semi-Government/ Autonomous Organization other than PWD The Certifying Authority shall be an Officer not Below The Rank of Executive Engineer and The Same Duly Verified by The Concerned Executive Engineer of PWD of That District Under Whose Jurisdiction The Work been Done. (C) The Tenderer Shall have a Minimum Average Annual Construction Turnover During Last 5 Financial years of Tk 3.15 Crore. Payment Certificates for Contracts in Progress orCompleted Under Public Sector Must be Submitted along with Tender in Support ofConstruction Turnover. (D) The Tenderer must have a Minimum Liquid Assets/Cash flow capacity/Creditfacilities/Credit Line Tk. 55 (Fifty five) lakh Only and Must be Certified Within 28 Days up to TheLast Date of Lodgment of The Tender and must be followed by the appropriate format(PW3-7). (E) The Tender Must Possess: (i) Up to date Income Tax Clearance Certificate. (ii) Valid VAT Registration Certificate and clearance certificate (iii) Up to date Trade License. (iv) Up to date ABC Category Contractorship and Supervisory License from Electricity Licensing Board of Bangladesh. |
(A) The Minimum Number of Years of General Experience of The Tenderer in Civil Works Shall be 5 years. (B) (i) The minimum specific experience as a Contractor in successful completion of atleast 1(one) number of Building Construction works including Electrification Works of Tk 80.00(Eighty) lakh in a single contract in Government /Semi-Government/ Autonomous Organization of Bangladesh during last 5 (Five) years. (ii) In Case of Work Done Under PWD The Certifying and Authenticating Authority Shouldbe The Concerned Executive Engineer and In Case of Works Under anyGovernment/Semi-Government/ Autonomous Organization other than PWD The Certifying Authority shall be an Officer not Below The Rank of Executive Engineer and The Same Duly Verified by The Concerned Executive Engineer of PWD of That District Under Whose Jurisdiction The Work been Done. (C) The Tenderer Shall have a Minimum Average Annual Construction Turnover During Last 5 Financial years of Tk 3.15 Crore. Payment Certificates for Contracts in Progress orCompleted Under Public Sector Must be Submitted along with Tender in Support ofConstruction Turnover. (D) The Tenderer must have a Minimum Liquid Assets/Cash flow capacity/Creditfacilities/Credit Line Tk. 55 (Fifty five) lakh Only and Must be Certified Within 28 Days up to TheLast Date of Lodgment of The Tender and must be followed by the appropriate format(PW3-7). (E) The Tender Must Possess: (i) Up to date Income Tax Clearance Certificate. (ii) Valid VAT Registration Certificate and clearance certificate (iii) Up to date Trade License.
(iv) Up to date ABC Category Contractorship and Supervisory License from Electricity Licensing Board of Bangladesh. |
| Opening Date & Time | 30/11/2023 13:00 | 07/12/2023 13:00 |
| Last date & time for Tender/Proposal Security Submission | 30/11/2023 12:50 | 07/12/2023 12:50 |
| Closing Date & Time | 30/11/2023 13:00 | 07/12/2023 13:00 |
| Brief Description of Goods,Works or Service | Construction of 1(One) storied Armory Building with 2(Two) storied Foundation for Bangladesh Ansar Battalion one at Feni district under the project titled "Construction of Armory Building for Ansar & VDP (40 Nos in 1st Phase)". Financial year- 2023-2024. |
Construction of 1(One) storied Armory Building with 2(Two) storied Foundation for Bangladesh Ansar Battalion one at Feni district under the project titled "Construction of Armory Building for Ansar & VDP (40 Nos in 1st Phase)". Financial year- 2023-2024. |