View IFT /PQ / REOI / RFP / PPS Notice Details
|
Amendment / Corrigendum No. : 1
|
|
| Amendment / Corrigendum Text : | TDS correction |
| Field Name | Old Value | New Value | ||||
|---|---|---|---|---|---|---|
| Eligibility of Consultant | As per ITT & TDS |
As per ITT & TDS |
||||
| TDS/PDS--A. General-- |
|
|
||||
| TDS/PDS--B. Tender Document-- | Allowed to post clarification till [Date and Time] |
Allowed to post clarification N/A |
||||
| TDS/PDS--C. Qualification Criteria-- | The minimum amount of liquid assets or working capital or credit facilities of the Tenderer shall be Tk [state amount]
[usually the required liquid asset is the equivalent of 2-6 months payment flow at the average construction rate (straight line distribution), accessible or available after taking into account the financial requirements of existing commitments. The actual period will depend on the speed with which the PE will pay the Contractor’s monthly certificate, allowing time to prepare an invoice, for the Project Manager’s time to certify it, and at least one month contingency for preparing the cheque and making actual payment.
Therefore, the minimum required liquid asset will be Tk. 6 lakh, i.e. 3 months cash flow based on the above assumptions.] |
|
||||
| TDS/PDS--C. Qualification Criteria-- |
The minimum capacity shall be:[70%-80% of the official estimated cost]
Where
For Tenders where the package contains more than one (1) Lot, this qualification requirement shall be mentioned separately for each lot in the package |
The minimum capacity shall be: 60.00 Lac BDT. |
||||
| TDS/PDS--C. Qualification Criteria-- | The required average annual construction turnover shall be greater than Tk [insert amount] over the last [state number] years.
[ the required average annual construction turn over is recommended to be about less than or equal to the estimated annual cash flow for the Contract; however the multiplier may vary from 0.30 to 1.00 ; [ years counting backward from the date of publication of IFT in the newspaper. The period may be best three (3) years in the last five (5) years or best five (5) years in the last ten (10) years (as appropriate)] |
The required average annual construction turnover shall be greater than Tk. 25.00 Lac over the last 05 (Five) years. [Year’s counting backward from the date of publication of IFT in the newspaper] Payment certificates for contracts in progress or completed under public sector must be submitted along with Tender in support of average annual construction turnover. |
||||
| TDS/PDS--C. Qualification Criteria-- | A satisfactory completion of similar works of at least Tk [insert amount] under [state number] of contract(s) over a period of [state number] years shall be required. [the minimum value of the similar works under a single or multiple number of contract(s) is recommended to be between 50 and 75 percent of the estimated cost, rounded off to nearest Taka thousand, of the proposed work. years counting backward from the date of publication of IFT in the newspaper]
[for Tenders where the package contains more than one (1) lot, this qualification requirements, shall be mentioned separately for each lot in the package] |
The minimum specific experience in similar works shall be at least Tk. 21.00 Lakh; under 01 (one) no. of contract; completed successfully within 01 year, over a period of last 03 ii) In case of the work done under any Govt/Semi Govt./Autonomous Bodies other than PWD the certifying authority shall be an officer not below the rank of Executive Engineer and the same certificate duly verified by the concern Executive Engineer of PWD of that district under whose jurisdiction the work has been done. iii) Self work or non-tendered work or work under Private Organization will not be entertained for the work experience. |
||||
| TDS/PDS--D. Tender Preparation-- | Tenderer shall submit with its Tender, the following additional documents: |
The Tenderer must submit with tender: (i) Up-to-date valid Trade Licence. (ii) Up-to-date Income Tax clearance certificate. (iii)Valid VAT registration certificate. (iv) Up-to-date valid ABC/BC Electrical Supervisory Licence from Electrical Licensing Board. (v) Valid BIN Certificate (vi) Site visit report with the picture of the site from the representative of PE. vii) Methodology of works with bar/Gantt chart viii) All other required qualifications, special terms & conditions of the tender are shown in the ITT, GCC, & Tender Data Sheet (TDS) & Tender Documents |
||||
| Brief Description of Goods,Works or Service | Ancillary electrical work including changing of underground service cable at Government Homoeopathic Medical College Hospital, Mirpur, Dhaka. . |
Ancillary electrical work including changing of underground service cable at Government Homoeopathic Medical College Hospital, Mirpur, Dhaka. . |